SPCB Written Question · S1W-22109 · Session 1
Further to his answer to question S1W-12273 on 25 January 2001, whether each of the works packages listed has been completed within the est…
The question
To ask the Presiding Officer, further to his answer to question S1W-12273 on 25 January 2001, whether each of the works packages listed has been completed within the estimated contract duration stated and, if not, when it is estimated that the works in respect of each contract will be completed
The answer
All of the works packages listed in the answer to question S1W-12273 on 25 January 2001 were completed within the estimated contract duration with the exception of Tower Cranes, Queensberry House Scaffolding, Lifts (whole site) and Queensberry House Demolition/Reconstruction which are expected to run as previously estimated for a further 11 months, six months, 14 months and five months respectively.