Parliament Workbench
Data: Motions & questions to 26 Nov 2026

SPCB Written Question · S1W-12273 · Session 1

What capital contracts have been let to date in relation to the Holyrood Project, indicating in each case the successful tenderer and the t…

Answered Asked by Murray Tosh Con Lodged 4 Jan 2001

The question

To ask the Presiding Officer what capital contracts have been let to date in relation to the Holyrood Project, indicating in each case the successful tenderer and the timescale for each works package.

The answer

Answered by David Steel on 22 Jan 2001 · 18 days after it was lodged, on time

The information is as follows:Works Package | Contractor | Estimated contract duration
Retention West Basement | Amec Civil Engineering Ltd | 4 months
Excavation West | Barr Ltd | 3 months
Well Probing | Wimtec Environmental Ltd | 11 months
Piling West Basement | Amec Civil Engineering Ltd | 3 months
Substructure West Basement | O'Rourke Civil Engineering Ltd | 5 months
Tower Cranes | Select Plant Hire Ltd | 20 months
Asbestos/Pigeon Dropping Removal | Chamic Industrial Services Ltd | 5 months
Well Drilling | Richies Ltd | 5 months
QH Scaffolding | Lyndon Scaffolding PLC | 19 months
MSP Frame | O'Rourke Civil Engineering Ltd | 10 months
Electrical Enabling Works | James Scott Ltd | 10 months
Lifts Whole Site | Otis Limited | 24 months
QH Demolition/Reconstruction | Ballast Construction Scotland Ltd | 17 months
Substructure East Basement | O'Rourke Civil Engineering Limited | 7 months

In the Official Report

No contribution in the Official Report cites S1W-12273 by reference.