Further to the answer to question S1W-12112 by Sarah Boyack on 18 January 2001, whether the assignation to Skye Bridge Limited (SBL) of the…

Answered Asked by Irene McGugan SNP Lodged 13 Feb 2001

The question

To ask the Scottish Executive, further to the answer to question S1W-12112 by Sarah Boyack on 18 January 2001, whether the assignation to Skye Bridge Limited (SBL) of the right to collect tolls on the Skye Bridge and the operation of the bridge by Miller Dywidag on SBL's behalf means that Miller Civil Engineering is authorised to charge tolls on the A87.

The answer

Answered by Sarah Boyack on 20 Mar 2001 · 35 days after it was lodged, 21 days after it was due

Miller Civil Engineering Ltd does not have the authority to charge tolls on the A87 in its own right. As I made clear in my answers to S1W-10325 on 5 December and S1W-12112 on 18 January, the right to collect tolls has been assigned to Skye Bridge Limited while the operation of the bridge is carried out on SBL's behalf by the joint venture Miller Dywidag.