Whether Miller Civil Engineering Limited is authorised to charge tolls on the A87.

Answered Asked by Irene McGugan SNP Lodged 19 Dec 2000

The question

To ask the Scottish Executive whether Miller Civil Engineering Limited is authorised to charge tolls on the A87.

The answer

Answered by Sarah Boyack on 18 Jan 2001 · 30 days after it was lodged, 15 days after it was due

As I made clear in my letter of 27 October to the member, the right to collect tolls on the Skye Bridge has been assigned to Skye Bridge Limited. The operation and maintenance of the bridge is carried out on SBL's behalf by Miller Dywidag, a joint venture between Miller Civil Engineering Limited and Dyckerhoff & Widmann AG.