Written Question · S1W-12507 · Session 1
Further to the answer to question S1W-6862 on 22 June 2000 by Sarah Boyack, whether work in relation to the Kingston Bridge Phase 1 Strengt…
The question
To ask the Scottish Executive, further to the answer to question S1W-6862 on 22 June 2000 by Sarah Boyack, whether work in relation to the Kingston Bridge Phase 1 Strengthening contract has now been completed and when existing traffic restrictions on the bridge are expected to be lifted.
The answer
All major strengthening operations have been completed and the remaining minor works such as landscaping and site clearance are programmed for completion by April.Revised traffic management arrangements are in hand, including re-opening the traffic lanes that are currently closed, and implementation is expected by the end of February.
In the Official Report
No contribution in the Official Report cites S1W-12507 by reference.