Written Question · S1W-06862 · Session 1

Whether the proposed expenditure on the Kingston Bridge in Glasgow, noted in page 95 of Investing in You, will allow the complete re-openin…

Answered Asked by Murray Tosh Con Lodged 15 May 2000

The question

To ask the Scottish Executive whether the proposed expenditure on the Kingston Bridge in Glasgow, noted in page 95 of Investing in You, will allow the complete re-opening of the bridge.

The answer

Answered by Sarah Boyack on 22 Jun 2000 · 38 days after it was lodged, 23 days after it was due

Following the completion of the Kingston Bridge Phase 1 Strengthening contract in December 2000 the existing traffic restrictions on the bridge will no longer be required.The ongoing programme of refurbishment works to the complex of approach viaducts and entry and exit ramps to Kingston Bridge will require separate traffic management schemes to allow the works to proceed safely.