SPCB Written Question · S1W-06520 · Session 1
Further to his answer to question S1W-5936 on 6 April 2000, what alternative solutions were considered for the construction of foundations …
The question
To ask the Presiding Officer, further to his answer to question S1W-5936 on 6 April 2000, what alternative solutions were considered for the construction of foundations for the Holyrood complex and what the comparative costs of each solution were.
The answer
The ground conditions on the Holyrood site together with the physical properties of the proposed Parliament building dictate the types of foundations which can be used. The Structural Engineer's professional judgement was that the most suitable and cost-effective solution for the Holyrood site was to use a combination of "piles" and "pads" foundation systems.
In the Official Report
No contribution in the Official Report cites S1W-06520 by reference.