DCC Richardson, in your letter to the sub-committee, you state clearly that there have been no additional costs as a result of the contract variation. Is that correct?
Official Report · Committee
i6 Programme
Speakers
Showing Kevin Stewart only · show everyone- Deputy Chief Constable Richardson 14
- Margaret Mitchell Con 12
- Chief Superintendent Macpherson 11
- Kevin Stewart SNP 9
- John Finnie Ind 6
- Alison McInnes LD 5
- Deputy Chief Constable Neil Richardson Police Scotland 1
- Chief Superintendent Hamish Macpherson Police Scotland 1
- Tom McMahon Scottish Police Authority 1
Kevin Stewart’s contributions
9 contributionsWe discussed the contract variation in some depth the last time you were here to give evidence on i6. What changes have been made to the timetable for complete delivery of the i6 system?
I do have an interest. You are saying that the contract variation that was put in place after your initial difficulties with the supplier has led to no additional cost and that the system will still be delivered on time. Yet, at the same time, you are saying that time changes have been built in to ensure delivery by September 2016. I am interested in how there can be changes in that timescale from the original contract but you can still meet the operational deadline of September 2016. If you could explain that, it would be extremely useful.
Could you explain that different approach? Does having a data store mean that the data does not go into the i6 system initially? It would be helpful for us to know, in layman’s terms, what you mean by that.
That sounds a lot more logical than your original proposal. Why was it not decided to move in that direction during the initial stages?
Thank you for that. We have previously taken an interest in the milestones that you have set out, and again we have some indication of them in the information that we have in front of us today. I note from your letter to the committee, DCC Richardson, talk of “milestone 5B”. As I have said to you guys before, I have some experience of major IT projects, and when numbers start having letters added to them, which usually means new milestones, it has previously indicated to me that there may be some difficulties.
Was there previously no milestone 5B? What is 5B? What was 5A? I take it that there will have been a 5A. Are we likely to see changes to the other milestones, too?
It would also be useful for us to know what those elements were. It is always useful for us to get things into context. What were the difficulties?
Okay. Finally, do you foresee difficulties that might lead to further contract variation or changes to the milestones before i6 goes live and the system becomes operational?
I would never expect anyone who is dealing with an information technology contract to tell us that it is plain sailing. I have dealt with a number of IT contracts, and they are never plain sailing.
However, the committee is concerned about further contract variation. There was a contract variation quite early in the programme. It did not cost the public purse any more money—thank God for that. I am keen to know, as I think other members are, whether there is likely to be another contract variation.
I am always rather perplexed that the original tenders in IT contracts sometimes do not seem to allow for the flexibility that is likely to be needed during the construction of the programme.
Do you foresee any contract variation in the near future?
In this meeting
Everything on 8 Jan 2015 →- 13:15 Temporary Convener Procedure · 3
- 13:15 Decision on Taking Business in Private Procedure · 1
- 13:15 i6 Programme Committee business · 60
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.