First, let me say that I am very pleased with where we are at the moment. We have managed to complete the design to our satisfaction, which is a major milestone in its own right. The design is directly in line with the principles of retaining the functions and with the terms of the contract, meeting our requirements. That has been completed.
However, the reality is that, for any major programme that runs for a number of years and has the complexities that the i6 programme has, delivery never follows a linear path.
I can tell you that our principles have remained consistent, that we have an end date that has not altered since the contract variation, that our costs remain constant and that the functionality that we expect to be delivered and which was in the business case is exactly what has been designed.
That said, there have been variations along the route, as members know. There has been some slippage and some things have changed in nature. That is the reality of programme delivery.
Now that the design is complete and elements of the engine—to use a mechanical metaphor—have been constructed, we are at the stage of putting those elements together to see whether the engine runs smoothly.
In any such process, there will be issues that we did not expect and adjustments will require to be made. I can say with confidence that I will continue to hold true to the principles to which I have held up to now. However, in all probability there will be things to which we need to adapt and adjust.
I have no reason to think that that will be problematic or will lead to another contract variation, but it would be wrong to give you a sense that, now that we have reached this point, everything will be plain sailing all the way through. That is not the case. This is an incredibly difficult and challenging programme, and I imagine that it will continue to be so. However, at the moment we are in a good place.