Hugh Henry Lab The Convener · Renfrewshire South
link

The next item is evidence on the section 23 report “Preparations for the implementation of the Scotland Act 2012”. Caroline Gardner, the Auditor General for Scotland, is here today and is joined by Gordon Smail, senior manager, Rebecca Seidel, project manager, and Mark Taylor, assistant director, who are all from Audit Scotland.

I invite the Auditor General to make some comments.

Caroline Gardner Auditor General for Scotland
link

The report that I am bringing to the committee today considers the Scottish Government’s progress in preparing for the financial measures in the Scotland Act 2012, including the introduction of the two new devolved taxes, new borrowing and cash management powers, and a Scottish rate of income tax.

Before I set out what we found, I would like to highlight two important points. First, establishing the arrangements for the new powers is a large and complex task, which includes developing an overall approach to devolved tax and the legislative framework to implement it. The Scottish Government has successfully developed a legislative framework for the devolved taxes, through three bills that have been passed by the Scottish Parliament. Secondly, the changes that come into force next year through the Scotland Act 2012 are even more significant when set into the context of the recent report by the Smith commission and the heads of agreement on further financial powers for the Scottish Parliament.

My report focuses on the preparations for administering the two new devolved taxes, land and buildings transaction tax and Scottish landfill tax, which come into effect from April 2015. It also provides some initial observations on progress towards introducing the Scottish rate of income tax. It is important to note that the audit was carried out while preparations for the implementation of the 2012 act were on-going. Given the scale and importance of the changes, I felt that it was important to review progress at this stage, before the new powers come into effect next year. The report acknowledges that substantial activity continues within the Scottish Government.

I will briefly summarise my findings under three headings. First, on the devolved taxes, we found that the Scottish Government has established clear structures for managing the set-up of the new tax authority, Revenue Scotland, and now has well-developed plans for implementing the devolved taxes. However, the staff needed to manage the overall programme were not in place early enough and there were also delays in procuring the Information Technology system to collect and administer the devolved taxes. That has reduced the time available to develop the IT system and to appoint staff to Revenue Scotland’s operational team. As a result, there is an increased risk that the IT system may not be fully operational by 1 April and that Revenue Scotland may not have the required expertise fully in place to manage the devolved taxes effectively when they come into force. That could result in tax payments taking longer to process and lead to an increase in processing costs.

To be clear, I am not saying that nothing will be ready in time; I am saying that there is more risk of things not being fully in place, resulting in the need for short-term alternative arrangements, which has potential cost and performance implications. Revenue Scotland is fully aware of those issues and is taking steps to manage them.

The report makes some short-term recommendations for Revenue Scotland. In particular, we would like to see it closely monitoring the development of the IT system and recruitment to its operational team. That will help Revenue Scotland to decide whether to implement its contingency plans to ensure that it is in a position to manage the devolved taxes effectively from April 2015.

Secondly, we found that the Scottish Government is working closely with HM Revenue and Customs to prepare for the introduction of the Scottish rate of income tax in April 2016. We have highlighted the fact that the Scottish Government needs to ensure that it has enough appropriately skilled people in place to support the successful implementation of the new responsibilities in 2016.

Finally, we found that the Scottish Government is working to incorporate the financial aspects of the Scotland Act 2012 powers in its financial management arrangements. The new financial powers that the 2012 act introduces, and the prospect of further powers following the Smith commission’s report, have significant implications for Scotland’s public finances. All of that makes the need for comprehensive, transparent, reliable and timely financial reporting even more important. I plan to publish an update report on the progress that the Scottish Government is making on developing its financial reporting early next year, and will continue to keep this area under close review.

As always, my colleagues and I are happy to answer the committee’s questions.

Hugh Henry Lab The Convener · Renfrewshire South
link

We should not underestimate some of the complexities that are involved in setting up a completely new tax collection system, and I suppose that we should not underestimate the historic and political significance of doing so, particularly when we consider what lies ahead. We need to get this right. We need to prove that the Scottish Government and the Scottish Parliament are competent with regard to handling tax collection.

Would you say that your report is dated, or does it have continued relevance?

Caroline Gardner Auditor General for Scotland
link

As we say in the report, the audit work on which the report is based was completed in early November. We had been looking at the matter throughout 2014, and the team can give you more detail about that. With any report, there comes a point at which we have to draw a line, draw our conclusions and go into the process of agreeing it for factual accuracy. Therefore, as of early November, the report is fully up to date. In these circumstances, we know that Revenue Scotland and the Government have been working hard since then to overcome some of the problems that are identified in the report. I am sure that they will be able to report to you on the progress that they have made.

Hugh Henry Lab The Convener · Renfrewshire South
link

You completed your report in early November, and you published it in early December. The normal process is that you give a private copy to those concerned so that they can make private comments—in this case, presumably, the Scottish Government and Revenue Scotland. Is that correct?

Caroline Gardner Auditor General for Scotland
link

Yes. We always ensure that our reports are agreed for factual accuracy to avoid this committee having to arbitrate in disagreements between us and the people we are auditing. The team will keep me straight, but I think that, in this case, the report was agreed for factual accuracy fully with the Scottish Government and Revenue Scotland, and sections were cleared with the Scottish Environment Protection Agency, Registers of Scotland and the Scottish Fiscal Commission.

Hugh Henry Lab The Convener · Renfrewshire South
link

So, between early November and 11 December, those concerned had the opportunity to challenge the accuracy of anything that you said and say whether it gave a wrong interpretation or analysis. Was the wording of the final report challenged by any of those concerned?

Caroline Gardner Auditor General for Scotland
link

It is normal for us to make minor changes to the wording to ensure that we are fully reflecting the situation at the point at which the report is agreed. That was the case with this report, too.

Hugh Henry Lab The Convener · Renfrewshire South
link

However, when you reached that final wording, there was no further challenge to those words.

Caroline Gardner Auditor General for Scotland
link

No. However, it is important to distinguish between factual accuracy and the conclusions that I draw from those facts. The factual accuracy of the report was fully agreed.

Hugh Henry Lab The Convener · Renfrewshire South
link

Would you say that your comments about readiness and the fact that there was a risk that the full IT system might not be in place in time were positive comments, negative comments or comments of concern? How would you assess the readiness of the IT system at that point in terms of red, green or amber?

Caroline Gardner Auditor General for Scotland
link

As we say in the report, at that point the progress that had been made on developing and testing the IT system and on appointing the staff who will be needed to administer the new taxes was behind where the Scottish Government and Revenue Scotland had planned it to be. We know that a significant amount of work is going on to remedy those delays, and the Government has told us that it is confident that things will be in place on 1 April. That is why I have reported in the terms that I have and have said that there is an increased risk that things might not be fully in place, although I have reflected the fact that contingency plans are in place to ensure that the taxes can be collected on1 April.

Hugh Henry Lab The Convener · Renfrewshire South
link

Things are behind schedule, progress is not being made and there is a risk—if I asked you to assess those facts as being either positive or negative, how would you assess them?

Caroline Gardner Auditor General for Scotland
link

It is clear that the Government and Revenue Scotland would prefer to have been able to fulfil the plans as they were originally set out. We all want to see the new taxes working on 31 March. As I said in my introductory remarks, however, I am not saying at this point that it will be impossible to collect them; I am simply saying that there is a risk that contingency plans will need to be put in place and that doing so could have cost and performance implications.

Hugh Henry Lab The Convener · Renfrewshire South
link

Can you say to the committee this morning that, on the date that you produced your report and sent it to the parties concerned, you had nothing negative to comment on—that it was all positive?

Caroline Gardner Auditor General for Scotland
link

No. As my report says, I think that there is an increased risk that the system will not be fully in place as planned on 1 April, but I am certainly not saying that the Government and Revenue Scotland will not be in a position to collect the taxes at that point.

Hugh Henry Lab The Convener · Renfrewshire South
link

At the point that you produced the report, therefore, there were some concerns. At that point, you were worried that there was a lot of work to be done. Would it be fair to say that things were not necessarily on track at that time?

Caroline Gardner Auditor General for Scotland
link

It might be helpful for me to refer the committee to exhibit 3 on page 14 of the report, which shows the progress made in implementing the IT system to deliver devolved taxes. On the left-hand side you can see what the Government originally planned, and on the right-hand side you can see what happened in practice. It is clear from that that progress was slower than planned.

As we say in the report, as a result of those delays, Revenue Scotland and the Government have been developing contingency plans that, first, they hope they will not need to use, but, secondly, they believe will be able to deliver the devolved taxes on 1 April if needed.

Hugh Henry Lab The Convener · Renfrewshire South
link

If there was nothing negative to report between early November and when your report was published, how can you say in your report that the delays have increased the risk that the IT system may not be fully functioning by 1 April, and that Revenue Scotland will not have the required operational expertise in place by then? Either what you say in the report is wrong, or the statement that there is nothing negative to report is wrong. Which would it be?

Caroline Gardner Auditor General for Scotland
link

What I need to make clear is that the audit work was completed in early November. I do not have evidence that I can bring to the committee in the way that I normally would about what has happened since then. You may well want to explore that with your next panel of witnesses, but my evidence tells you that, as at the beginning of November, those delays had materialised and they had led to an increased risk.

Hugh Henry Lab The Convener · Renfrewshire South
link

Between that point in November and the publication of your report, did none of the agencies or organisations concerned come back to you with further evidence to say that events had changed and everything was back on track and fully functioning? Have they accepted, after comment, the details of your report?

Caroline Gardner Auditor General for Scotland
link

They accept that the report was factually accurate as at the date that we sent it to them for clearance.

Mary Scanlon Con Highlands and Islands
link

I will follow that line of questioning for a moment.

Between the first week in November and publication of the Audit Scotland report on 11 December, we had Eleanor Emberson and John King speak to the Finance Committee. Eleanor Emberson said:

“We have had small numbers of amber indicators out of two dozen”

but

“we have been working hard to turn ... them back to green.”

She also said:

“We have nothing at red.”

John King said:

“ROS is confident that we have everything in place that will support effective delivery ... The system has already been delivered and tested, and it is available to Revenue Scotland’s IT team to use.”—Official Report, Finance Committee, 26 November 2014; c 30, 31.

Those statements were made to the Finance Committee, and I know that that committee will be asking questions later today. That was a very confident delivery to the Finance Committee, given that the Auditor General’s report is telling us of an increased risk.

At a date between 7 November and 11 December, the Parliament’s Finance Committee was given confident assurance that everything was wonderful, so what happened? As we know from responses to the convener’s questions, the organisations agreed to your report, which is highly critical and highly concerning to both the Finance Committee and the Public Audit Committee, so why was such a glorious, confident pitch given to the Finance Committee to say that everything was in order, and why do we now receive this report today?

09:15

Caroline Gardner Auditor General for Scotland
link

All that I can do is repeat that the conclusions in my report are based on the audit work that we carried out up until early November, and I am confident that the conclusions that I have drawn in it about the increased risks to successful delivery of the new taxes reflect all the evidence that was available to us. For developments since then, you will need to ask colleagues from the Scottish Government and Revenue Scotland about the work that they are doing and the basis for their confidence.

Mary Scanlon Con Highlands and Islands
link

I have no doubt about, and do not lack confidence in, the accuracy of the Audit Scotland report. However, as a member of the committee and being charged with the duties that we are charged with, I have to say that I was shocked to read your report about increased risks two weeks after the confident claim that everything was in order. That is perhaps a matter for the next panel.

I return to the report that you gave us in August 2012, “Managing ICT contracts: An audit of three public sector programmes”, which looked at Registers of Scotland. It is an old report, but you highlighted the fact that

“The Scottish Government provided limited support”.

You were quite critical of the fact that the Scottish Government had failed to support the organisations, including ROS, so it is quite shocking that paragraph 30 your report of 11 December 2014, which we are considering today, says of Revenue Scotland:

“It explored the option to develop the IT system fully within the Scottish Government. This was rejected at the end of April 2014, as the Scottish Government did not have the staff or expertise available to develop the system within the timescales, due to other commitments.”

What was the Scottish Government doing that was more important than preparing to collect more devolved taxes in Scotland? Can you tell us what those other commitments were, because that was flagged up two years earlier?

Caroline Gardner Auditor General for Scotland
link

We are currently carrying out work that will be reported in 2015-16, following up on the report that you are referring to, looking at the overall progress that the Government is making with its management of large IT systems. The committee will be aware that I have brought a couple of other reports to the committee recently—on the agricultural futures programme and NHS 24—looking at the challenges that the Government is still facing in that area. I think that it is fair to say that Government as a whole, not just in Scotland but more widely, faces problems in getting the appropriate skills and resources to develop those big systems.

What we have seen in relation to the new tax powers is a detailed process of making the decision about whether the best course of action was to develop the system in-house or to go externally. That decision was taken later than originally planned but, at this stage, we have no concern that the decision to go externally was not the right one to ensure that the system could be in place quickly, given other competing demands. The committee will be aware that the agricultural futures system is also one that brings with it a great deal of financial risk, and there is always a prioritising process going on to decide on the best approach, given competing demands.

Mary Scanlon Con Highlands and Islands
link

I am sorry to be a little bit boring and I appreciate the facts that you have outlined, but I am now becoming one of the older members of the committee so I have a bulky filing system in my office, and I have a copy of a submission to this committee from Paul Gray, which was sent in response to your report on managing ICT contracts. It is dated October 2012, and it refers to setting up delivery of public services, an organisation called SWAN—Scottish wide area network—and

“an action plan for the Central Government ICT Workforce to be available for consultation across the sector”,

with gateway reviews every six months.

The committee was told that the smaller organisations such as ROS, Disclosure Scotland and the Crown Office and Procurator Fiscal Service would not be left to languish on their own, the Government would take charge, and all these wonderful systems and help and advice would be available. That was two years ago, and naively I took that at face value. More than two years later, we are hearing that the Government did not have time to sort it out, despite everything that we were told. What happened to the Government’s big advisory service to help organisations such as ROS?

Caroline Gardner Auditor General for Scotland
link

The decision that was taken in January to give Revenue Scotland a more central role in collecting the two new taxes that are due next year was very much a reflection and recognition of the fact that the resources available in ROS and SEPA were limited and that it might be difficult for them to do what was required. The decision to give Revenue Scotland a more central role reflected those challenges.

A decision was then needed on whether IT systems should be developed in-house or procured externally. Mark Taylor will say more about the way in which that decision was taken.

Mark Taylor Audit Scotland
link

The decision to have a single IT system that was largely based in Revenue Scotland was a move from the initial thinking, which was to have a number of systems, including one in SEPA and one in ROS. Instead there was a decision to bring those systems together. Although the assessment of capacity was taken into account, the main driver for that decision was a look to the future and to the fact that further taxes may be devolved to Scotland, which, of course, the Smith commission had proposed. It was thought that having a single, centralised IT system that could accommodate those future taxes was the way to go. That was the core of the decision and we do not have any concerns with the nature of that decision.

Subsequent to that, the Government’s plan was to build the system itself—it thought that it could. An understanding was then reached that, given the range of IT activity that goes on in the Government, there was a need to go outside to procure that resource. The issue that we raise in the report is in relation to the time between reaching an understanding that there was not sufficient in-house capacity, and making the procurement decision and putting in place the procurement arrangements, which squeezed the time available for development of the system.

As the Auditor General says, in the new year we will have a more rounded look at IT and how Government is managing it. The issue that we flag up in the report in relation to this particular project is the time delay between the understanding being reached that an outside resource was needed and the decision to get the external resource in, which squeezed the time available.

Mary Scanlon Con Highlands and Islands
link

Twice you have highlighted that ROS asked the Government for help. In October 2012 it chapped on the door and there was limited support. When it next chapped on the door and said, “Please can you help us? We were assured that all the expertise and support is there,” the Government said, “Sorry, but we have other commitments.”

Why has the cost of setting up Revenue Scotland risen from £16 million to £20 million or £21 million?

Caroline Gardner Auditor General for Scotland
link

Gordon Smail will talk you through the figures, to keep us straight.

Gordon Smail Audit Scotland
link

The explanation is in paragraphs 37 and 38 of the report. The initial amount was £16.7 million over seven years, but as you have seen in the story in the report, over time there were reassessments of what the job of collecting taxes and supporting the new tax administration would involve, which gave rise to an increase.

There is some detail in paragraph 38 about how amounts have increased over the period. The bottom line is that the revised start-up costs totalled £4.3 million, as opposed to the £3.2 million that was expected over the two years. The set-up costs are now over three years, so there is explanation there of why the amounts went up.

Mary Scanlon Con Highlands and Islands
link

I am sorry to be boring, but I heard the finance secretary tell Parliament that, through the Scottish Government, the set-up and operational costs

“will be at least 25 per cent lower than they would be had I asked HMRC to deliver the status quo. Through revenue Scotland, we will serve the needs of the people of Scotland at a lower cost than the UK set-up”.—Official Report, 7 June 2012; c 9906.

The costs have now risen from £16.7 million to £21 million, so instead of the process costing 25 per cent less than it would have done had we used HMRC, it will cost us about £1 million less than the £22 million that HMRC estimated that it would cost. Why did the finance secretary say that the set-up and operational costs would be 25 per cent lower than the cost of using HMRC when the actual saving will be less than £1 million? By the time the new body is set up, we will be very close to HMRC’s figure. I cannot imagine that Mr Swinney would have wished to mislead Parliament. Why has the commitment that he gave changed so much?

Caroline Gardner Auditor General for Scotland
link

Our understanding is that the finance secretary’s statement was based on the original estimates that were provided by the Scottish Government and HMRC for administering the devolved taxes.

Mary Scanlon Con Highlands and Islands
link

That is what the £22 million figure related to, but he said that the Scottish Government was going to do it 25 per cent more cheaply.

Caroline Gardner Auditor General for Scotland
link

Yes. At that point, the Scottish Government and HMRC produced estimates of what the costs would be. The Scottish Government’s costs were lower. You have highlighted the increase in the Scottish Government’s costs; what we do not know is what would have happened to HMRC’s costs over the same period. I am not in a position to comment further on whether there is still a difference between them.

Mary Scanlon Con Highlands and Islands
link

Was the Scottish Government realistic in its estimate that the costs would be 25 per cent lower than they would have been had HMRC been involved? The costs are now 5 per cent lower than those of HMRC.

Caroline Gardner Auditor General for Scotland
link

It is clear that the changes have arisen as the Government goes through the process of establishing a tax authority for the first time. I am afraid that we simply do not know what the counterfactual would have been had HMRC been asked to do the work.

Hugh Henry Lab The Convener · Renfrewshire South
link

I will bring in Colin Keir and then Tavish Scott. We might have to squeeze members’ contributions, because the witnesses on the next panel have to be at the Finance Committee for 11.30, so we will need to work within that timescale.

Colin Keir SNP Edinburgh Western
link

Good morning. It seems to me that, to a certain extent, what has been said about the report has been overtaken by events. There is actually quite a lot of good stuff in it—I see it as a fairly positive report; the two issues are with staffing and IT. We might have on-going difficulties with the audit function as regards the rate of income tax, because Audit Scotland will not be the main functionary in that area. As a committee, we have talked about that over a period of months.

I turn to exhibit 3 on page 14 of the report. Last week, in an answer to Mr Rennie, the First Minister gave us an update on the Revenue Scotland staffing situation. Exhibit 3 is extremely helpful and is quite illuminating in that it shows that, between January and April, the initial decision to develop the IT system in-house was reversed after it was realised that, for whatever reason, it would be better to go to an external supplier.

The revised plan appears to be moving forward. At the point at which the report was prepared, you had some concerns, which I think have been allayed by what has been said recently. It is heartening to see that we have not ended up in the situation in which some other major IT projects have ended up, whereby they ploughed on regardless despite going way over budget, only to realise at a later stage the cost implications of doing so.

Something is happening here in that the revised plan would appear to be more or less on track. As we know, every IT system has a risk in it somewhere along the line. I am actually very heartened by a lot of what is in the report, because matters have been identified and taken forward.

We are looking at all this retrospectively. We had a clear answer from the First Minister on Thursday on the issue of staffing. Auditor General, you say that there is a risk. Moving away from the report, at this moment in time and given what you have heard in the past few weeks, is the risk the same as it was when you wrote the report or do you see a lightening of the load? The First Minister was fairly clear that although there are contingencies, there is no intention to use them at this time, given the work that has been done.

09:30

Caroline Gardner Auditor General for Scotland
link

I do not think that I can answer that question, Mr Keir. We stake our reputation on credible work that is grounded in the audit evidence that we have. That is what you have in the report in front of you. The report is very clear that some things have been achieved well, including establishing the overall framework for taxes, the bills that have been passed and the progress that is being made in other areas. Equally, at the time that we concluded the audit work and I made my audit judgments, I felt that there was a risk that both the staffing and the IT might not be fully in place at the end of March.

We hear, as you have done, that a significant amount of work is going on to make sure that everything that is required is in place, but without auditing that I do not feel that I can take my conclusions further than I have done at the moment. We all want this to work and we very much recognise the amount of commitment and investment that the Scottish Government and Revenue Scotland are making in that regard, but I need to reserve my position until I have audit evidence to work with.

Colin Keir SNP Edinburgh Western
link

At the time that the report was written—I am certainly not having a go at you about that—there were concerns, but I think a lot of us are feeling a bit happier simply because of what we have heard after that. The enlightening bit of exhibit 3 was the relatively quick decision to say, “This is beyond us”, for whatever reason and to move the IT system to an external source. I think that that is commendable and it is good that it is highlighted in the report.

Caroline Gardner Auditor General for Scotland
link

As we have said, that looks to us like a sound decision. We also say in the report that Revenue Scotland has detailed plans in place. Our finding alongside that is that, had the scale of the programme been recognised and staffed for earlier, some of those delays might not have happened. However, the response at this stage makes it clear that a significant commitment and investment are being made.

Colin Keir SNP Edinburgh Western
link

Given that we are pressed for time, I will leave it there just now.

Tavish Scott LD Shetland Islands
link

I want to deal with the dates, because they really matter in this report. Auditor General, you said that the Audit Scotland report was completed in early November. Can you give us the actual date?

Caroline Gardner Auditor General for Scotland
link

I will ask Mark Taylor to talk you through the final stages. This was fast moving all the way through, as you can imagine.

Mark Taylor Audit Scotland
link

It is worth saying that because of the fast-moving environment, we did everything that we could to try to get an understanding of the position up until we needed to go to press. The effective date on which we had final pieces of evidence put in front of us was the end of October. We then had a bit of reflection and discussion on what that meant. That is how we came up with the date of early November. We were doing field work and taking bits of evidence until the end of October, and then we had some further discussion in the early days of November.

Tavish Scott LD Shetland Islands
link

When was the factual accuracy of the final report cleared by the Government and Revenue Scotland? What date was it cleared on? You must have e-mails that say exactly when it was cleared.

Mark Taylor Audit Scotland
link

We can get back to you on the specifics but, broadly, it would have been about a week into November—in the first half of November. Rather than my trying to have a stab at the exact date, which colleagues here do not know, we will come back to you on it.

Tavish Scott LD Shetland Islands
link

So, it was in the first half of November and then it took from the middle of November to 11 December for it to be published. Nothing happened in that period; the report was just being sent to the printers and all the rest of it.

Mark Taylor Audit Scotland
link

Yes.

Tavish Scott LD Shetland Islands
link

Auditor General, you said in your opening remarks that staff were not in place early enough. Did you discover why not?

Caroline Gardner Auditor General for Scotland
link

The team will want to add to what I am about to say. There are two dimensions. In paragraph 14, I make the comment:

“Revenue Scotland did not put the required staff in place early enough to manage a programme of this scale and complexity.”

The staffing required for the tax administration programme element was slower in coming together than was needed, with hindsight and thinking through the whole way in which the arrangements would work.

Beyond that, evidence is coming through, both in our findings about why costs have risen and in our evidence to the Finance Committee, of the growing understanding of what is involved in putting together a new tax administration authority of this scale for the first time, where one has not been in place before. There was an element of underestimating the scale of the task earlier on, with an unavoidable element of simply learning from experience as the process goes on.

Tavish Scott LD Shetland Islands
link

Did the Government bring in external expertise from people who have run tax systems, from other parts of the United Kingdom or anywhere else in the world?

Caroline Gardner Auditor General for Scotland
link

There has been close working, through the tax administration programme board, with a range of people from around Scotland and from further afield. I will ask Mark Taylor and Gordon Smail to talk you through the detail of how that has worked.

Tavish Scott LD Shetland Islands
link

I just want to know, succinctly, if the Government brought in expertise, from wherever, to help it do the work.

Mark Taylor Audit Scotland
link

It is important to distinguish between putting the project team together and putting the operational team in place. The project team is very much focused on getting the IT systems and the organisation established. The operational team then administers taxes.

The approach that the Scottish Government has taken involves the operational team identifying its own staff, but looking to draw on a pool of expertise to bring those staff into place and prioritise the technical posts. You can see that, at the time of writing our report, we recognised the progress that had been made. There were 10 positions filled at that point.

In terms of the project team—

Tavish Scott LD Shetland Islands
link

Before we get on to that, what expertise did you find? What expertise was brought in?

Rebecca Seidel Audit Scotland
link

It is worth noting that the tax administration programme board, which is overseeing the project to implement the devolved taxes, has representatives from HMRC who sit on it. Expertise was coming in through those—

Rebecca Seidel Audit Scotland
link

Through the governance arrangements, yes.

We do not have details to hand about the staff who were employed as part of the programme team or about their background, but our understanding is that some of the staff have a background in tax administration.

Tavish Scott LD Shetland Islands
link

You could say a bit more than “our understanding is”. I do not mean to be pushy, but it is really important to understand whether that expertise was brought in, or whether they are just civil servants who have been moved from a completely different department—they could have been running agriculture or something—and have suddenly been told to set up a tax system. I am trying to establish that you did not find that—that the situation was rather better than that. That is what I am driving at—I would like to know for sure that that was not the case.

Mark Taylor Audit Scotland
link

I think that we were content that, in terms of oversight of the project and the arrangements, as Rebecca Seidel has discussed, the right people were involved.

Mark Taylor Audit Scotland
link

There was an understanding of what the job was.

Tavish Scott LD Shetland Islands
link

Okay—I think that I am reassured by that.

You have touched on this at some length already this morning, Auditor General: you said that the IT system may not be fully operational by go date in April. Your exhibit 3 shows that we are running two months behind schedule, according to the time plan. I guess that that is the cause of your concern about the risk.

Caroline Gardner Auditor General for Scotland
link

It is. As you say, the decision to purchase rather than to develop the system was taken later, and the procurement then took longer. The system is now in place. It is being developed and tested. As I say in paragraph 32 of the report, however, the delays

“have reduced the time available to ... implement the full IT system”;

to ensure that all the pieces act together;

“to ensure it is compatible with the Scottish Government’s accounting system”,

so that the money can be transferred into the Government’s accounts smoothly; to do user development, training and testing; and to ensure that all the various bits of the process work together as planned.

To be clear, I am not saying that there is not time for that to happen; I am saying that the time for it to happen has been reduced. The assurance is not yet in place.

Colin Beattie SNP Midlothian North and Musselburgh
link

I share some of the confusion that has been expressed about the report. Overall, it seems to indicate a well-managed project that is progressing well, although two areas have been highlighted—human resources and IT. When you carried out the audit, Auditor General, did you look at the robustness of the contingency plans?

Caroline Gardner Auditor General for Scotland
link

When we carried out the audit work, the contingency plans were still being developed, so it was not possible to look at them in detail. We know that they focus on ensuring that the taxes can be collected come 1 April, but that more paperwork or manual processing might be required to do that than was originally planned. When we completed the audit work, those contingency plans were not developed enough to be audited.

Colin Beattie SNP Midlothian North and Musselburgh
link

A couple of things jump out in relation to the IT systems. In paragraph 36, on page 15, the report comments on the Government’s accounting system to record and account for the devolved taxes. It states:

“Currently, this work has not been affected by the delays in developing the central tax collection IT system.”

I am just a layman, but that looks to me as if the core system for recording and accounting for the taxation is already in place.

Caroline Gardner Auditor General for Scotland
link

The Scottish Executive accounting system—SEAS—is the core system and has been in place for a number of years. It is a long-standing and stable system. The challenge is to ensure that the IT system that will process the payments, particularly for the land and buildings transaction tax, can talk smoothly to SEAS, which is the financial system, and that the appropriate controls are in place, given the importance of those transactions.

Colin Beattie SNP Midlothian North and Musselburgh
link

So, actually, just one piece of the IT system looks like it might be running behind.

Caroline Gardner Auditor General for Scotland
link

No. There is the interface with SEAS, which has not yet been tested. The whole system for administering the taxes is the system on which the decision was taken late and the procurement was late, and of which the testing is still under way to ensure that it can do what is required come 1 April.

Colin Beattie SNP Midlothian North and Musselburgh
link

You have highlighted the decision to move to a central IT system, and you said that you agree with the wisdom of doing so. What sort of delay did that contribute? I think that we are talking about seven or eight weeks’ delay in total to the IT system. What proportion of that was caused by the decision to move to a different outcome?

Caroline Gardner Auditor General for Scotland
link

We have tried to lay that out as clearly as we can in exhibit 3. I ask Gordon Smail to talk Mr Beattie through the timeline in a bit more detail.

Gordon Smail Audit Scotland
link

In January, a substantial and important decision was made that Revenue Scotland would take on more responsibility than was originally planned. As we say in the report, it is important to realise that when that decision was made, account was taken of preliminary work that had happened in SEPA and Registers of Scotland. Between then and April, the IT supplier was to be identified. In relation to the amount of time that the Government has to deliver the system and Revenue Scotland has to put the system in place, in hindsight, probably more could have been done over that period.

The Scottish Government was looking at the options for delivering the system and that tied in with the decision to externalise the system rather than use in-house provision, which we had a conversation about earlier—there were good reasons why the Government decided not to go down the in-house route. Having decided which road to go down, the Government then put in place the process of seeking an external supplier, as exhibit 3 shows. If you are asking where the delays occurred, there was a delay between the decision in January to go ahead with the revised system, which involved more work for Revenue Scotland, and, ultimately, the decision to get an external supplier. That was over quite a few months.

Colin Beattie SNP Midlothian North and Musselburgh
link

So you are saying that the delay was between January and April, when an external supplier was being identified.

Gordon Smail Audit Scotland
link

That was when the decision was being made about how the system would be implemented. As we say in exhibit 3, the option to develop an in-house system was rejected at the end of April, so the delay was the period between January and April when discussions were on-going about how best to deliver.

Colin Beattie SNP Midlothian North and Musselburgh
link

So it took three months to decide which way to go.

Gordon Smail Audit Scotland
link

That is my understanding, and that is what our report says.

Colin Beattie SNP Midlothian North and Musselburgh
link

Does that seem unreasonable?

Gordon Smail Audit Scotland
link

It is difficult to know. We can go only on the basis of the available evidence. I presume that discussions were on-going. In the paperwork, which is the evidence base that we have on the issue, we have seen evidence of the various boards and teams in the Scottish Government and Revenue Scotland looking at the options over that period. Those were big decisions to make. You would have to speak to the next panel about what happened in that period.

09:45

Colin Beattie SNP Midlothian North and Musselburgh
link

To a layman who has been involved in IT systems, it does not seem too out of order to take three months to make such a decision.

Paragraph 23 on page 12 of the report talks about jobs—40 posts in total. It says that phase 2, which involves 20 posts, is on schedule as per the original estimate. Is that correct?

Caroline Gardner Auditor General for Scotland
link

For phase 2, we are saying that the confirmation of job descriptions and grades happened a little later than planned—originally, it was planned for September but it was completed in mid-October. The staff were due to be in post by February of next year, and clearly we do not know whether they will be in post by that date.

Colin Beattie SNP Midlothian North and Musselburgh
link

There was no reason to think that they would not be—otherwise you would not have said, “as originally estimated”.

Caroline Gardner Auditor General for Scotland
link

That is the estimate, but we were working with the audit evidence that was available to us at that point. We have not drawn a conclusion about it other than to note that the confirmation of job descriptions was a bit later than originally planned.

Colin Beattie SNP Midlothian North and Musselburgh
link

But there were no indications at that point that those 20 posts were necessarily going to be outside the estimate given.

Caroline Gardner Auditor General for Scotland
link

There was no indication that they would be outside the estimate, but there was no confirmation that they would be inside the estimate, given the concerns that there can be in relation to recruiting to specialist posts of this nature. All I can do, Mr Beattie, is refer you to the evidence that we have used in the report.

Colin Beattie SNP Midlothian North and Musselburgh
link

It sounds a bit like a case of, “Damned if you do, damned if you don’t.”

Caroline Gardner Auditor General for Scotland
link

One valuable thing that we can do for the Parliament is provide assurance about the process of these big and complex programmes and highlight where the risks remain. That is a remaining risk, which needs to be managed. That is all we are saying.

Colin Beattie SNP Midlothian North and Musselburgh
link

On the staffing side, the First Minister gave a clear response at First Minister’s questions last Thursday about the posts and about the stage that recruitment was at for the posts. There seems to be every reassurance that recruitment is going to be on schedule, so when will you look at all this again?

Caroline Gardner Auditor General for Scotland
link

We will keep the project under review routinely as part of our audit of the Scottish Government, and we will keep in touch with colleagues in the Government and in Revenue Scotland who are responsible for it. We are not planning to keep going in and checking on progress when we all hope that the focus will be on getting the IT system up and running and getting people in place. We are reassured by the evident commitment to taking the plans that are now in place and delivering them effectively for 1 April. What we are doing at this stage is providing evidence to Parliament about the progress that has been made.

Colin Beattie SNP Midlothian North and Musselburgh
link

Again, this is just a small point. On page 16 of the report, in paragraph 41, you refer to recruitment and

“Revenue Scotland’s difficulties in recruiting to their operational team”.

That is slightly different from saying that Revenue Scotland was delayed in recruiting its team. You are saying that it had difficulties. Where does that come from?

Caroline Gardner Auditor General for Scotland
link

I will ask Gordon Smail and Mark Taylor to talk you through the background to that, given the sensitivity.

Gordon Smail Audit Scotland
link

What we are trying to say relates to the track record that there has been so far. There were delays in coming to a decision about the number of staff. I think that there are good reasons for that—I do not want to understate that. There is an important job to do and, with the gift of a better understanding of what is needed in terms of staffing, a decision has been made.

All we are saying in the report is that, based on the evidence that we have available to us, some of the timescales have slipped. As we have said a few times this morning, our concerns—the risks that we have flagged—are to do with the period of time between when these important decisions are made and actions are taken and when the taxes are due to start and be collected from 1 April. That is where we are coming from.

Your specific point was about the word “difficulties”. The issue is the extent to which staff have been brought through the door in accordance with the revised timescales. It is reasonable for us, in a report that reflects on the risks that we see at that point in time, to use the language that is in the report.

Colin Beattie SNP Midlothian North and Musselburgh
link

On page 25, in paragraph 69, there is reference to work involving Audit Scotland and the National Audit Office. You say:

“We will report annually on this assurance work.”

No indication is given of what your cost will be, on top of the NAO cost.

Caroline Gardner Auditor General for Scotland
link

We have given evidence to the committee on this previously. The real challenge with the Scottish rate of income tax and potentially with further devolved taxes under the Smith commission is that they will continue to be collected by HMRC and assigned to the Scottish Parliament. HMRC is a UK-wide body that, under statute, is audited by the NAO and will continue to be so. There is no question about that. The NAO already does that work very effectively and it reports to the UK Parliament on it.

The Scottish taxes that HMRC collects on behalf of the Scottish Parliament will be only a small part of the NAO’s audit responsibilities because they are a relatively small amount of the overall tax that HMRC collects. We are working on the basis that, in order to give the Scottish Parliament the assurance that it needs about the taxes that are collected and the resource that is available to the Parliament for its purposes, we will carry out some work to review the work that is planned by the NAO and its findings. We will then report to this Parliament, if we think that that is appropriate, to highlight any issues that are significant in the context of the Scottish budget but insignificant in the context of HMRC’s tax collection overall.

At this stage, we do not expect that to have significant additional costs. We have flagged previously, in our budget submissions, that at this stage we are making no provision for new responsibilities that we may take on as a result of either the Scottish rate of income tax or, more significantly, the proposals that are coming out from the Smith commission. We may well need to do that as those proposals develop, as other public bodies will.

Colin Beattie SNP Midlothian North and Musselburgh
link

I suppose that the good news to note on costs is that the overall cost of implementing the SRIT is coming in below budget, at £35 million to £40 million instead of £40 million to £45 million.

Caroline Gardner Auditor General for Scotland
link

Absolutely, and we recognise in the report that the Scottish Government is working closely with HMRC to bring that about.

Hugh Henry Lab The Convener · Renfrewshire South
link

I ask Sandra White to bear with me. I will bring her in after Nigel Don.

Nigel Don SNP Angus North and Mearns
link

Thank you, convener. I have to go to another committee in about five minutes to discuss a constituency issue.

Good morning, Auditor General. If I may, I will pick up on the point about risk. I understand from running a few small projects in my time that there is always a risk, and I reflect that, whether the risk that something will go wrong is 50:50 or 0.5 per cent, we would still describe it as a risk. There is also a risk—in the other sense—that the rest of the world will believe that the world is about to fall down. The risk is actually minute, but you would still describe it as a risk.

Caroline Gardner Auditor General for Scotland
link

You are absolutely right. Any project of this scale brings risks with it, and we try hard to recognise that in the report. What we are saying, after careful consideration, is that because of the delays that have been experienced against the Scottish Government’s own plans, the risk has increased from where it would have been previously. That is not to say that it cannot be recovered. We are very aware of the scale of the effort that is going on to ensure that the arrangements are in place, as they need to be, on 1 April, but the risk is increased from the state of play earlier in the process because of the delays that have been experienced.

Nigel Don SNP Angus North and Mearns
link

May I then try to put that in the context of what I would describe from previous experience as the critical path? I am sure that that is a familiar term to you.

I am looking again at page 14 and exhibit 3, and I am thinking that, if the Scottish Government’s plans had put everything two months later, you would have had nothing to say other than that the project was on plan. I am not suggesting that the Scottish Government should have put things two months later, but I am reflecting that if the project could still have got to the end point—in other words, if the critical path allowed those points to be two months later—we would not be here talking about this, because it would appear that everything was on target.

My question then becomes: where is the critical path in this project? Are those milestones now in the right place, or are we actually past them?

Caroline Gardner Auditor General for Scotland
link

It is a very good question, and we have tried to answer it in the way we have worded the report, which has taken a good deal of care, as you can imagine. We say that we think that the detailed plans that are now in place could have been developed earlier and that, if they had been developed earlier, there would have been a lower risk of the milestones being missed. That is not to say that they would not have been missed or indeed that the plans may not have recognised that the critical path came later.

The central point is that that detailed planning did not happen early enough, and therefore we are now in a position where the investment that is needed to hit the end point of 1 April—it is a fixed and important end point—is more significant than it might otherwise have been.

Nigel Don SNP Angus North and Mearns
link

Thank you—and thank you, convener. I must go now.

Sandra White SNP Glasgow Kelvin
link

Both the Auditor General and the convener have said that it is a large and complex issue—we should not pretend otherwise. With the Smith commission, the situation is also a moveable feast. Indeed, Mr Taylor has mentioned the additional tax powers that are to come.

In your opening statement, you said that the audit took place while implementation was taking place. Is it normal for Audit Scotland to carry out a review when change is under way? Indeed, the audit took place when the Smith commission was under way. How difficult is it to audit a moveable feast when things are changing all the time and new legislation is coming forward?

Caroline Gardner Auditor General for Scotland
link

We carry out such audits frequently. My strong view is that, for large and complex projects such as this one, it is entirely appropriate to use our powers to provide assurance to the Parliament about progress rather than to wait for the end point and then report what went wrong, if that is the case—it clearly does not always happen that way.

Over the past few years, we have reported on, for example, key points in the development of the Commonwealth games, major transport infrastructure such as the second Forth road crossing, and a number of other large projects that involved lots of money and had significant implications for public services. I hold to the belief that that is an important part of our role on behalf of Parliament.

You are right to say that such audits bring additional challenges, not least because the fact that we are auditing tends to change things. People recognise what we are doing—we often highlight matters that had not been noticed or provide extra impetus to people to say, “We need more resource to get this delivered on time.” We work hard to mitigate the risks and to maintain good engagement with the people who we are auditing.

Such audits are more challenging, but I think that they are an important part of our role on behalf of Parliament.

Sandra White SNP Glasgow Kelvin
link

My point was about the accuracy of your audit. You mentioned the Commonwealth games. That came in below budget, so we saved money. How accurate is an audit of an issue that is on-going? The evidence from the Commonwealth games is that the games saved money and things worked fantastically.

Caroline Gardner Auditor General for Scotland
link

The Commonwealth games is a great example of how such auditing can work. Our prior reports on the games highlighted that progress was in line with the milestones; they also highlighted a couple of areas, particularly security, where more investment may have been needed to deliver what was required. In early 2015, we will publish a final report that will show exactly that.

Although I would not say that we are always able to forecast the future with absolute 20:20 vision—no one can do that—we have a pretty good track record of saying, “This is what’s happening entirely satisfactorily, this is what’s a real problem, and here’s where the risks lie.” We have tried to do that in a balanced way in the report.

Sandra White SNP Glasgow Kelvin
link

Thank you very much. Although that does not necessarily prove my point, it shows how difficult it is to be accurate.

You mentioned the factual accuracy of the report that we have before us; you also mentioned the conclusions that you have drawn from them. Various members have asked whether the involved parties, including Government, had seen the report and raised any issues, but that was in relation to the report’s factual accuracy. The conclusions that you have drawn from those facts is an entirely different issue.

Caroline Gardner Auditor General for Scotland
link

I have phrased my findings in the report and in discussion with the committee today to reflect the fact that I think that there is an increased risk because of the delays that have been experienced in staffing and IT systems. That is not in any sense a red flag or a warning that they will not be in place; I am reporting to you my professional judgment based on the evidence that my colleagues have collected and analysed that the risk is greater. I have also acknowledged the significant work that is going on to overcome the delays and get to where we all want to be on 1 April 2015.

Sandra White SNP Glasgow Kelvin
link

I absolutely take that on board, but I return to the fact that you cannot see into the future. Throughout the report, you refer to many things that “may” happen—you do not say that they will definitely happen.

I welcome the report and I think that it is right that you should highlight the issues that you draw in your conclusions, but not necessarily in the final report as we have here. For example, you mention the IT system in the report, but Mr Taylor said that having a centralised IT system is probably the right way to go in the long term, to save money and to have more transparency not only for the Parliament but for the people of Scotland as well.

Caroline Gardner Auditor General for Scotland
link

I want to be clear that there are areas where we conclude that there is increased risk and that there may be cost and performance implications. Equally, we have also found that there have already been delays in a number of significant areas that have led to that increased risk. Therefore, the report is not speculative—it draws conclusions on the evidence available to us, which has been agreed for factual accuracy with colleagues in Government and Revenue Scotland.

10:00

Sandra White SNP Glasgow Kelvin
link

There is factual accuracy, but it seems that the Government has not agreed with the conclusions—although perhaps it will do so when we ask it for evidence. I bring you back to the fact that you used the phrase “may be”. We must keep that point in mind, as you used that phrase earlier and it is in the report.

Caroline Gardner Auditor General for Scotland
link

I am happy to confirm that I have concluded that there is an increased risk, which clearly has a forward-looking dimension. However, my conclusion is based on the delays that have happened in the past, so there is an important balance to strike between the evidence that we are working with and the conclusions that I have drawn. I do not think that we are disagreeing; it is the balance between the two that is important.

Hugh Henry Lab The Convener · Renfrewshire South
link

I will ask three short questions before I invite the next panel to give evidence.

Is it possible in public sector contracts to show that you come in under budget by overstating the original estimate?

Caroline Gardner Auditor General for Scotland
link

I think that it is possible to do that in any contract. However, I do not want to speculate about any particular circumstances that you may be referring to.

Hugh Henry Lab The Convener · Renfrewshire South
link

Okay. Have you been notified of any intention to use the contingency?

Caroline Gardner Auditor General for Scotland
link

At this stage, we understand that the contingency plans are being developed but that Revenue Scotland and the Scottish Government hope to make enough progress between now and the end of the year for them not to be required.

Hugh Henry Lab The Convener · Renfrewshire South
link

My third question relates to a strange comment in paragraph 41, which is on page 16 of the report. Can you provide some clarification? The paragraph states:

“The Scottish Government’s current assessment is that while it currently has enough skilled people in place to fulfil its responsibilities, it is dependent on a single member of staff and consequently there is a need to consider resilience as April 2016 approaches.”

Does that mean that the absence of one person could have brought the project crashing?

Caroline Gardner Auditor General for Scotland
link

The comment is in relation to the development of the Scottish rate of income tax for April 2016 rather than the two new devolved taxes that will operate from 1 April 2015. Does Gordon Smail want to amplify the comment that we make in the report?

Gordon Smail Audit Scotland
link

It is just an observation that we made, and it is obviously part of a point that is important in the longer term. It is linked to the issue of having the necessary capacity for delivery. That part of the report is taking a longer-term view. We are very much focusing on the devolved taxes.

Hugh Henry Lab The Convener · Renfrewshire South
link

I understand that, but does the comment mean that the plans for the Scottish rate of income tax are dependent on one person?

Caroline Gardner Auditor General for Scotland
link

Not quite. Mark Taylor can give you a bit more detail on the background.

Mark Taylor Audit Scotland
link

We make the point that that is the right sort of capacity to deal with the current workload. The two other points that we make in the report are that the workload is bound to grow in the future, so the situation needs to be kept under review, and that there is also a resilience issue, because of the dependence on that one person who has the skills. The organisation needs to understand how it backfills that post if that person is not around.

Gil Paterson SNP Clydebank and Milngavie
link

I did not intend to say anything, but the Auditor General raises a question from a business perspective. In her answer, she said that there is a possibility that folk would overtender and that it would be agreed by the Government.

Caroline Gardner Auditor General for Scotland
link

No. I am sorry if that is the impression that I gave, but that is not what I intended to say.

Gil Paterson SNP Clydebank and Milngavie
link

I think that the question was whether it was possible to overestimate the budget.

Caroline Gardner Auditor General for Scotland
link

The way that I interpreted the question was whether it would be possible to set a budget that—

Hugh Henry Lab The Convener · Renfrewshire South
link

I was not talking about the tendering process.

Gil Paterson SNP Clydebank and Milngavie
link

Is that not related to the tendering process?

Hugh Henry Lab The Convener · Renfrewshire South
link

No. What I was—

Hugh Henry Lab The Convener · Renfrewshire South
link

I would like to clarify my question. I hope that I did not mislead the Auditor General.

Hugh Henry Lab The Convener · Renfrewshire South
link

The question that I was asking was whether, in indicating potential costs for projects, it is possible to show that projects come in under budget by overstating the potential cost. It is clear that I am not talking about the tendering process.

Caroline Gardner Auditor General for Scotland
link

That is how I interpreted the question, convener.

Gil Paterson SNP Clydebank and Milngavie
link

Can I come back in, again from a business perspective?

Gil Paterson SNP Clydebank and Milngavie
link

Is it possible for what the convener describes to happen because of the tender process that is involved?

Caroline Gardner Auditor General for Scotland
link

No—if the tender process works properly. The tender process should be a competition that produces a true cost.

Gil Paterson SNP Clydebank and Milngavie
link

In other words, when it comes to public sector contracts, what happens is that a tender is made and we get cost savings because of the efficiency with which the work is carried out.

Caroline Gardner Auditor General for Scotland
link

This is clearly a theoretical discussion.

Gil Paterson SNP Clydebank and Milngavie
link

Not for me—not in business. I do it all the time.

Caroline Gardner Auditor General for Scotland
link

I understand that entirely, Mr Paterson, but I am trying to avoid the implication that I am talking about any particular project or contract.

There is clearly scope for an awful lot of movement between setting a budget for a big project or programme and the final costs coming in. If there is true competition for a contract as part of that budget, that ought to drive out any overstatement in that part of the budget. There might be many other things that happen between the initial budget and the final estimate that would also have an impact.

Hugh Henry Lab The Convener · Renfrewshire South
link

Auditor General, I thank you and your team for your contribution.

I will briefly suspend the meeting to allow our witnesses to change over.

10:05 Meeting suspended.

10:07 On resuming—

Hugh Henry Lab The Convener · Renfrewshire South
link

On our next panel, we have: Alyson Stafford, director general of finance, Scottish Government; Eleanor Emberson, head of revenue, Revenue Scotland; John King, business development director, Registers of Scotland; and John Kenny, head of operations, SEPA.

I believe that Alyson Stafford would like to make an opening statement.

Alyson Stafford Scottish Government
link

We are pleased to be here to help the committee with its examination of the considerable work that has been done and is in train to implement the Scotland Act 2012.

Revenue Scotland, which was established by the Revenue Scotland and Tax Powers Act 2014, has an important part to play in the implementation of the 2012 act. In January 2015, it will become a separate body in the Scottish Administration, and, like bodies such as the Scottish Court Service and Registers of Scotland, it will be operationally independent of the Scottish ministers and will be directly accountable to the Scottish Parliament. Revenue Scotland will be ready to administer both the assessment and collection of the devolved taxes from April 2015 and the subsequent compliance regime.

The effective collection of devolved taxes in Scotland relies on the creation of the right conditions, which includes a principle-based approach to taxation, where the spirit as well as the letter of the law must be upheld by taxpayers and their agents. In June 2012, the cabinet secretary set out his approach, which is based on Adam Smith’s four maxims. Those have underpinned all the work to establish the devolved taxes in Scotland.

A further condition is, obviously, the programme of robust legislation, which commands a high degree of consensus. For example, the Revenue Scotland and Tax Powers Act 2014 received unanimous approval at each stage from the Finance Committee and the whole Parliament.

Another condition is active engagement with the appropriate stakeholder communities. For the two devolved taxes, agents of land and buildings transaction tax payers, landfill site operators and a range of professional bodies will continue to participate to inform policy formulation and guide operational implementation. That will mean that operational processes will be user friendly. At the heart of that activity in Scotland are the tax consultation forum and the devolved tax collaborative, which are accessible, broad-based, issue-specific working groups that are unique to the Scottish approach.

The final key condition is good governance of the tax administration processes. The tax administration programme and Revenue Scotland have been established to deliver those processes—and they will.

We are now seeing the final stages of the journey that began in June 2012 when the cabinet secretary announced in Parliament his decision to establish a tax authority for Scotland.

In the words of the Auditor General,

“there are now well-developed project plans for implementing the devolved taxes.”

Using those plans, Revenue Scotland has provided online tax calculators so that people can work out the tax that is due based on the proposed rates and bands. It has launched its website and developed a core information technology system to process tax returns and the associated case management—the system is currently subject to internal testing. It has also finalised payment systems and banking arrangements. It is currently consulting users on the drafting of technical guidance for taxpayers for both the devolved taxes. It has a fully staffed programme team so that it can continue programme delivery, and it is recruiting staff for operational delivery as and when they are needed.

Positive actions are being delivered thick and fast. My colleagues and I are well placed to help the committee with its exploration of the opportunities and risks, and to set out the robust actions that are in place to manage and mitigate them. All of us and our teams are highly motivated and committed to delivering the effective collection and administration of taxation from 1 April next year.

I will introduce my colleagues. Eleanor Emberson has been head of Revenue Scotland since October 2012, and is the chair of the tax administration programme board. She is the former chief executive of the Scottish Court Service. John King is business development director at Registers of Scotland and lead for ROS on the tax administration programme board. He has been with ROS for 30 years. John Kenny is head of national operations at SEPA and is the lead for SEPA on the tax administration programme board. He has been with SEPA since its inception 18 years ago.

As you know, I am the director general of finance at the Scottish Government. I chair the fiscal responsibility programme board, and I am happy to cover the other aspects of the implementation of the Scotland Act 2012 that sit outside the scope of Revenue Scotland.

Hugh Henry Lab The Convener · Renfrewshire South
link

Thank you. I will start with two questions. A very complicated finance system is being set up, and we all depend on that being done effectively and efficiently. You have highlighted the range of experience among the people who are involved, in particular the experience that you and Eleanor Emberson have gained at the Scottish Government and Revenue Scotland respectively. Can you tell me what accounting qualifications and revenue experience you have?

Alyson Stafford Scottish Government
link

I am a qualified chartered accountant and am recognised as a Chartered Institute of Public Finance and Accountancy accountant, which covers the private and public sector. My qualification includes taxation. That covers the particular span of your question.

Eleanor Emberson Revenue Scotland
link

I do not have an accounting qualification. I have taken two of the exams for the tax professional qualification that the Institute of Chartered Accountants of Scotland has introduced, and I passed both of them. I have gone out of my way to hire from HMRC people who have expertise in tax, and I have considerable expertise in running programmes and in running a public body.

Hugh Henry Lab The Convener · Renfrewshire South
link

Okay—thank you.

I do not know whether Alyson Stafford or Eleanor Emberson should answer my next question.

Paragraph 30 of the report, which is on delays to the IT system, says that

“the option to develop the IT system fully within the Scottish Government”

was explored, but that it

“was rejected at the end of April 2014, as the Scottish Government did not have the staff or expertise available to develop the system within the timescales, due to other commitments.”

Did the other commitments include preparations for the referendum?

10:15

Eleanor Emberson Revenue Scotland
link

I am afraid that I did not explore the range of other commitments that the Scottish Government IT team was facing, but they included the Commonwealth games, the Ryder cup and—as has already been noted by the Auditor General—at least one other major IT project that was already under way. When we took that decision, the point was about taking the lowest risk option.

Hugh Henry Lab The Convener · Renfrewshire South
link

Who would be able to tell me what the other commitments were?

Eleanor Emberson Revenue Scotland
link

I presume that my colleagues who line manage the IT team would know.

Hugh Henry Lab The Convener · Renfrewshire South
link

Which department would that rest with? Would it be the Scottish Government or Revenue Scotland?

Eleanor Emberson Revenue Scotland
link

It would be within the Scottish Government.

Hugh Henry Lab The Convener · Renfrewshire South
link

Would it rest with Alyson Stafford?

Alyson Stafford Scottish Government
link

The director of digital would be the best person to ask.

Hugh Henry Lab The Convener · Renfrewshire South
link

Right. Perhaps you could find out for me what those other commitments were and whether they included the referendum.

Alyson Stafford Scottish Government
link

Yes, we can come back to the committee on that.

Hugh Henry Lab The Convener · Renfrewshire South
link

Thank you.

On 26 November, Eleanor Emberson told a parliamentary committee that

“there is nothing negative that I need to report.”—Official Report, Finance Committee, 26 November 2014; c 29.

However, we have heard a number of warnings from Audit Scotland, which were repeated in the press release that it issued on 11 December 2014, that the delays

“have increased the risk that the IT system may not be fully functioning by 1 April 2015 and that Revenue Scotland won't have the required operational expertise in place by then.”

Do you not think that that is a negative?

Eleanor Emberson Revenue Scotland
link

I have two points to make on that. I reported fully to the Finance Committee that we had a number of areas at amber that we were managing back to green. That is a reflection of managing risk, because that is what one does in project management.

I used the specific words “nothing negative” in response to a question from Gavin Brown. He noted that my written report to the Finance Committee had been submitted in mid-October, as had been agreed, but, because of other committee business, the committee had not been able to see me until the end of November. He said that there had been “a slight time gap” and asked whether I could tell the committee if anything material had changed between my written report in mid-October and my appearance before the committee at the end of November. To that, I responded:

“There has been a lot of progress but there is nothing negative that I need to report.”

Hugh Henry Lab The Convener · Renfrewshire South
link

You said:

“We are still on track on all the areas”.—Official Report, Finance Committee, 26 November 2014; c 29.

However, the Audit Scotland press release indicates that

“the IT system may not be fully functioning by 1 April 2015”.

Which is correct: Audit Scotland’s comment, or your statement that Revenue Scotland is still on track in all areas?

Eleanor Emberson Revenue Scotland
link

We are on track in all areas.

Hugh Henry Lab The Convener · Renfrewshire South
link

Are you saying that the Audit Scotland report is wrong?

Eleanor Emberson Revenue Scotland
link

I am not saying that.

Hugh Henry Lab The Convener · Renfrewshire South
link

It is either right or wrong. If you are not saying that the report is right, are you saying that it is wrong?

Eleanor Emberson Revenue Scotland
link

Managing programmes and managing projects is about managing risk. We are on track because we are managing the risks that Audit Scotland has highlighted. There is no contradiction in those two statements.

Hugh Henry Lab The Convener · Renfrewshire South
link

Is there not? You are on target, but the system

“may not be fully functioning by 1 April 2015”.

How is there no contradiction in that?

Eleanor Emberson Revenue Scotland
link

The Auditor General has just highlighted that there is a risk but, as has been discussed with the committee, there are always risks. We manage risks, and we are confident that we have managed this one. Life has moved on a long way since the Auditor General’s staff did their fieldwork. We have an IT system that is currently in testing. I have seen it, and it is being tested internally at the moment. We will bring in external users to test it in January. That is how I can be confident that we are on track.

Hugh Henry Lab The Convener · Renfrewshire South
link

Okay. When you were given the draft report, did you challenge the statement that

“the IT system may not be fully functioning by 1 April 2015”?

Eleanor Emberson Revenue Scotland
link

I challenged a number of statements in the report.

Hugh Henry Lab The Convener · Renfrewshire South
link

Did you challenge that one?

Eleanor Emberson Revenue Scotland
link

I challenged the perception of risk.

Hugh Henry Lab The Convener · Renfrewshire South
link

Did you tell Audit Scotland that that statement was wrong because you are “still on track”?

Eleanor Emberson Revenue Scotland
link

Audit Scotland’s response to me, when I discussed all this with it, was that it still saw a risk and felt that it had to be highlighted.

I am managing the risk and I see that we are on track. Audit Scotland notes that there is a risk; I think that I am managing it. Audit Scotland has to draw its own conclusions from the evidence in front of it.

Hugh Henry Lab The Convener · Renfrewshire South
link

The report also says:

“There is a risk that Revenue Scotland will not fill all of its operational posts in line with its plans”.

Is that wrong as well?

Eleanor Emberson Revenue Scotland
link

Again, the risk that Audit Scotland perceived has reduced dramatically. The First Minister gave an update in the chamber last week but even since then life has moved on. Audit Scotland noted that we had recruited 10 of the operational staff. As of today, the figure is 21, and eight more posts are in the recruitment process: three of them have interviews scheduled, and five more are not quite at that stage.

Hugh Henry Lab The Convener · Renfrewshire South
link

Will you fill all your operational posts in line with your plans?

Eleanor Emberson Revenue Scotland
link

We will have all the operational staff that we need by April, yes.

Hugh Henry Lab The Convener · Renfrewshire South
link

Okay. Were ministers alerted to the warning that not enough staff were in place?

Eleanor Emberson Revenue Scotland
link

Do you mean the programme staff?

Hugh Henry Lab The Convener · Renfrewshire South
link

I mean any staff.

Eleanor Emberson Revenue Scotland
link

It is important to distinguish between the programme staff, who have worked on set-up, and the operational staff, who will manage live running.

Hugh Henry Lab The Convener · Renfrewshire South
link

Okay. Tell me about both.

Eleanor Emberson Revenue Scotland
link

On programme staffing, Audit Scotland has concluded that the staff that it considers were required were not in place. I do not accept the word “required”. If it was possible to have the time over again, I would seek to have more set-up staff in earlier. However, I do not believe that that was necessary or would have materially changed where we are right now.

Hugh Henry Lab The Convener · Renfrewshire South
link

Why would you have done it differently if it was not necessary?

Eleanor Emberson Revenue Scotland
link

It would have been helpful. As the Auditor General has pointed out, when you work through a programme such as this one, you iterate planning. When you start, you have a very high-level plan, particularly in a programme that works alongside legislation, as this one does. The level of detail in programme planning matches the development of the policy and the legislation, so there cannot be completely detailed plans for implementation until what is going to be implemented is understood exactly. Therefore, it would have been unhelpful to have 40 staff in place two years ago. We have the right level of staffing now. If I could go back and do it again, I might have built the team up two months earlier than I did, but I say that with the benefit of hindsight.

Hugh Henry Lab The Convener · Renfrewshire South
link

At various times, posts were not filled. Did ministers agree at any time that staff should not be recruited?

Eleanor Emberson Revenue Scotland
link

I did not go to ministers at any point during the recruitment of set-up staff.

Hugh Henry Lab The Convener · Renfrewshire South
link

Costs have risen by £2 million.

Eleanor Emberson Revenue Scotland
link

The figure is £1.7 million.

Hugh Henry Lab The Convener · Renfrewshire South
link

Well, nearly £2 million. Is that the end of the rises? Is that the final figure?

Eleanor Emberson Revenue Scotland
link

I believe so.

Hugh Henry Lab The Convener · Renfrewshire South
link

You will be able to report that.

Eleanor Emberson Revenue Scotland
link

That is my current best estimate.

Colin Beattie SNP Midlothian North and Musselburgh
link

Just to be absolutely clear, you are telling us that IT systems and staff recruitment are on track.

  1. 10:00 Interests Procedure · 3
  2. 10:00 Decision on Taking Business in Private Procedure · 1
  3. 10:00 Section 23 Report Committee business · 333
  4. 11:00 Section 22 Reports Evidence session · 15

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.