1. To ask the Scottish Parliamentary Corporate Body what developments there have been since November 2012 regarding the external screening facility. (S4O-01859)
Official Report · Chamber
External Screening Facility
Scottish Parliamentary Corporate Body Question Time
Speakers
Choose an MSP to read only their contributions- Graeme Pearson Lab 2
- David Stewart Lab 2
The record
4 contributions1. To ask the Scottish Parliamentary Corporate Body what developments there have been since November 2012 regarding the external screening facility. (S4O-01859)
The contractor’s progress to date has included establishing the construction site, the temporary removal of parts of the glass roof over the concourse and wall panels, excavating and laying the foundations, and constructing the steel and concrete system frame. The project is on track and within budget.
I remind members that the decision to proceed with the project was not taken lightly and was based on the corporate body’s corporate and legal responsibilities to ensure safety. The corporate body has a duty of care to all building users to put in place sufficient measures to the extent that is reasonably practical in the circumstances to do so. Failure to carry out measures that are, in law, reasonably practical could leave the corporate body and its individual members open to prosecution.
The external security facility will provide protection for more than 400,000 visitors per year and up to 1,000 passholders daily, including staff, members, the media and contractors, through a significantly safer and more secure environment for screening.
I remind members that the decision to proceed with the project was not taken lightly and was based on the corporate body’s corporate and legal responsibilities to ensure safety. The corporate body has a duty of care to all building users to put in place sufficient measures to the extent that is reasonably practical in the circumstances to do so. Failure to carry out measures that are, in law, reasonably practical could leave the corporate body and its individual members open to prosecution.
The external security facility will provide protection for more than 400,000 visitors per year and up to 1,000 passholders daily, including staff, members, the media and contractors, through a significantly safer and more secure environment for screening.
David Stewart will realise that members are sensitive about the costs attached to such projects. Has the corporate body received an up-to-date threat assessment of the situation for which the facility was designed, and can it share with the Parliament any details of that assessment?
The corporate body has received clear and consistent expert security advice that, in light of current threats, it is highly advisable for the Parliament to construct an external security facility. Although Graeme Pearson will understand more than most that I cannot go into the detail of that advice, there are other indicators such as the number of incidents that our own security staff deal with. For example, more than 1,500 sharp objects such as knives were retained in the public access area during 2012. The risk profile has changed from organised groups to obsessed individuals.
Motions, questions and votes
Linked from this item of the Official ReportIn this meeting
Everything on 7 Mar 2013 →- Housing Benefit Changes (Homeless People) Questions · 11
- Fairtrade Nation Questions · 5
- Justice of the Peace Courts (Motherwell, Cumbernauld and Coatbridge) Questions · 6
- Miners’ Strike (Arrests) Questions · 4
- Structural Funds Questions · 6
- Commission on Women Offenders Questions · 6
- Engagements First Minister’s Questions · 22
- Secretary of State for Scotland (Meetings) First Minister’s Questions · 11
- Cabinet (Meetings) First Minister’s Questions · 12
- Human Rights Act 1998 First Minister’s Questions · 6
- Scottish Police Authority and Police Scotland First Minister’s Questions · 12
- Schools (Reform) First Minister’s Questions · 6
- Point of Order Procedure · 10
- #Scotlandhour Members’ business · 7
- External Screening Facility Questions · 4
- Voting Consoles Questions · 4
- Living Wage Questions · 10
- SPCB Questions Questions · 5
- Accessibility of Parliamentary Campus (People with Autistic Spectrum Disorder) Questions · 4
- Catering Contractor (Traceability of Meat) Questions · 4
- Adult Health and Social Care (Integration) Debate · 64
- Point of Order Procedure · 2
- Enterprise and Regulatory Reform Bill Bill debate · 2
- Public Bodies (The Office of Fair Trading Transfer of Consumer Advice Scheme Function and Modification of Enforcement Functions) Order 2013 Debate · 2
- Parliamentary Bureau Motion Business motions · 2
- Decision Time Decision time · 7
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.