Concern has been expressed about the impact of mud and dust from construction vehicles and heavy goods vehicles, particularly on the A904 at Echline corner and in the Linn Mill area. What is being done to resolve problems, which include mud and dust being deposited on footways?
Official Report · Committee
Forth Replacement Crossing
Speakers
Showing Alex Johnstone only · show everyone- Lawrence Shackman Transport Scotland 24
- David Climie Transport Scotland 22
- Gordon MacDonald SNP 20
- Maureen Watt SNP 14
- Alex Johnstone Con 5
- Jim Eadie SNP 4
- Adam Ingram SNP 3
- Elaine Murray Lab 2
Alex Johnstone’s contributions
5 contributionsIs it fair to say that you are aware of a problem and are trying to improve matters?
You said that lorries are running along the A904. Something that emerged from the consultation that the committee carried out was concern that some HGVs associated with the project are driving at excessive speed on the A904. Respondents said that some drivers conduct themselves rather aggressively. Have you identified a problem in that regard and, if so, is there anything that you can do to prevent it?
The committee has heard concerns about adverse impacts from noise and vibration at the Echline corner construction site, including concerns that promised mitigation measures appear not to have been installed. Do you share those concerns? Can you explain why mitigation measures have not been installed?
So it continues to be a work in progress.
In this meeting
Everything on 6 Mar 2013 →- 10:00 Decision on Taking Business in Private Procedure · 1
- 10:00 Forth Replacement Crossing Committee business · 94
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.