To ask the Scottish Executive what the specific programmed dates are for the start of construction of the six improvement schemes on the A75 between Stranraer and Dumfries. (S2O-10080)
Official Report · Chamber
A75
SCOTTISH EXECUTIVE General Questions
Speakers
Choose an MSP to read only their contributions- George Lyon LD 3
- Alasdair Morgan SNP 2
- Alex Fergusson Con 1
The record
6 contributions
George Lyon
LD The Deputy Minister for Finance, Public Service Reform and Parliamentary Business · Argyll and Bute
link
Expressions of interest from contractors have been received for the schemes at Barfil, Newton Stewart and Planting End. Tenders are expected to be issued in August 2006, and the projected construction start is April 2007. Transport Scotland's intention is to publish draft orders for the schemes at Dunragit, Hardgrove and Cairntop in the next two months.
I thank the minister for that answer, which is more positive than any of the others I have received since I first started asking the question in 2002. Even yet, the start date is slipping by another year, and it is now in the financial year 2007-08. Does the minister accept that it is important for the communities along the A75 that there are no more of the interminable delays that have occurred with those six important projects since 2002?
George Lyon
LD The Deputy Minister for Finance, Public Service Reform and Parliamentary Business · Argyll and Bute
link
I am pleased that the member is pleased with the response. I restate that we expect the construction of the first three schemes to commence next year.
When the concept of providing guaranteed, unambiguous overtaking lanes was first proposed, it was insufficiently detailed for all the value-for-money issues to be identified and addressed. I acknowledge that that process has taken some time, but we are now beyond it and we are moving towards construction. The Minister for Transport and I regret that the process has taken some time, but we are now in a position to move forward with those important works on the A75.
When the concept of providing guaranteed, unambiguous overtaking lanes was first proposed, it was insufficiently detailed for all the value-for-money issues to be identified and addressed. I acknowledge that that process has taken some time, but we are now beyond it and we are moving towards construction. The Minister for Transport and I regret that the process has taken some time, but we are now in a position to move forward with those important works on the A75.
Does the minister accept that the unusually high percentage of heavy goods vehicles that use the A75—as borne out by the Executive's own figures—the effect of which will be greatly exacerbated following the construction of the joint port facility at Cairnryan, more than justifies giving a different weighting to any modelling exercise on the A75, as seemed to be acknowledged by the Minister for Transport when he visited Galloway and Upper Nithsdale? Does the minister accept that we urgently require not just a start date for those six agreed projects—I welcome the minister's reply on that issue—but several more projects, including bypasses for the two villages that will be left without one, Springholm and Crocketford?
George Lyon
LD The Deputy Minister for Finance, Public Service Reform and Parliamentary Business · Argyll and Bute
link
I recognise the issues that the member raises, which I understand he has discussed with the Minister for Transport. I will certainly pass on to him the concerns that the member raises once again today. I am sure that those issues will be addressed under the forthcoming review of transport projects that the Minister for Transport announced recently.
In this meeting
Everything on 8 Jun 2006 →- Scottish Parliament Thursday 8 June 2006 Debate · 1
- Regulatory Framework Debate · 36
- Interests of Members of the Scottish Parliament Bill: Stage 3 Bill debate · 8
- Interests of Members of the Scottish Parliament Bill Bill debate · 21
- Point of Order Procedure · 3
- Reparation Actions Questions · 9
- Class Sizes Questions · 6
- A75 Questions · 6
- National Transport Strategy Questions · 6
- Kilmarnock to Glasgow Rail Line Questions · 4
- Enterprise in Education Questions · 4
- Youth Facilities (Audit) Questions · 4
- Cabinet (Meetings) First Minister’s Questions · 17
- Prime Minister (Meetings) First Minister’s Questions · 12
- Scottish Executive (Targets) First Minister’s Questions · 6
- Glasgow Bar Association First Minister’s Questions · 6
- Scottish Criminal Record Office Inquiry First Minister’s Questions · 6
- Teachers (Paperwork) First Minister’s Questions · 6
- SCOTTISH EXECUTIVE Questions · 1
- Diversion from Landfill Questions · 6
- Scottish Natural Heritage and the Scottish Environment Protection Agency (Public Inquiries) Questions · 7
- Fly-tipping Questions · 8
- Aberdeen Beach Recharge Scheme Questions · 8
- Beef Exports Questions · 13
- SCOTTISH EXECUTIVE Questions · 1
- Digital Hearing Aids (Waiting Times) Questions · 11
- Residential Care (Highland) Questions · 4
- NHS Boards (Performance) Questions · 4
- Drug Addiction (Specialist Facilities) Questions · 9
- Primary Care (Springburn) Questions · 4
- Osteoporosis (West of Scotland) Questions · 6
- Cancer (Waiting Times) Questions · 4
- Climate Change Debate · 78
- Parliamentary Bureau Motion Business motions · 4
- Decision Time Decision time · 35
- Muscular Dystrophy Members’ business · 19
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.