To ask the Scottish Executive what progress has been made in identifying an improvement scheme for the Hardgrove to Kinmont section of the A75. (S2O-8215)
Official Report · Chamber
A75 (Improvement)
SCOTTISH EXECUTIVE Enterprise, Lifelong Learning and Transport
Speakers
Choose an MSP to read only their contributions- Tavish Scott LD 3
- Elaine Murray Lab 2
- Alasdair Morgan SNP 1
The record
6 contributionsDesign work is well advanced and I expect draft orders for the scheme to be published next spring.
Three years ago, the construction start for the scheme was expected to be autumn 2006 and the cost £6.2 million. In January this year, the earliest start date had slipped to 2006-07 and the cost had risen to £9.2 million. I was advised in a letter from the minister's predecessor in April that further problems with the scheme had been identified and that a new scheme would have to be proposed. When does the minister expect construction of an improvement scheme for the Hardgrove to Kinmont section of the A75 to commence and what is the current estimate of cost? Can he guarantee that sufficient funding will be available to enable the improvement scheme to go ahead?
Dr Murray is correct in her assessment of the situation. She is also correct about the cost of the scheme. Although this will provide no comfort on the timescale, I am pleased to say that because of the additional design work, we have been able to reduce the estimate of cost to £6.8 million. It is expected that the project will take 12 months to complete and I am led to understand that it will start during 2007. I will give the member an exact date as soon as I can.
Does the minister share the disappointment of many at the snail's pace at which that improvement to the A75 and others have been progressed? Young men such as I have visibly aged waiting for anything to happen and goodness knows how many ministers have been in office. Does the minister intend to inject some urgency into his department's dealings?
I take seriously the point that Alasdair Morgan, Dr Murray and others make about the circumstances of the A75 and other routes. Several schemes, including those for overtaking, have been identified and are in preparation. In response to questions that were asked a couple of question times ago, I have undertaken to consider in coming weeks several specific issues that have come to my attention in relation to the A75 and the A76. I will pull all those matters together and instigate the urgency that we all need.
In this meeting
Everything on 24 Nov 2005 →- Scottish Parliament Thursday 24 November 2005 Debate · 1
- Business Motion Business motions · 9
- Housing (Scotland) Bill: Stage 3 Bill debate · 223
- Sex Education Questions · 4
- European Union Legislation Questions · 11
- Schools (Bullying) Questions · 4
- Loch Lomond and the Trossachs National Park (Byelaws) Questions · 6
- Sportscotland (Meetings) Questions · 8
- National Health Service (Missed Appointments) Questions · 6
- Fresh Talent Initiative Questions · 4
- Prime Minister (Meetings) First Minister’s Questions · 14
- Cabinet (Meetings) First Minister’s Questions · 8
- Asylum Seeker Removals First Minister’s Questions · 14
- Police Safety First Minister’s Questions · 4
- Nuclear Power First Minister’s Questions · 4
- St Andrew's Day Celebrations First Minister’s Questions · 12
- Terrorism Suspects (Detention) Questions · 6
- Mobile Closed-circuit Television Cameras Questions · 4
- Movement of Prisoners (Correspondence) Questions · 4
- Fingerprint Evidence Questions · 13
- Corporate Homicide Questions · 4
- Environmental Law Questions · 4
- Torture Questions · 17
- A75 (Improvement) Questions · 6
- Glasgow Airport Rail Link Questions · 6
- Glasgow School of Art Questions · 6
- M74 (Northern Extension) Questions · 4
- Edinburgh Tramlines (Funding) Questions · 11
- Glasgow Airport (Discussions) Questions · 4
- Rail (Freight) Questions · 8
- Housing (Scotland) Bill: Stage 3 Bill debate · 134
- Housing (Scotland) Bill Bill debate · 24
- Point of Order Procedure · 6
- Decision Time Decision time · 7
- Television Licence and Digital Reception Members’ business · 19
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.