The Tomatin to Moy section was announced in 2021, but it will not be completed until 2028 at the earliest. That is seven years, and there are eight remaining sections. Let us do the maths: if there are similar delays, we are talking about 2075 and not 2035.
When the Tomatin to Moy section was first tendered, it got one offer of £170 million, which was regarded as too expensive, but the outturn figure was £310 million or thereabouts. Does the cabinet secretary agree that there must be an examination of what went wrong and why Transport Scotland failed so abysmally? Will she recognise that there must be an inquiry by Audit Scotland into that scandal of gross abuse and the failure of Transport Scotland to develop terms and conditions that produced competitive bids for the industry, which is a sine qua non—