A9 Dualling (Programme for 2035 Completion)

Wednesday 14 January 2026 Meeting of the Parliament Statement 43 contributions · 18 speakers Watch on Scottish Parliament TV

Speakers

Showing Fiona Hyslop only · show everyone

Fiona Hyslop’s contributions

18 contributions
Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

The A9 is a vital element of our national infrastructure that connects the communities of the Highlands and Islands with central Scotland and supports their economic and social wellbeing. Dualling the A9 between Perth and Inverness will improve the safety, reliability and resilience of the route, and this Government has been consistent in its commitment to completing that vital work.

In support of that commitment, in December 2023, the Government announced its delivery plan for the completion of the A9 dualling programme by the end of 2035. That plan involved the procurement of four design and build contracts and, subject to further decision making in late 2025, the procurement of two mutual investment model contracts.

As the Government indicated yesterday in the budget and spending review statement, the programme will be delivered using capital-funded contracts instead of mutual investment model contracts, and it will still achieve dualling of the A9 between Perth and Inverness by 2035.

I am pleased to provide an update for the Parliament on the A9 dualling programme and further detail on the decision making and on how that decision affects our delivery plan for the completion of this vital programme of work.

The 2023 delivery plan set target dates for progress of the dualling programme. So far, the Government has met all those targets dates, and construction is under way on the third and fourth sections of the programme—Tomatin to Moy and Tay crossing to Ballinluig—which, together, will provide approximately 11 miles of dualling. Procurement of the fifth section, Pitlochry to Killiecrankie, commenced in July this year, and we are on track to award that contract in autumn 2026. That will bring another four miles of the programme into construction. The Government has also made significant progress with statutory processes. Since December 2023, we have published draft orders for one project, made orders for a further three projects and completed land acquisition for six projects.

The 2023 delivery plan anticipated the use of two mutual investment model contracts to achieve completion of the dualling programme. The Government indicated at the time that that would be subject to further decision making in late 2025, to take account of updated assessments of expected market conditions. Extensive work to inform that decision making was undertaken throughout 2025. Our updated business case confirmed that the rationale for completing the dualling programme remains strong and that it is considered to provide value for money. Our market consultation indicated a strong appetite among European contractors for involvement in the delivery of MIM contracts and an appetite among domestic contractors for involvement in the delivery of capital-funded contracts.

Our updated financial modelling indicates that the cost of MIM contracts is now around 28 per cent higher than the cost of equivalent capital-funded contracts—an increase from the 16 per cent difference estimated in 2023. The increased difference is primarily linked to the fact that the expected costs of borrowing for each MIM contract are now around 2 per cent higher per annum, which reflects macroeconomic factors impacting on borrowing costs.

It was concluded that using MIM contracts for the A9 dualling programme would provide poorer commercial value for money than would be provided by capital-funded contracts. Therefore, the Government will progress the A9 dualling programme to completion using capital-funded contracts. That important decision demonstrates the strength of the Government’s commitment to meeting its target of completing the A9 dualling programme by the end of 2035.

The decision not to use MIM contracts has implications for how completion of the A9 dualling programme by 2035 will be achieved. The 2026 delivery plan continues to balance factors including industry’s capacity to deliver and the need to minimise disruption to road users. It also takes into account the likely need for a public local inquiry for the Pass of Birnam to Tay crossing project. It brings forward the start of works for the Dalraddy to Slochd section in the north, providing earlier completion of the new grade-separated junctions that serve Aviemore and Carrbridge. It facilitates the earlier completion of a section of dualling that includes the new grade-separated junction at Dalnaspidal as part of a combined Glen Garry to Crubenmore contract, rather than as a stand-alone advance works contract.

The 2026 delivery plan is based on establishing a framework agreement that will streamline the procurement process and provide a pipeline of work, as the market has requested. We will continue to engage with the construction industry on the A9 dualling programme, including with the Civil Engineering Contractors Association, which has welcomed the use of capital-funded contracts.

Next week, in support of that aim, Transport Scotland will launch a further market consultation with interested parties on the design of the framework agreement. That consultation will inform procurement of the framework agreement, which is planned to commence in spring this year, with appointments being confirmed by the end of the year.

Once it is in place, the framework will be used to procure five contracts for completion of the six projects that are yet to commence procurement. Full details of the target dates for each contract to be procured are set out in the 2026 delivery plan, which has been published today on both Transport Scotland’s website and the dedicated A9 dualling website.

The 2026 delivery plan maintains the target of having dualling operational between Perth and Inverness by the end of 2035. With continuous construction activity taking place across the corridor, dualling will continue to be brought into operation on a phased basis, with 50 per cent of the route between Perth and Inverness operating as dual carriageway by the end of 2030; 67 per cent by the end of 2032; 91 per cent by the end of 2034; and 100 per cent by the end of 2035.

Today’s confirmation of the procurement and funding route for the remaining sections of the A9 dualling programme provides further reassurance for communities and businesses throughout the corridor on the timelines for construction of those projects.

I can also confirm that the updated cost estimate for the programme is now £3.97 billion at April 2025 prices. When adjusted for inflation, that is equivalent to £2.5 billion at April 2008 prices, which remains well within the original cost estimate of £3 billion at 2008 prices. This Government remains committed to providing the necessary funding in support of the estimated costs in order to deliver the dualling programme on track in 2035.

I will briefly cover three related matters. First, the Government has been progressing work to secure planning consent for the proposed active travel route between Aviemore and Carrbridge. Subject to obtaining the planning consent and completing land acquisition, those works will be included within the now earlier Dalraddy to Slochd section.

Secondly, Transport Scotland will continue to investigate the potential introduction of temporary traffic signals at the A923 Dunkeld junction and an associated reduced speed limit. Assuming that those proposals are confirmed, our target is to deliver those improvements during the 2026-27 financial year.

Thirdly, we will continue to prioritise road safety along the corridor. In 2025, we completed a £5.2 million package of short-term measures. We continue to work in partnership with Police Scotland and our wider road safety partners to respond, where appropriate, to any safety concerns on the route through our established processes, including the A9 safety group.

The 2023 delivery plan provided certainty on the target dates for key early milestones, as well as allowing for a further decision-making process to be completed in late 2025. That decision-making process has led to the 2026 delivery plan that I am announcing today, which provides further detail and certainty on the target dates for key milestones for the remainder of the dualling programme.

The Government is fully aware that much work remains to be done to deliver this vital major infrastructure programme, and we are relying on the contracting industry to work collaboratively with us to achieve that outcome. The Government has made it clear that completion of the A9 dualling programme by the end of 2035 is an absolute priority, and we have now set out clearly how we intend to achieve that goal.

I hope that today’s update further reassures the communities that are served by the A9 that there is a clear, robust plan for dualling the A9 between Perth and Inverness by the end of 2035. The visible work that we can all see on the route will continue to ramp up, and I want to take the opportunity to thank all road users for their patience while we undertake this vital work to upgrade Scotland’s arterial route, which will support the Highlands and benefit all of Scotland.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

I think that Sue Webber has selective memory when it comes to the financial constraints on capital projects that her party put on the Parliament and the Government. If she had been listening to the statement, she would have heard that I stated that the project is within the original budget, so the costs are not increasing in the way that she describes.

She implies that somehow the project is stalling. When was the last time Sue Webber actually drove the A9?

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

If she did, she would see the groundwork that is happening from Tomatin to Moy. How can the project be stalling when those works are happening at the north and the south ends of the A9 as we speak?

As she will know—[Interruption.]

Undoubtedly she has driven the A9 recently, which makes me wonder why she asked the question.

With regard to the budget, the cabinet secretary, in her comments yesterday, referred to the one-year budget and the investment there. I refer the member to the budget items at levels 2 and 3—she can find them in the budget documents and in the spending review; that is where the funding is.

We have said clearly that when we get to the latter sections of the A9 in particular, the work will be funded by revenue transferred to capital. The full funding of the requirements for the 2035 completion has been set out; we have identified how we are going to fund that and we have set out the programme. That is very certain indeed, and I refer the member to the new plan so that she can have a look at the budget figures and identify that we have delivered and are delivering.

The project has construction work happening now, and I encourage all members, if they want to have confidence that it is happening, to go and see the work on the A9.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

I refer the member to table 9.01 on page 28 of the spending review. The figures for trunk road network safety adaptation, maintenance and improvement are contained in the spending review, as is the next one-year budget for 2026-27. The review covers a number of years, so the figures for the A9 will have both capital and resource funding. The member will see the increase in the budget, which is reflected as we move to the latter stages of the spending review.

I deliberately wrote to the Net Zero, Energy and Transport Committee to advise that I would be making a statement about whether we would be using MIM contracts or capital funded contracts. What I have just announced has been baked in to the budget provision for one year, as well as the comprehensive spending review for future years. That is how it has been organised, which is why I can come to the chamber to deliver the statement that I have just made. I am conscious of time, Presiding Officer.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

There is an opportunity to bring forward the Dalraddy to Slochd route. We know that there have been safety concerns about a number of junctions on the A9. Work on the three junctions serving Aviemore and Carrbridge will help to improve road safety. That will mean that that section of the road will become the first of the remaining sections to go to procurement. After the framework agreements have been established, the next stage will be to move to develop that area. That will be very welcome, as will the active travel section, which a number of people have been interested in.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

I am sure that the member will have been in the chamber in 2023 when the then cabinet secretary set out the 2023 delivery plan. I reassure him that all the milestones in that delivery plan had been approved. The member is quite right to identify that there has been an adjustment. The Glen Garry to Crubenmore section will go to procurement in 2027, with dualling operational in 2034. That will be a longer period for construction and some of the central sections may take longer. We have to look at what will happen to the Pass of Birnam, depending on the timing and results of any public inquiry, should that happen. The Glen Garry to Crubenmore section will allow us to at least try to get the Dalnaspidal junction into fairly early development. I know that that had been raised previously from a safety point of view.

The remainder of the contracts will be resequenced, but there are benefits within that. I hope that the member can appreciate that we are trying to optimise the remainder of the programme, with completion by 2035.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

The previous Conservative UK Government did not inflation-proof its capital budget. At the time, we forecast that that would have resulted in a nearly 10 per cent real-terms cut in our capital funding over the medium term. We should also remember that the previous UK Government stripped £6 billion out of our budget.

Despite facing significant demands on our capital budget, from inflationary pressures, economic uncertainty, and the energy and cost crises, we are using all the levers that are at our disposal to top up our capital funding through ScotWind. We will continue to prioritise capital funding to eliminate child poverty, grasp the opportunities of net zero, boost economic growth through our infrastructure plans, and maintain services. We can do that only with the funding that is available to us, which has been severely hampered by Westminster Governments.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

I am being as open as I can be. I have come to the chamber whenever there is anything to announce.

Having a dedicated committee is a matter not for me, but for the next session of Parliament. However, I have indicated to the current convener of the Net Zero, Energy and Transport Committee that I think that transport would get more attention if the committees were readjusted. The current committee is diligent in its work and has received regular six-monthly updates from Transport Scotland officials. I am also open to being examined by the committee on the provision.

I think that the way in which the programme has been set out has balanced what it means for contractors in terms of the market and how we manage that constant work, which Sue Webber does not seem to understand is happening now. We have to balance the work that is done with the needs of drivers and we have to try to prevent frustrations.

Ms Grant is right to identify the issue that she raises but, if we want the A9 dualled, there will need to be construction work, and our contractors are working very hard to minimise disruptions, as I think that people who travel on the Tomatin to Moy route appreciate already.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

I have limited information before me today, but I will be happy to point Rona Mackay to a number of projects. I am pleased that the comprehensive spending review has funding in it that will help to make improvements at the Rest and Be Thankful on the A83 main artery west, and that, with regard to the road from Inverness, the budget and the spending review contain funding for advance works on the A96 next year, and to progress the work on the Inshes to Smithton route and the Nairn bypass in particular.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

I recognise those issues, which is why, in my statement, I addressed some of the issues around the A923-A9 junction. There have been local representations about trying to manage them, and we discussed the matter at the most recent meeting of the A9 safety group, in relation to what can be done with our contractors. That is why we are exploring the possibility of implementing a speed reduction, along with, potentially, signalling.

On the idea of a temporary roundabout, I note that there have been a significant number of objections made and concerns raised about that from people in the Pass of Birnam and Dunkeld area. If the issue goes to a public inquiry, as it might do, it will not be possible for work to proceed on a temporary roundabout.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

In terms of the risk factors, some disruptions are outwith the control of contractors. For example, severe weather over lengths of time can cause issues.

We are planning the project as tightly as we can. In my opening remarks, I said that we would have to work with contractors to ensure that we can deliver the project. That has already happened, and I am sure that it will continue to happen.

The framework agreement will provide more certainty, which will be helpful. However, the on-going risk aspects are something that I and future Governments, as well as future committees of this Parliament, will consider as we progress over the years ahead, towards the delivery date in 2035.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

I make the point that the Highlands and the central belt both benefit from the dualling of the A9.

We have already carried out many additional projects. Given Clare Adamson’s earlier question about private finance, I point out that we use private finance when appropriate. The Aberdeen western peripheral route and the M8, M73 and M74 motorway improvements all include that element, and the payments for them are identified. We must ensure that we have value for money.

There are limits to our borrowing. If people want us to use additional funding, our borrowing limits would have to be increased. However, we will pursue the A83 works and the Inverness to Nairn section. Obviously, there are constant improvements on the A75 and the A77, but the work on the A75 bypasses is important, as well.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

Regarding the northern section, Tomatin to Moy is a northern section that is being worked on now. It will be done by the spring of 2028, and the Dalraddy to Slochd section by 2032. That will mean that, on completion by 2032, there will be 38 miles dualled from Inverness to Kincraig.

That information on those 38 miles should reassure Edward Mountain about what is happening in the north. That is one of the significant changes in this work, but, as I mentioned, there will be an area—Glen Garry to Crubenmore—that is due by the end of 2034. I said that we are delivering the first sections on target.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

The statement was specifically about the A9, and the A9 safety group continues to meet. Some of the consequences regarding safety improvements that I mentioned in my statement came from that group.

Any death on any of our roads is regrettable. There was one fatality on the A9 Perth to Inverness section in the operational records that we have—although sometimes those figures can alter—but we need to be constantly vigilant. That is why I put a great deal of emphasis on road safety investment, and £12 million is being spent on delivering casualty-reduction measures and speed reductions on our trunk road network.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

Competitive bids are what is required. I think that Fergus Ewing is being selective. I know that he likes to dwell on the past—I understand that—[Interruption.] We must learn the lessons of that and then move forward. That is what the 2023 delivery plan set out.

I correct the member: the Tomatin to Moy procurement began in September 2023, the contract award was made in 2024 and the dualling operation is due to be complete by spring 2028.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

In relation to the A9 and providing certainty, we are trying to set out for the constituents of Jamie Halcro Johnston—and, indeed, for the constituents of all members across the Highlands—what the work will mean for their area and what will happen locally. Community involvement is essential, and I have been asked by a number of members to look into issues for individual constituents.

The point about energy and planning is important. That is why I, as Cabinet Secretary for Transport, have been encouraging Transport Scotland to engage, and ensuring that it does so—particularly with our renewables sector in relation to different plans. Jamie Halcro Johnston is perhaps talking about actual delivery, whereas I am talking abut transportation requirements, but it is an essential part of our infrastructure planning, and I am very cognisant of what he said.

Jamie Halcro Johnston can write to me to explain what, in particular, he is seeking me to do. I am in regular correspondence about the interests of individual constituents—not least with the First Minister and other members who have constituency interests along the A9.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

Inshes to Smithton is clearly an important part of the A9 and the connection to the A96. That is where the budget has provided for early advance works to take place, similarly to the Nairn bypass. We will need to look at the procurement method, which would determine which phases of the A9 can be developed and when. However, our commitment to the full dualling of the A96 is unwavering.

In terms of the work and the pressures on the fiscal position, I have set out that, in relation to the Inverness to Nairn aspects, we would expect advance construction early on. Construction work and procurement will certainly take place in the next spending review, and we would see construction of those two parts during the next spending review. At the same time, we will be working on progress improvements eastwards, including on the Elgin bypass. Steps in taking forward an Elgin bypass will include further route development.

Fiona Hyslop SNP The Cabinet Secretary for Transport · Linlithgow
link

Anybody will know—I am sure that Davy Russell will know from his experience—that construction costs and inflation have been particularly problematic over recent years.

I agree with Davy Russell that capital infrastructure is a major driver for economic growth. If he can speak to his Westminster counterparts and the Labour UK Government to ensure that this Parliament and this Government get more capital, we can drive ahead our infrastructure projects. In the meantime, we will use our resources appropriately and deliver, as I have set out in the statement today.

  1. Deputy First Minister Responsibilities, Economy and Gaelic Debate · 1
  2. Mossmorran Task Force Questions · 4
  3. Mossmorran Just Transition Fund Questions · 16
  4. Ferguson Marine Questions · 7
  5. Gaelic Language and Culture (Young People) Questions · 4
  6. Glasgow (Economic Performance) Questions · 7
  7. Young People not in Education, Employment or Training Questions · 9
  8. A96 Dualling (Economic Impact) Questions · 5
  9. Pension Contributions (West of Scotland Local Authorities) Questions · 4
  10. A720 Sheriffhall Roundabout (Grade Separation) Questions · 6
  11. Budget 2026-27 (Prostitution Support and Exit Services) Questions · 4
  12. Employer National Insurance Contributions (Cost to Local Government) Questions · 6
  13. Non-domestic Rates Revaluation (Business Support) Questions · 6
  14. Business Rate Discount (Retail, Hospitality and Leisure Premises) Questions · 5
  15. Budget 2026-27 (International Development) Questions · 13
  16. PFI and PPP Payment Obligations (Local Authorities) Questions · 7
  17. Points of Order Procedure · 10
  18. A9 Dualling (Programme for 2035 Completion) Statement · 43
  19. Children (Care, Care Experience and Services Planning) (Scotland) Bill: Stage 1 Bill debate · 43
  20. Point of Order Procedure · 2
  21. Children (Care, Care Experience and Services Planning) (Scotland) Bill: Financial Resolution Bill debate · 2
  22. Business Motions Business motions · 3
  23. Parliamentary Bureau Motions Business motions · 2
  24. Decision Time Decision time · 4
  25. Football Members’ business · 56
  26. Correction Procedure · 1

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.