PE2095 seeks to improve the public consultation processes for energy infrastructure projects. The petition calls on the Scottish Parliament to urge the Scottish Government to review and seek to update section 3.2 of the energy consents unit’s “Good Practice Guidance for Applications under Section 36 and 37 of the Electricity Act 1989” document to address the concerns of communities about the lack of meaningful, responsible and robust voluntary and pre-application consultation by transmission operators on energy infrastructure projects, and to explore all available levers to strengthen community liaison and public participation for the lifecycle of energy infrastructure projects.
We last considered the petition on 11 September 2024, when we agreed to write to the Acting Minister for Climate Action, the Office of Gas and Electricity Markets and the National Energy System Operator.
I should have said that the petition was lodged by Margaret Smith, who I understand is with us in the public gallery.
In its response, Ofgem underlines that planning consultation does not lie within its remit. Development of the options, scope, design, planning and delivery of projects are the responsibility of the relevant transmission owner, NESO and other relevant authorities, prior to Ofgem’s final decision on cost efficiency. However, Ofgem’s expectation is for transmission owners to engage effectively with local communities, and it states that stakeholders who are interested in infrastructure projects are welcome to submit responses to any relevant Ofgem consultations on efficient funding for transmission projects.
The response from NESO indicates that it balances any proposed new network infrastructure against four high-level objectives, one of which is the impact on communities. While NESO puts forward a recommendation, it is the responsibility of the transmission operator, at the next stage of project development, to decide on potential route corridors and types of infrastructure to use. NESO’s expectation is that operators will consult with local communities and planning authorities on the proposals.
The response from the Acting Minister for Climate Action highlights that a joint review that was undertaken by the UK and Scottish Governments has concluded, with a consultation expected to launch. He states that proposals include a statutory pre-application community and stakeholder engagement process, which would apply to all transmission infrastructure projects. That consultation was launched, and has closed, since the minister’s response was sent in October last year, so it is now historical.
The minister also refers to some additional Scottish Government work on developing guidance for pre-application engagement with communities. The minister says that the Government aims to engage with communities on their views before the guidance is finalised. At the time of the minister’s response, which was whenever, that work had just started.
We are joined by two of our parliamentary colleagues: Tess White, who is a veteran of the committee in the early months of this parliamentary session, and Douglas Lumsden. I know that you would both like to say a few words to the committee, which would be gratefully received, although it is not a speech to the chamber. Have you tossed a coin as to which of the two of you feels that they would like to speak first?
You have nominated yourself, Ms White.