I commend Laura Hansler for bringing the petition to the Parliament. I believe that it has been signed by several thousand people.
Last year, 13 people lost their lives in incidents on the A9, and 12 of those occurred on sections of the A9 that are single carriageway. There is evidence that the risk of fatality or incapacitating injuries as a result of incidents is three times greater on single carriageway than on dual carriageway, and the risk is 10 times greater on single carriageway than on motorway. There are no dual carriageway links in the Highlands; therefore, for a Highlander—a Highland resident—the chance of dying on the road is between three and 10 times greater than for people living in the central belt. Every death has been a tragedy for families and has caused absolute devastation. That is the backdrop that has brought representatives from nearly all parties to the conclusion that we need to get to the bottom of what is happening.
My suggestion is that there should be a parliamentary inquiry. Perhaps the Net Zero, Energy and Transport Committee could be approached privately to see whether, if it wishes, it has the time to undertake such an inquiry, given its busy work schedule. If the net zero committee is not able to undertake such an inquiry, I suggest that this committee carries it out.
The important point is that an inquiry is required. Why? There are several questions to be considered, but there are two main ones. I would be interested to hear what Murdo Fraser and Rhoda Grant say about this, because we have been working cross party—including with the Liberal Democrats—on the issue, which is good.
The first of the two main questions is about what exactly went wrong with the Tomatin to Moy section. Around the spring of 2021, it was announced that the work would be going ahead, and it was only fairly recently that we heard that it would not go ahead. What happened in that intervening period? Why did it go wrong, and will a retender solve the problem or could it lead to the same situation, with apparently only one bidder left, at a price that was reported to be unacceptably high?
The second and perhaps the main question—and this is the thrust of my recommendation—is about the scope of the inquiry, which should be on how we can most swiftly complete the dualling of the A9 between Perth and Inverness. How can that be done and what procurement options and choices should be carried out?
I have had extensive discussions with people in the civil engineering sector, including the Civil Engineering Contractors Association, which is the representative body. Those discussions have led me to the conclusion that the industry believes that, if things proceed as they do at the moment, where we procure one section consecutively after another and only build one at a time, given that it takes three years minimum for each section—one year to procure and two years to build—and there are nine remaining sections, the work will be completed in 2050, because nine threes are 27 and 2023 plus 27 years is 2050. The prospect of the road not being dualled until 2050 is utterly unacceptable to all parties and certainly to my constituents in the Highlands.
This is the final point that I will make, convener, because I appreciate that you have given me some latitude. The very same senior industry insiders tell me that, if everything is done as swiftly as it could be done, and if companies—if they can be persuaded to do the work by Transport Scotland—have the capacity to do it, the dualling could be completed by around 2030.
The key is the procurement options, and I think that Transport Scotland recognises that the current model of procurement, in which all the risks are passed to contractors, has resulted in a situation with one company leaving Scotland entirely and another company no longer bidding for roads, leaving a limited pool of potential bidders from whom competitive bids can be acquired. In that circumstance, competitive bidding might well again lead to a scenario with no competitive bids, particularly since it costs about £500,000 to prepare a bid and four or five companies would have to do the same preparation work four or five times over. Therefore, a framework contract, which I understand is applicable in Highways England, some local authorities and Scottish Water, would seem to be the way ahead. That would allow the dualling of several sections of the road to be done, as well as parts of the A96, which should also be dualled and the dualling of which from Smithton to Auldearn, including the Nairn bypass, is another Government commitment.
An inquiry into all those things by a parliamentary committee would allow us all to display critical but supportive forensic questioning of Transport Scotland, the minister and industry figures in order to get the work done. Frankly, people in the Highlands and throughout Scotland have been frustrated and, in many cases, angry that the pledge that the Scottish Government made has not been kept and, furthermore, that there has not even been an apology for that.