Good morning, and welcome to the 34th meeting in 2017 of the Rural Economy and Connectivity Committee. I remind everyone to ensure that their mobile phones are on silent.
Agenda item 1 is an update on the Forth replacement crossing. This evidence session will take us forward from our previous update. On 27 November, the committee received a written update from Transport Scotland providing details of the snagging work that will start this week and will require partial closure of the new crossing for several days. I welcome from the Scottish Government Michelle Rennie, the director of major transport infrastructure projects, and Lawrence Shackman, the project manager. From Amey, we have Mark Arndt, who is representing the operating company for the Forth bridges.
Lawrence, would you like to make a short opening statement?
I would like clarification on a matter. During your answer, I think that you said that it was a works defect, but previously you said that it was a design defect. Is it a design defect because the joints were not known about, or is it a defect in the surfacing?
Gail Ross has a question. Just before I move on, I remember hearing evidence that one of the reasons for the bridge opening not coming as quickly as was originally anticipated was that resurfacing could not be done in cold weather. It appears that you are now doing resurfacing at potentially the coldest time of the year. Is that right, or have I misunderstood?
I can confirm that you kindly sent a letter to the committee outlining the costs—which came to £3.5 million—and one or two other points. Thank you for that.
Mark, you can very much take it that your answers are to do with the bridge and leave it at that. You have made quite a clear statement on that, but if you want to add anything, I am happy to take it.
I am not sure that that is in anyone’s gift to say at the moment.
The point has been made that it would be very helpful for the committee to have a list of the on-going works to the Queensferry crossing, and following Peter Chapman’s questions, it would be helpful for the committee to have a schedule of proposed works to the Forth road bridge so that we know what work is to be undertaken.
Sadly, we are now out of time. I thank the three witnesses for giving evidence to the committee.
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.