Forth Replacement Crossing (Update}

Wednesday 29 November 2017 Rural Economy and Connectivity Committee About 09:30–10:15 Evidence session 129 contributions · 14 speakers

Speakers

Showing Stewart Stevenson only · show everyone

Stewart Stevenson’s contributions

12 contributions
Stewart Stevenson SNP Banffshire and Buchan Coast
link

Now that the bridge is a success, I can confess that I was, as the then Minister for Transport, Infrastructure and Climate Change, responsible for the legislation that led to its being built. I took through the Forth Crossing Bill, apart from stage 3—as a result of that year’s winter’s snow—for which Keith Brown was the minister.

As the convener mentioned, some snagging work—which, I note, is around the joints—is to be done shortly. Historically, the joints have been the big issue on the Forth road bridge. Will the joints be a big problem on the new bridge? Was that expected?

Stewart Stevenson SNP Banffshire and Buchan Coast
link

Will all the associated costs lie with the contractor?

Stewart Stevenson SNP Banffshire and Buchan Coast
link

Does that include the costs of the diversions and things like that?

Stewart Stevenson SNP Banffshire and Buchan Coast
link

I have quite a lot of questions. This all seems to have come at quite short notice—the issues have been a bit of a surprise. Is that a fair comment?

Stewart Stevenson SNP Banffshire and Buchan Coast
link

How would you describe the potential disruption that you are planning for?

Stewart Stevenson SNP Banffshire and Buchan Coast
link

We have already talked about the lessons learned about how we manage relationships, but are there any internal lessons for Transport Scotland to learn about how it might manage things? When I lectured postgraduates on project management, I always said, “Successful projects need an intelligent buyer.” Is Transport Scotland learning any lessons from this for procurement, financial planning control, relationships with contractors and so on to ensure that it is a more intelligent buyer in future?

Stewart Stevenson SNP Banffshire and Buchan Coast
link

Did you have a risk register that was agreed and shared between you, as the purchaser, and the contractor?

Stewart Stevenson SNP Banffshire and Buchan Coast
link

It is clear that you have learned a lot of lessons. I know that other members have questions.

Stewart Stevenson SNP Banffshire and Buchan Coast
link

I am quite happy for Michelle Rennie to continue, if she wants to do so.

Stewart Stevenson SNP Banffshire and Buchan Coast
link

Well, let me ask one supplementary, if I may. A big area of risk in any big project is change, and there is no big project in which there is no change—I think that a project dies when there is no change. Did you have an effective method of identifying, controlling and allocating responsibility for change, which will help you in future projects?

Stewart Stevenson SNP Banffshire and Buchan Coast
link

I worked on software projects. They were much more complex in change terms but we always had the option of dumping the difficult changes into phase 2. You had no phase 2.

  1. 09:30 Forth Replacement Crossing (Update} Evidence session · 129
  2. 10:15 Implications of European Union Referendum Committee business · 133
  3. 12:00 Subordinate Legislation Subordinate legislation · 13
  4. 12:00 Subordinate Legislation Subordinate legislation · 1

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.