Now that the bridge is a success, I can confess that I was, as the then Minister for Transport, Infrastructure and Climate Change, responsible for the legislation that led to its being built. I took through the Forth Crossing Bill, apart from stage 3—as a result of that year’s winter’s snow—for which Keith Brown was the minister.
As the convener mentioned, some snagging work—which, I note, is around the joints—is to be done shortly. Historically, the joints have been the big issue on the Forth road bridge. Will the joints be a big problem on the new bridge? Was that expected?
We have already talked about the lessons learned about how we manage relationships, but are there any internal lessons for Transport Scotland to learn about how it might manage things? When I lectured postgraduates on project management, I always said, “Successful projects need an intelligent buyer.” Is Transport Scotland learning any lessons from this for procurement, financial planning control, relationships with contractors and so on to ensure that it is a more intelligent buyer in future?
Well, let me ask one supplementary, if I may. A big area of risk in any big project is change, and there is no big project in which there is no change—I think that a project dies when there is no change. Did you have an effective method of identifying, controlling and allocating responsibility for change, which will help you in future projects?
I worked on software projects. They were much more complex in change terms but we always had the option of dumping the difficult changes into phase 2. You had no phase 2.
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.