A90/A937 (Safety Improvements) (PE1236)

Wednesday 14 December 2016 Rural Economy and Connectivity Committee About 12:00 Petitions 5 contributions · 4 speakers

Speakers

Choose an MSP to read only their contributions

The record

5 contributions
Edward Mountain Con The Convener · Highlands and Islands
link

The committee will consider two public petitions. The first is PE1236, by Jill Fotheringham, on A90/A937 safety improvements at Laurencekirk. The petition was previously considered on 26 October, when the Minister for Transport and the Islands agreed to write to the committee with further information on an indicative timescale for the design, development and delivery of the proposed project.

We have heard more about that today. Members will note that a letter has been received from the minister that indicates the Scottish Government’s intention to identify a preferred junction layout by 2018 and, provided that no objections are raised in response to the draft order, to begin construction in 2021. The cabinet secretary confirmed that today.

I invite members’ comments on the petition.

Mairi Gougeon SNP Angus North and Mearns
link

I know that we have just heard from the cabinet secretary, but I am keen for us to keep the petition open. A previous petition on the issue was closed in the past, and closure remains a concern for the petitioner and for the people who have campaigned for the Laurencekirk junction, because I think that work stalled when the previous petition was closed.

We have heard a commitment that the work will take place but, if we can keep the petition open—even if it does not appear on our agenda as regularly as it has over the past few months—that will show the committee’s commitment to the Laurencekirk junction project progressing.

Mike Rumbles LD North East Scotland
link

I agree. The problem is that people out there do not understand why the Scottish Government is taking three years to get through the first part of the process. They feel that the issue has been kicked into touch. If it has not been, and if the Scottish Government is getting on with the work, people need to know that. It will be extremely helpful to receive in writing the information about the three-year process. That is probably all the information that we need, and I would like to keep the petition open until we get it.

Stewart Stevenson SNP Banffshire and Buchan Coast
link

A previous petition on the subject from Jill Fotheringham was closed and did not lead to action. It would therefore be fair to her to keep this petition open until we are absolutely sure that there will be a project, but I agree that we should not gratuitously bring it back for further discussion in the absence of progress, unless we feel that the project is slipping.

Edward Mountain Con The Convener · Highlands and Islands
link

As no one wishes to speak against that suggestion, it seems that there is a consensus that we should keep the petition open and that we should press the cabinet secretary for the detailed information about the timeframe that he talked about, make those details available to the petitioner as soon as we have them and review the petition when it is appropriate to do so. I give an undertaking to the two committee members who have a constituency interest in the issue to keep it on the agenda. Do we agree to that course of action?

Members indicated agreement.

  1. 10:00 Forth Replacement Crossing (Project Team Update) Evidence session · 88
  2. 10:45 Major Transport Infrastructure Projects (Update) Evidence session · 93
  3. 12:00 Public Petitions Petitions · 5
  4. 12:00 Public Petitions Petitions · 5

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.