Thank you very much. Good morning.
We are very pleased to be here to update the committee on progress that has been made since our previous appearance at the committee on 7 September and the committee’s site visit on 31 October.
I can confirm that the date for opening to traffic for the Queensferry crossing continues to be May 2017 and that the project outturn cost range remains at £1.325 billion to £1.35 billion.
The weather has continued to be challenging, but the Forth crossing bridge constructors—FCBC—consortium, which is the contractor, has generally been successful in mitigating that.
In the past 12 months, the site workforce has averaged 1,242, with a peak of more than 1,400 during the summer and the autumn. Following the committee’s visit to the site at the end of October, I am sure that committee members will have an appreciation of the size and scale of the works that are being undertaken and the skill and dedication that are required from the site workforce to complete this outstanding project.
I will focus specifically on progress on the principal contract.
On the south side, the road works are substantially complete. Final landscaping and planting works are currently in progress.
On the Queensferry crossing, 107 of 110 deck units have been lifted into place. One more deck unit is to be lifted in the next few days, and the final two are to be lifted in the new year. In October, the centre tower deck fan achieved the milestone of being the longest free-standing balanced cantilever structure in the world. Guinness World Records has verified and recognised that. However, the record existed for only about three weeks, as the closure units at either end were lifted and connected to form a continuous structure all the way from the north abutment to pier S2, leaving a gap of only 36m.
The installation of the concrete deck on the south approach viaduct is progressing northwards from the south abutment, and 36 out of the total of 42 concrete pours that are required have been completed. On the north side, all 12 concrete deck pours that are required have been completed and the travelling formwork that was used to construct them has been dismantled and removed. Installation of the large expansion joints at the south end of the bridge has just started.
On the north-side road works, the wind-shielding barrier has been installed on the west side of the Ferrytoll viaduct. That provides a good indication of how the finished Queensferry crossing will look. The new Ferrytoll junction is now in use, and traffic is passing under the new overbridges. Traffic on the A90 was recently transferred on to the new south-bound carriageway between the Admiralty and Ferrytoll junctions. Work on the reconfigured park-and-ride facility at Ferrytoll is nearing completion, and the new turning circle for buses is currently being completed.
With the completion of deck lifting in January, the focus will shift on to the deck-finishing activities, which include the installation of the crossing stay cables, erecting the wind-shielding and vehicle-restraint barriers, fitting motorway gantries at the towers, waterproofing the concrete deck and the road surfacing. In addition, the three tower cranes, which have been a landmark on the skyline for so long, will be dismantled, and the temporary trestles, platforms, cofferdam and caissons at each tower will be cut up and removed.
Those activities are the more visible ones to the public, but inside the towers, piers, abutment buildings and deck structures, work is progressing on the installation, testing and commissioning of the mechanical, electrical and plumbing systems as well as the extensive structural health monitoring system, which is very important to modern bridge structures.
Community relations continue to be extremely good, with the north and south community forums having been combined into a single entity for the November meeting and for the future. More than 68,000 people have now attended events relating to the FRC, nearly all of them being held in the contact and education centre. Among them, more than 19,000 pupils from schools all over Scotland have attended science, technology, engineering and maths-related activities.
The level of interest and excitement around the opening of the bridge is continuing to increase, and we are continuing to develop the plans for that, on which we expect to be able to make an announcement in the new year.