We come to the final petition on the agenda today, petition PE1610, by Matt Halliday, which calls for an upgrade to the A75. Members have a submission from the Scottish Government providing an update following the transport summit held in Dumfries on 22 August 2016.
Members are advised that the Minister for Transport and the Islands has announced an update to the strategic transport projects review and a review of the national transport strategy. Options for dualling the A75 will be considered as part of those reviews. The Scottish Government could not provide a timetable for the process but has said that it will keep the committee informed.
Members also have a submission from the petitioner, who has expressed concern at the uncertain timeframe for making a decision on the issue. Mr Halliday is concerned that the local region is negatively affected by the current condition of the A75, and that the impact may worsen if action is not taken to upgrade the road soon.
I think I mentioned this the last time we discussed the petition. I was at the summit that the transport minister chaired. The action points that he took away from that included consideration of a range of inputs from the floor.
As we mentioned before, the A75 is a Euro-route. I think that we also mentioned before that a high volume of articulated lorries pass through some small villages, and not all of those villages have speed cameras and the like. Furthermore, there is the potential impact on Stranraer as a port if that part of the Euro-route is not dualled, given the evidence that a couple of ports south of the border have had significant investment and development. There is a perceived threat to Stranraer.
I would like to move the petition on quite swiftly. I suggest that we ask the Minister for Transport and the Islands to come and give us an update. The other possibility is to bring in the MSPs who represent the area. They will have more information than I do on the matter. It is an issue that needs to be brought to the fore and pushed on.
Any MSP is free to come to the Public Petitions Committee. We have had experience of that with other petitions. People will be aware of that invitation.
The question is about not having an absolute timetable. Would it be worth writing to the minister to say that, given the uncertainty and concern, we would expect a timetable? If that is not forthcoming, or if there continues to be uncertainty on the matter, we could consider it further in the new year. I do not know how long such reviews normally take, but I am sure that people locally will want to know that there has been an active review, as opposed to the issue going into the long grass.
If I remember correctly, the minister suggested that there would be a reply to the conference by the end of the year. That is why I am suggesting that we ask the minister to come to the committee and update us on where the Scottish Government is on the matter.
I would be happy to defer the issue until the very start of the new year, and then ask for a further update. I am not sure what merit there would be in bringing the minister here before the end of the year.
I suggest that we write to the Minister for Transport and the Islands, saying in general terms that the committee wishes some certainty around the timescale. The Government must have one, even if it has not made it public. Its officials must be working to an expectation of when they should be reporting. If the Government can share that information with us, well and good. If it continues to say that it does not have a timescale—when we get a response—we could perhaps make a decision on whether to have the minister in. Is that agreed?
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.