Agenda item 2 is evidence on the Auditor General for Scotland’s report “The 2014/15 audit of NHS 24: Update on management of an IT contract”. We will hear from two panels. I welcome our first panel: Ian Crichton, interim chief executive, NHS 24; and Margo McGurk, director of finance, NHS 24. I understand that Mr Crichton has a brief opening statement to make.

Paul Martin Lab The Convener · Glasgow Provan
link

Thank you, Mr Crichton. I have a few questions relating to Audit Scotland’s report. Are you the accountable officer for NHS 24?

Paul Martin Lab The Convener · Glasgow Provan
link

Why are you the interim chief executive?

Paul Martin Lab The Convener · Glasgow Provan
link

What is your annual salary?

Paul Martin Lab The Convener · Glasgow Provan
link

Do you receive the same annual salary for your other post?

Paul Martin Lab The Convener · Glasgow Provan
link

Will you confirm what the overspend position is, from the time that the project was first developed until present?

Paul Martin Lab The Convener · Glasgow Provan
link

Will you confirm what that is?

Paul Martin Lab The Convener · Glasgow Provan
link

Will you explain what “sunk cost” means?

Paul Martin Lab The Convener · Glasgow Provan
link

So you have already spent £70 million.

Paul Martin Lab The Convener · Glasgow Provan
link

The overspend is £46 million—is that correct?

Paul Martin Lab The Convener · Glasgow Provan
link

Let me clarify this point for the benefit of the public. I cannot think of many people who would argue with the fact that £46 million is a significant sum of money.

Paul Martin Lab The Convener · Glasgow Provan
link

And £41.6 million is a significant overspend. I estimate that about 1,900 nurses could be employed for that money. Do you find the situation unacceptable?

Paul Martin Lab The Convener · Glasgow Provan
link

Do you think not only that you should apologise on behalf of the organisation but that the organisation should be ashamed that it has found itself in this position?

Paul Martin Lab The Convener · Glasgow Provan
link

Should it not be ashamed, though?

Paul Martin Lab The Convener · Glasgow Provan
link

You were brought into the organisation in September. Who do you blame? Who do you think is accountable for the organisation’s failures? There are 1,500 individuals, and you advised me that not all of them could be blamed. I understand that position, but tell me who is responsible for the failures in the organisation.

Paul Martin Lab The Convener · Glasgow Provan
link

I will decide what I want to hear. We will ask the questions and you will answer them. Please do not make assumptions about what I want to hear. Today, the committee is seeking evidence based on a report. Following that report, we want to raise issues about governance.

Is the accountable officer responsible for the systemic failures that you refer to?

Paul Martin Lab The Convener · Glasgow Provan
link

Are you referring to specific individuals who were part of a management team?

Paul Martin Lab The Convener · Glasgow Provan
link

There is a £41.6 million overspend. Are you advising me that none of the individuals who were part of the management team, or the accountable officer—the former chief executive—have to look at themselves in the mirror and realise that they may have been responsible for some of the decisions—

Paul Martin Lab The Convener · Glasgow Provan
link

Hear me out.

Do those individuals not have to realise that some of the decisions that they made may have had an impact on this significant overspend? The money was not spent by itself and it was not managed by itself. There was a management team in place to do that work, was there not?

Paul Martin Lab The Convener · Glasgow Provan
link

It was not an information technology system that took the decisions, was it?

Paul Martin Lab The Convener · Glasgow Provan
link

Individuals took the decisions.

Paul Martin Lab The Convener · Glasgow Provan
link

They were paid to take the decisions. As you have confirmed, you are paid a salary of £130,000, so there is a significant responsibility placed on you.

Paul Martin Lab The Convener · Glasgow Provan
link

Those individuals are paid to do the work. Did those individuals take decisions that effectively resulted in a £41.6 million overspend?

Paul Martin Lab The Convener · Glasgow Provan
link

They are gutted by a £41.6 million overspend. Any other organisation would be bankrupt. If this was Apple or another company, it would find the situation unacceptable.

Paul Martin Lab The Convener · Glasgow Provan
link

But do they provide the funds to keep propping up an organisation that is clearly losing money?

Paul Martin Lab The Convener · Glasgow Provan
link

Very briefly, and then I will move on to Mary Scanlon.

Paul Martin Lab The Convener · Glasgow Provan
link

Who should have picked up on that?

Paul Martin Lab The Convener · Glasgow Provan
link

That accounts for the total amount.

Paul Martin Lab The Convener · Glasgow Provan
link

It would be helpful if I make it clear to all that the witnesses can provide an opinion on what happened previously, but it will be for the next panel to give specific factual information about the project.

Paul Martin Lab The Convener · Glasgow Provan
link

This is your final question.

Paul Martin Lab The Convener · Glasgow Provan
link

I have some brief final questions. Have you put in place measures to ensure that the errors that were made are never made again? We have discussed the contract flaw. Can you give us an assurance that for as long as you are the accountable officer there will not be a recurrence?

Paul Martin Lab The Convener · Glasgow Provan
link

As the accountable officer, how many contracts have you signed since September?

Paul Martin Lab The Convener · Glasgow Provan
link

Have you personally reviewed every document that has been signed that is similar to the flawed contract with Capgemini?

Paul Martin Lab The Convener · Glasgow Provan
link

What has been put in place to ensure that your director of finance, who is with you today, provides you with necessary information?

Paul Martin Lab The Convener · Glasgow Provan
link

How do you prevent that? Can you?

Paul Martin Lab The Convener · Glasgow Provan
link

I asked a specific question. If the director of finance, who is sitting next to you, decided not to provide you with information because of a contract flaw that she thought it would not be in her interests to report, what would happen?

Paul Martin Lab The Convener · Glasgow Provan
link

If the Scottish Government were to say, “We’re not giving you the money”, where would you go from there? Would the organisation be bankrupt?

Paul Martin Lab The Convener · Glasgow Provan
link

As we know, the Scottish Government has asked a number of boards across the sector to make cuts. I know that £60 million-worth of cuts have been proposed in the budget of NHS Greater Glasgow and Clyde over the next five years. How can the Government possibly guarantee that you will be provided with the necessary funding? What would happen if it were just to turn off the tap and say, “Sorry, we’re not going to provide it”? Where would you go from there?

Paul Martin Lab The Convener · Glasgow Provan
link

We should be careful here, colleagues. Asking the panel to comment on previous events is acceptable, but I think our next witness will be able to answer questions about specific events.

Paul Martin Lab The Convener · Glasgow Provan
link

I thank Mr Crichton and Ms McGurk for their contributions this morning. I suspend the meeting for five minutes before we move on to the next agenda item.

11:05 Meeting suspended.

11:09 On resuming—

Paul Martin Lab The Convener · Glasgow Provan
link

We will continue with agenda item 2, which is on the AGS report entitled “The 2014/15 audit of NHS 24: Update on management of an IT contract”. I welcome John Turner, the former chief executive of NHS 24. I understand that Mr Turner has a brief opening statement.

Paul Martin Lab The Convener · Glasgow Provan
link

Thank you, Mr Turner. I will open the questions by confirming that you were the accountable officer.

Paul Martin Lab The Convener · Glasgow Provan
link

Was that between 2008 and July 2015?

Paul Martin Lab The Convener · Glasgow Provan
link

What was the salary that you received when you left in 2015?

Paul Martin Lab The Convener · Glasgow Provan
link

On what terms did you leave the organisation? Were you asked to leave or were you offered a voluntary severance scheme?

Paul Martin Lab The Convener · Glasgow Provan
link

So you did not leave with an enhanced package or anything like that—basically, you left the organisation. How much notice did you give?

Paul Martin Lab The Convener · Glasgow Provan
link

Can you confirm for the record what that sum was or what the agreement was?

Paul Martin Lab The Convener · Glasgow Provan
link

We have heard from your opening statement that you accept responsibility.

Paul Martin Lab The Convener · Glasgow Provan
link

So, in a sense, that is accepted. You have shown humility, and people would see that as a step forward. Earlier, we heard that there were some issues concerning the way in which the system operated in your organisation, particularly with regard to governance. Who do you think was responsible, apart from you?

11:15

Paul Martin Lab The Convener · Glasgow Provan
link

Can I just reiterate my question? I understand what you are saying, but I think that it would take us a considerable time to clarify all the arrangements that you had in place.

I am speculating here, but do you feel let down by some members of the team who were around you at that point? All of the issues appear to stem from the contract that was signed. There was a contractual flaw, which, to the public, is just unacceptable. Did you feel let down by any particular group of advisers or whatever?

Paul Martin Lab The Convener · Glasgow Provan
link

Could you be specific about that?

Paul Martin Lab The Convener · Glasgow Provan
link

Did he fail to advise you of the contractual flaw?

Paul Martin Lab The Convener · Glasgow Provan
link

When did he advise you of the flaw?

Paul Martin Lab The Convener · Glasgow Provan
link

So when did he become aware of the flaw?

Paul Martin Lab The Convener · Glasgow Provan
link

Did you review the contract?

Paul Martin Lab The Convener · Glasgow Provan
link

Let us say that I sign a mortgage agreement with my bank, but my solicitor has given me incorrect advice and I end up signing for something that I was not advised of when I signed the contract. If I subsequently find that I am responsible for something that I should not have been—there is something in the contract that should not have been there—my understanding is that I can take action against the solicitor who gave me advice. Why did that not happen on this occasion? You obviously feel let down by the director of finance, and I can understand that—you have made that issue clear, and that is for further discussion. However, let us deal with the legal advice that you received. A specialist solicitor was providing you with advice. What would the legal adviser have been paid?

Paul Martin Lab The Convener · Glasgow Provan
link

A company that had been given several hundred thousand pounds’ worth of work provided advice specifically to you to say, “We’re more than happy for you to sign this document, Mr Turner. This is our legal advice.” However, something was omitted from the final document. Is that company not responsible for that?

Paul Martin Lab The Convener · Glasgow Provan
link

Why did you not take action against the company when that became apparent?

Paul Martin Lab The Convener · Glasgow Provan
link

But that would have been within the five years.

Paul Martin Lab The Convener · Glasgow Provan
link

With respect, I understand where you want to focus your energy and resources. However, the organisation now finds itself in £41.6 million-worth of debt. If that overspend was not provided by the Scottish Government, the organisation would need to close down and people would lose their jobs. Should pursuing the matter of the incorrect legal advice that you received not have been a priority?

Paul Martin Lab The Convener · Glasgow Provan
link

You are just repeating what you said, Mr Turner. I am just making a point that seems pretty straightforward to me. You are advising me that the solicitor provided advice to you that subsequently led to you signing a document, which has now cost the public purse £41.6 million, and you are advising me that it is not a priority to pursue that legal adviser. Again, that is a failing on your part. I accept that you have shown humility today. However, you are the accountable officer and you tell me that you were incorrectly advised, so why not take action against the solicitors who are responsible and, for that matter, your director of finance? What happened subsequently?

Paul Martin Lab The Convener · Glasgow Provan
link

What advice did you give the board? Did you not say to the board, “We should be pursuing the two individuals who advised us to sign the document”?

Paul Martin Lab The Convener · Glasgow Provan
link

So is it still being considered?

Paul Martin Lab The Convener · Glasgow Provan
link

Finally, what was your advice to the board?

Paul Martin Lab The Convener · Glasgow Provan
link

I understand, but I am asking a straightforward question. You find yourself here today and you have lost your job as a result of a document that was signed that, looking at it now, really should not have been signed. Did you not say at the time, “Listen, we’re facing significant challenges because of a flawed document that you asked me to sign”? What was your position on that? Forget about the legal advice that you received—what was your personal advice to the board?

Paul Martin Lab The Convener · Glasgow Provan
link

Okay.

I pass over to Mary Scanlon.

Paul Martin Lab The Convener · Glasgow Provan
link

Can you be clear about names as well? Can you provide names rather than titles, please?

Paul Martin Lab The Convener · Glasgow Provan
link

I ask you to reflect on the fact that you were at NHS 24 from 2008 to 2015. During that time, the accountable officer’s role changed from being that of an NHS manager, in effect, to that of somebody who was in charge of a significant IT project. That is really what happened. You became responsible for something that, when you signed up for the job, was perhaps not such a significant part of the role. Were you out of your depth? We can blame the director of finance, and you have taken responsibility as well, but is the issue not just that you became unable to manage the project? As we have heard, there were issues about tracking the decisions that were taken and the process of managing the contract. Did it not just get out of hand?

Paul Martin Lab The Convener · Glasgow Provan
link

However, you needed somebody to manage the project, did you not? You could bring in all sorts of expertise but, at the end of the day, it became a major IT project. We are talking about significant sums of public money being spent, for which you became ultimately responsible. You have a track record as an NHS manager and in managing staff in different ways, but you did not have any experience of managing a significant IT project, did you?

Paul Martin Lab The Convener · Glasgow Provan
link

Should you not have reflected on that and said that you were maybe not the accountable officer to oversee the project? I ask you that question because you said that you were willing to be part of the process of reflecting on the matter. Was it not that you simply did not have the expertise and too much pressure was placed on you? Hence the management of the project got out of hand. People were not reporting things to you.

Paul Martin Lab The Convener · Glasgow Provan
link

You overspent £41.6 million, so you could have done a lot better. If the tap had been turned off—if the Scottish Government had said that it was not giving you any more money for your IT project—1,500 people would have lost their jobs, so should you not have reflected on the significance of the project and said, “I really can’t do this”? You demonstrated humility today—after the event—but could you not have looked ahead and said that you were not in a position to manage it and it was not for you?

Paul Martin Lab The Convener · Glasgow Provan
link

Yes, but I am asking about you. You were the accountable officer. If you asked me to be the manager of Manchester United, I could not. I do not think that there is anybody in this room who could do that. We are not qualified to do it, and it is a significant task. I am asking you whether you should have said, “Wait a minute. This is significant. I do not have expertise in this IT project. I am a manager of NHS staff. That is what I do and where I come from. Really, this is not for me”?

Paul Martin Lab The Convener · Glasgow Provan
link

At the end of the day, you had the responsibility. You had to ensure that those advisers were brought in. You can bring in all the players that you want, but you were the person who needed to manage the players whom you brought in and you did not do that effectively, because they did not feel that they had the confidence to come to you. Mr Crichton advised us that there would be no blame game and that staff could advise him that there had been faults in the system. That did not happen on this occasion, did it?

Paul Martin Lab The Convener · Glasgow Provan
link

The staff did not feel that they could advise you, so the management process that was in place was not as effective as it should have been. Is that not the case?

Paul Martin Lab The Convener · Glasgow Provan
link

I want to ask a final quick question about the legal advisers. I take it that, when the flaw in the contract was uncovered, the legal advisers had to start making representations to the various parties to find out whether the contract could be reconciled. Is that right?

Paul Martin Lab The Convener · Glasgow Provan
link

Did they charge for that work? Did they bill the organisation for that?

Paul Martin Lab The Convener · Glasgow Provan
link

But my question is this: you have advised us that Mr Stewart had instructed the solicitors to look at ways in which the contract could be clarified, but did the legal advisers bill NHS 24 for undertaking that work?

Paul Martin Lab The Convener · Glasgow Provan
link

If they had agreed that that was their issue, where is the legal argument? If they accepted that that was their issue, why are we worrying about who is responsible? Is it not very clear that all responsibility should have been placed on the legal advisers, who at that point had admitted their own responsibility? Why was there any debate on the matter? After all, they would have billed you if they had not been responsible.

Paul Martin Lab The Convener · Glasgow Provan
link

I think that the question is crystal clear; in fact, you have actually answered part of it. You have just advised me that the legal advisers uncovered a flaw in the contract and that they said that they were aware that they were responsible for it. Is that correct?

Paul Martin Lab The Convener · Glasgow Provan
link

And they did not bill accordingly. Surely when, later on, the board was considering what action it could take with the legal advisers who provided the advice, it must have been a no-brainer. The argument must have been pretty straightforward; after all, the legal advisers had already advised you that they were responsible for the flaw in the contract. Why was there an argument about taking further action against the solicitors? Earlier you said that when you looked at it you were not really sure whether or not you could take action; you were still considering that, because you were still within the five-year period. However, is the situation not pretty straightforward? They had advised you that they were not going to bill you, because they were responsible.

Paul Martin Lab The Convener · Glasgow Provan
link

So why was there any debate about taking action against them? We are talking about £41.6 million of public money, and you are debating whether to take action against legal advisers who have already admitted internally that they were responsible.

Paul Martin Lab The Convener · Glasgow Provan
link

The board is taking its time, though, is it not? Has it not been reflecting on this for quite a long time now? We are talking about £41.6 million of public money, and it seems to be saying, “Let’s have a think about this.”

Paul Martin Lab The Convener · Glasgow Provan
link

Thank you, Mr Turner.

  1. 10:00 Decision on Taking Business in Private Procedure · 1
  2. 10:00 Section 22 Report Committee business · 514
  3. 12:15 Section 23 Report Committee business · 11
  4. 12:15 Section 22 Reports Committee business · 9

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.