To ask the Scottish Government whether it will provide an update on the progress of the M8 Woodside eastbound viaduct. (S7O-00511)
Official Report · Chamber
General Question Time
This is the draft Official Report. The final version may differ.
link
To ask the Scottish Government whether it will provide an update on the progress of the M8 Woodside eastbound viaduct. (S7O-00511)
Extensive and essential concrete repairs are required to joints. We anticipate that the eastbound carriageway will reopen in early 2027 and we expect the westbound works to be completed in the second half of next year.
It is opportune that I update the Parliament that we expect the costs of the completed project to be in the region of £175 million to £185 million. I thank Pauline McNeill for her continued interest in the matter and I thank residents, businesses and commuters for their continued patience while the essential works are undertaken.
link
I hope that the cabinet secretary shares my disappointment, because the road was supposed to be opened in autumn 2026 after five years of work. I was not aware, but I now know, that the road will be opened in the early part of 2027.
Will the cabinet secretary commit today to giving the public and my constituents better engagement with Transport Scotland on the progress on this very important road? I know that he shares my view on the critical importance of the M8 for the east and west of Scotland, but it is about time that we had more up-to-date information on when the road will be complete.
link
Like me, Pauline McNeill has been under the viaduct and seen the extent of the essential works that have been required. She will be cognisant of the issues that relate to the existence of a sewer in a place that was not anticipated, the proximity of the Strathclyde Partnership for Transport subway and the need to ensure that that remains safe, and the procurement challenges that undoubtedly exist because of global matters. If there is more work to be done, I will be quite happy to engage with the member. I share her disappointment, but we anticipate the eastbound carriageway being opened in early 2027. I hope that that is some comfort to road users, residents and businesses, who I know want the work to be completed as quickly as possible.
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.