To ask the Scottish Government what consideration it has given to compensating businesses in Fochabers and Mosstodloch in light of delays to the completion of works at the A96 Fochabers bridge. (S7O-00216)
Official Report · Chamber
General Question Time
This is the draft Official Report. The final version may differ.
link
To ask the Scottish Government what consideration it has given to compensating businesses in Fochabers and Mosstodloch in light of delays to the completion of works at the A96 Fochabers bridge. (S7O-00216)
I certainly sympathise with those in Fochabers who have learned that the works will continue into November. I understand their frustrations in that regard. Those are essential works.
There is no statutory funding in place, as Mr Eagle is all too well aware. However, I can assure him and people in the local area that every effort is being made to ensure that the works are completed as quickly as possible.
link
I believe that the delays to those works mean that they will now go into December, and, as the cabinet secretary will know, they are on a critical part of the A96. The problem is that some of the affected local businesses—which are quite small—buy stock months in advance. The works have put huge financial pressure on them over the last few months, and they are now worried about what will happen next year.
If compensation is not possible, will the cabinet secretary look into reviewing guidance to ensure that notification occurs as early as possible when there are such works in the future?
link
Clear and consistent communication with the public in that respect is essential. I know that Mr Eagle’s comments will be heard by Amey and colleagues in Transport Scotland.
It is important for the chamber to recognise and understand that there are in excess of 2,000 bridges on our trunk road network. Putting in place a compensation mechanism, to which Mr Eagle initially alluded, would not be proportionate or practical. However, I can certainly take away his suggestion on improving communication with local businesses.
link
I was pleased to meet the cabinet secretary last week, and he will recall that we discussed the roadworks on the Spey bridge when we met. As he set out, those works are essential, but he recognises the disruption and the impact that the closure is having on businesses and the community around Fochabers and the wider area. Can he assure my constituents that Transport Scotland will work with Amey to explore all options to expedite the works, including weekend and evening works on the bridge?
link
I first thank Laura Mitchell for her continued efforts to ensure that her community’s voices are heard in respect of the desire to see continuation of the work on the A96 dualling, which is incredibly important.
We discussed the Fochabers bridge last week, and I can offer her the reassurance that, as I understand it, work on alternate weekends is being taken forward. Work is also already taking place overnight.
It is important that that work is concluded as quickly and as swiftly as possible. The work is essential to ensuring the safety of the bridge and road in the long term, but I recognise the impact that it is having on the member’s constituents.
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.