To ask the Scottish Government, in light of the recent announcement that the total projected cost of MV Glen Rosa has risen by £12.5 million to £197.5 million, whether it will confirm how much further public funding will be required before the vessel enters service. (S6T-02875)
Official Report · Chamber
MV Glen Rosa (Public Funding)
Topical Question Time
Speakers
Choose an MSP to read only their contributions- Kate Forbes SNP 5
- Edward Mountain Con 3
- Stuart McMillan SNP 1
- Katy Clark Lab 1
The record
10 contributionsLast week, the chief executive of Ferguson Marine advised the Net Zero, Energy and Transport Committee that the estimated cost to finish building the Glen Rosa had increased by £7 million. To account for potential risks, the business has allocated an additional £5.5 million of contingency, resulting in a total forecast cost to complete of £197.5 million.
In line with normal practice, the Government is carefully assessing the information provided to understand the full implications of the revised timetable and costs. Although I understand that the final stages of building and testing a complex vessel are highly technical and some risks become clear only at that point in the process, the further delay and increased costs are still extremely disappointing, particularly for island communities that rely on these services. Ferguson has planned to hand over the vessel in quarter 4, and we would expect it to enter service six weeks after handover.
On 13 May last year, Graeme Thomson and the Deputy First Minister each wrote to the Net Zero, Energy and Transport Committee. Graeme Thomson said that he was “comfortable” with the new plan and the revised costings for the Glen Rosa. The Deputy First Minister stated the Government’s
“expectation that the senior leadership at Ferguson Marine must demonstrate capability and accountability in the delivery of MV Glen Rosa”.
Now that there is a further increase of £12.5 million—not £7.5 million; there was a contingency sum in there that, it was hoped, would never be spent—does the Government have any confidence in the board and new chief executive of Ferguson Marine?
I have great confidence in the board and the chief executive. As the member will know, Graeme Thomson was newly in the door at that point—I think that, by 13 May, which is the date that Edward Mountain cited, he had been in the job for about 13 days. We have also recently appointed a new chair. Between them, they probably have more experience of shipbuilding than any of their predecessors, so I have confidence in them. That does not take away in any way from how regrettable the latest change is.
Let us be clear. When the chief executive officer moved in, he delayed reporting to the Net Zero, Energy and Transport Committee so that he could find out the facts on the ground. He delayed that report and wrote that letter when he did. We will now end up with a ferry worth £55 million that has cost us £197.5 million. If Kate Forbes has confidence in the board while the rest of Scotland does not, surely she should resign from overseeing Ferguson Marine, because she has been ignored and her position has been totally undermined.
The member will recall that only about two months are left before I will no longer be in this place.
On the chief executive and the board, off the back of the changes that were made earlier last year, we put in place a new structure in order to query, challenge and scrutinise the figures. That is working well, and issues have been identified late in the process. We appreciate that that is far from ideal. However, the accuracy of the figures that have been put to the committee are being challenged by the Scottish Government, and the expectation is that the board and the chief executive, both of whom signed off on the most recent budget forecasts, will be held to account for the forecasts that they provided to the committee.
link
Given the new structure that has been referenced by the Deputy First Minister, can she provide reassurance that the Scottish Government continues to seek both social and economic best value in delivering vessels with Ferguson Marine?
My top priority has been the completion of the Glen Rosa, so that we are able to improve the lifeline services for our island communities through a more sustainable and better-quality service, which is what they deserve. Considerable time having been spent in the completion of the Glen Rosa, my firm view is that it must be completed as quickly as possible.
I also agree with Stuart McMillan, who has worked tirelessly to represent his constituents who work at Ferguson Marine and the wider community in Inverclyde, that we will continue to support the talented and dedicated workforce at the yard and ensure the best value for those who rely on the vessels.
link
Does the Deputy First Minister agree that this is yet another failure by the management, rather than the workforce, at Ferguson Marine? In her role as finance secretary, will she say more about what is being done to provide support to those who are suffering as a result of the situation—the islanders on Arran and the community in Ardrossan—and what financial support she is putting in place?
On a point of information, I am no longer the finance secretary, which is probably relevant to that question.
I think that Katy Clark’s first point was about the talent of the workforce. I absolutely agree with her, in full, that the talent, ability and skills of the workforce were never in doubt. In the most recent tenders for new work, the feedback that has been received has pointed to the quality of the work and the need to build on that reputationally, in order to secure new work.
Motions, questions and votes
Linked from this item of the Official ReportIn this meeting
Everything on 3 Feb 2026 →- 14:00 Time for Reflection Time for reflection · 2
- 14:04 Business Motion Business motions · 2
- 14:05 Motion of Condolence Procedure · 11
- 14:46 Business Motion Business motions · 5
- 14:48 Topical Question Time Questions · 1
- 14:48 MV Glen Rosa (Public Funding) Questions · 10
- 14:48 Qualifications Scotland Questions · 20
- 15:05 Prison Population Statement · 38
- 15:35 Desecration of War Memorials (Scotland) Bill: Stage 1 Bill debate · 24
- 15:49 Prostitution (Offences and Support) (Scotland) Bill: Stage 1 Bill debate · 199
- 18:11 Scottish Hospitals Inquiry Statement · 45
- 18:48 Children’s Wellbeing and Schools Bill Bill debate · 6
- 18:53 Decision Time Decision time · 8
- 19:00 Scottish Games Network’s “Level Up Scotland: A National Action Plan for the Scottish Games Sector” Members’ business · 14
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.