To ask the Scottish Government what actions Caledonian Maritime Assets Ltd will take to improve the resilience of Ardrossan harbour, once it has been acquired. (S6O-05600)
Official Report · Chamber
General Question Time
This is the draft Official Report. The final version may differ.
link
To ask the Scottish Government what actions Caledonian Maritime Assets Ltd will take to improve the resilience of Ardrossan harbour, once it has been acquired. (S6O-05600)
As I outlined in my statement to the Parliament on 3 March and at the subsequent Ardrossan task force meeting, which was held on the same day, CMAL, as the new statutory harbour authority, is expected to take forward immediate works at the harbour to improve resilience. To ensure the continuation of the two-port operation, CMAL has identified immediate minor works and has therefore already procured replacement fenders and will repair navigation lights. Those initial works will be undertaken as soon as possible and are planned to not disrupt continuing services, thus ensuring improved resilience of the Arran berth.
link
I thank the cabinet secretary for returning Ardrossan harbour to the public sector and for that very positive response. Will she confirm not only that CMAL is primed to boost resilience and immediately take control of the site but that plans to fully redevelop that vital Ayrshire port are well advanced and that the regeneration and renewal will ensure a first-class, 21st century, fully functioning port that will serve the communities of Ardrossan and Arran for 60 years or more?
It is acknowledged that the purchase of Ardrossan harbour is a significant milestone, but momentum on the project is needed. CMAL will review the original detailed design proposals and scope of works, including for the Arran berth realignment. An indicative timeline for design and procurement works is being drafted. Based on current estimates, works could begin in June 2027, but that is subject to the procurement stage, approval of funding and contractor award and mobilisation.
link
I understand that the save Ardrossan harbour campaign has been involved in discussions with the cabinet secretary about support for businesses over the past few years. It tells me that the cabinet secretary said that that issue could be looked at when the harbour closes for redevelopment. Will the cabinet secretary ensure that campaign groups such as save Ardrossan harbour and Arran for Ardrossan harbour are at the forefront of decisions that are made? Will she outline when compensation discussions can take place?
A number of partners will be involved in the redevelopment, not least North Ayrshire Council, which co-chairs the Ardrossan task force. The other evening, we discussed ensuring that, at future meetings, future aspects of development are more fully embraced by the local community, as well as issues relating to immediate investment in the harbour.
I have indicated that, when the harbour has to close for the major redevelopment that is required, we need to improve the port. Everybody knows that, and that is part of the purchase arrangement. We need to ensure that the businesses that will be affected at that time are supported. I have put that on the record and discussed it with the task force, but the decisions will need to be made by a future Government.
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.