Official Report · Chamber
Topical Question Time
link
To ask the Scottish Government how it will work with the United Kingdom Government on the recently announced £200 million investment in Grangemouth, as part of the national wealth fund. (S6T-02380)
link
Last week, the First Minister announced the new £25 million Grangemouth just transition fund, as part of this Government’s nearly £90 million of planned support to Grangemouth.
We welcome the recent UK Government announcement that £200 million will also be allocated for Grangemouth from the national wealth fund. We are already engaging with the UK Government on that and we are seeking clarity on the details of the fund to ensure alignment with our interventions, in order to maximise the impact for the workforce, the community, and business development.
I am committed to continuing my collaborative relationship with the UK Secretary of State for Energy Security and Net Zero in order to secure a long-term and sustainable future for Grangemouth. I hope that Daniel Johnson can show a similar collaborative approach for Grangemouth by backing the budget—and the money that we have announced—at stage 3 this afternoon.
link
Our position on the budget is clear. This is such a big issue that I do not think that the workers at Grangemouth would thank us for playing politics with it. [Interruption.] It is an important point.
Of all the numbers of great importance, the most important is that 400 people have been given redundancy notices. Given that this is the start of the hard work to attract investment in, which is what the funds are expected to do, what steps will the Scottish Government take alongside the United Kingdom Government to attract that investment? Critically, will those sums be available to fund project willow?
link
First, I am not playing politics. I am making the point that it is important that we all get behind any money that is pledged by any Government to support the workers at Grangemouth. I do not mean that to be a party political point.
This is not the start of the hard work by either Government. Since the new UK Government came in, we have had a much more collaborative relationship than we had with the previous UK Government and we have been working very hard, initially to prevent the closure and ask Petroineos to make a different decision. We have been unstinting in that, and that is still the course of action that I would like to see.
As regards the moneys and what will be done with the £200 million and indeed the £90 million, including the £25 million just transition fund, I want to work with the Grangemouth future industry board and the UK Government on that, because they are critical. We have been working together for a good two years now on what needs to happen in the Grangemouth area. Our £25 million just transition fund will be deployed this year. We have a precedent in how the north-east and Moray just transition fund has worked and some of the projects that it has supported for oil and gas workers and, indeed, the supply chain.
The first thing that I will do after the budget is—touch wood—passed this afternoon, once I know that the moneys are coming to the just transition fund, is to meet my officials to make sure that we get early engagement with the Grangemouth future industry board to talk about how that money can be deployed and the mechanisms that will be put in place for that. I will have a similar conversation with Ed Miliband, I hope very soon—I will be writing to him this afternoon—to discuss how the £200 million can work with that money.
There is a great deal of interest in asking supplementary questions, so I would be grateful for concise questions and responses.
link
With the £25 million from the Scottish Government and £200 million from the UK Government on top of the £100 million city deal, this is one of the largest industrial interventions that this country has seen in decades, but it is not just about the money. A number of policy and regulatory changes will be required, particularly if we are looking at project willow and biorefining. Will the cabinet secretary set out how those things will be examined and how she will take the actions that we expect to see in the project willow public document in the coming days, so that we can implement those changes?
link
I have been talking about some of the regulatory changes that the UK Government will have to make since well before the Labour Government came into place. I had those discussions with the Conservative Governments. I am pleased to say that I have now had a lot more feedback in our discussions about what might need to be done. Project willow has been essential in that regard because, as well as looking at some areas in which the refinery can adapt and become a different type of plant for sustainable aviation fuel or biorefining, it requires regulatory change. That will be outlined in project willow.
The UK Government has the most locus in that, but we are already aware of what some of those policy changes should be, and I stand ready to support the UK Government in making the right decisions that will allow some of the future industries—in the short term, I hope—to be viable and ensure that they are competitive, given that other countries might already have the regulatory changes in place and we must not be left behind.
I, too, welcome the additional moneys, although I note that the UK Government application process will be time consuming, with money being made available as debt or equity on the probability of a sufficient return on investment to the UK Government. For businesses to make applications at pace, there must be, as the minister stated, considerably more policy certainty. I know that she has been pursuing the matter, but has she had any advice on it thus far from the UK Government? Will there be a shift in its current attitude to carbon capture and storage and the Acorn project, which is a critical enabler of green hydrogen, or the possibility of Grangemouth and the associated work becoming a test site for sustainable aviation fuel? I repeat that policy certainty will be needed as much as finance to encourage confidence in business investment.
link
What Michelle Thomson has just outlined is absolutely critical. I welcome the response from the Prime Minister to the First Minister’s call for the UK Government to provide its fair share of support for Grangemouth, but I agree that we need policy certainty, particularly on carbon capture, utilisation and storage.
I have had repeated discussions with the former and current UK Governments and remain deeply frustrated that there is still no clarity on timelines, funding and criteria for the Acorn project, which, I think, will provide that policy certainty and, as I have been told by people who have an interest, ramp up the investability that is in the plant. I agree whole-heartedly that giving the Acorn project the go-ahead is the next intervention that the UK Government should make, and I think that it should be made immediately. I hope that all members will support me on that, because it would be a game changer.
link
Daniel Johnson is right that this is about jobs. However, it is not just about 400 jobs; it is about nearly 3,000 jobs. That is the economic impact assessment of what is happening at Grangemouth.
It is a great pity that we do not have more detail on the £200 million and exactly how that will be distributed and used. It is also a great pity that we still do not have much detail about the £25 million. I would really like to hear a lot more detail about how that money is going to be used.
I would also like the minister to tell us about the report on project willow. I remember her saying that that would come out by the end of this month. This is the end of the month. When exactly will we see it? Colin Mackay of STV saw it. He even wrote a detailed report on it. I do not understand why we have not seen it. Has Petroineos got a copy of the EY report on project willow? How much did it cost? How specific are the project willow proposals? Are they costed? Where will the investment come from? Those are all burning questions on the minds of the people of Grangemouth.
link
There are a lot of questions in that. I will not have time to answer all of them. I will be able to write to the member about some of the detail—in particular, the cost of project willow. That involved money that was put in by the Scottish Government and the UK Government. None was put in by Petroineos.
The report is due by the end of the month, and nothing has been said to me to indicate that that will slip in any way. As I mentioned, the budget needs to be passed today for the £25 million to be released but, once the £25 million has been secured, through the Parliament’s voting for it, it is my number 1 priority to look—particularly with the Grangemouth future industry board, because this is about not just the refinery but the industrial complex of Grangemouth as a whole—at how that can be deployed and used. It will be able to be deployed in a way that makes a difference only if we work together with the people of Grangemouth and the stakeholders in it, much as we did with the north-east and Moray just transition fund, which has been very successful.
link
All the money that has been announced for Grangemouth is absolutely welcome, but trying to get money out quickly does not always mean that that money gets spent in the correct projects for the area. At the Grangemouth community council meeting last Thursday, 120 people were in the room, asking about the industrial future of Grangemouth and wanting to resolve some of the disconnect between them and industry. How can the cabinet secretary implore people to resolve that disconnect as well as ensure that projects are value for money and will support both skills and the local community?
link
Both the local council and the community council are members of the Grangemouth future industry board. That is the vehicle by which any disconnect will be resolved. As I have said, the £25 million can be deployed over the next year, but it has to be deployed in the right way, to create more opportunities for the workers, supply chain and communities. The supply chain, the communities and the workers will dictate how that money is spent. I need to work with them via the vehicle of the Grangemouth future industry board, of which some of the people whom Gillian Mackay has mentioned are members.
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.