To ask the Scottish Government what the total monthly running cost of Ferguson Marine is. (S6O-04285)
Official Report · Chamber
Ferguson Marine (Running Cost)
Portfolio Question Time Deputy First Minister Responsibilities, Economy and Gaelic
Speakers
Choose an MSP to read only their contributions- Kate Forbes SNP 5
- Edward Mountain Con 2
- Liam McArthur LD 1
- Stuart McMillan SNP 1
- Neil Bibby Lab 1
- Paul Sweeney Lab 1
The record
11 contributionsThe running costs are a commercial matter for Ferguson Marine to answer. Monthly charges to the Scottish Government fluctuate, based on the work that is undertaken under current contracts.
Let me help the Deputy First Minister in answering that question. The monthly under-recovery, as quoted by Ferguson Marine, is £1 million per calendar month. It has been suggested that it costs £20 million a year to run Ferguson Marine if there is no recovery of any works. That is £84,000 per job. How will the Scottish Government fund that if it does not give the small vessels contract to Ferguson Marine?
I hope that the member is not recommending that we break procurement law. The yard is tendering for new vessels, and that will be managed as it should be in accordance with procurement law.
The number that the member quotes, if I understand it correctly, covers all employment at the yard, plus overheads in central administration costs. Perhaps he can clarify that.
Now that the Glen Sannox has been completed, the bulk of the workforce at Ferguson Marine is working on the delivery of the Glen Rosa, and those costs are therefore recoverable.
link
I have a lot of supplementaries here; I will not get through all of them, but I will get through as many as I can.
link
Does the Deputy First Minister agree that the Scottish Government’s £14.2 million investment—as we heard this morning in the Public Audit Committee, £9 million of that is for the next budget year—would be a significant step in helping to develop the yard so that it can secure both public and commercial contracts?
The £14.2 million will be invested over two years. It will support a range of initiatives to improve productivity and will help to give the shipyard the best possible opportunity to bid for and secure new work.
link
Securing future work will be key to securing the future of Ferguson’s yard. Board papers from May last year say that it got positive legal advice on a direct award for the small vessel replacement programme. The GMB union would like to know what the Scottish Government’s reaction was to that advice and why the Government did not act on it. If Ferguson Marine does not get the award of the contract in the first round, will the direct award still be considered for the second round?
As I said in my answer to Edward Mountain, a live procurement process is underway and it would not be appropriate for me to comment on it. It needs to go down the road that is understood for those processes. The Scottish Government has set out an approach to future work, and the Cabinet Secretary for Transport will update the Parliament on the tender and procurement for the second phase of the small vessel replacement programme.
link
Does the cabinet secretary agree that it is essential that the demand signal from public sector procurement underpins Scottish ship building? To achieve that, could she look at emulating what the Australians have done with the Australian marine complex in Perth? It is set up as a common user facility, which means that, regardless of who wins public procurement contracts, the companies can use the infrastructure and the facility in Australia to deliver the programmes.
Right now, we are working with Ferguson Marine to focus on improving productivity and to invest in the equipment and machinery that it needs to update in order to enable the company to compete internationally for procurement work. Irrespective of what ends up happening with the ownership of the yard, our commitment is to continue to invest in it as a shipbuilding facility. The first step is to ensure that it can compete internationally.
Motions, questions and votes
Linked from this item of the Official ReportIn this meeting
Everything on 5 Feb 2025 →- Deputy First Minister Responsibilities, Economy and Gaelic Questions · 1
- Visitor Levy (Scotland) Act 2024 Questions · 10
- Ferguson Marine (Discussions) Questions · 6
- Ferguson Marine (Running Cost) Questions · 11
- Artificial Intelligence Sector Questions · 10
- South of Scotland Enterprise Questions · 8
- Postgraduate Business School (Proposal) Questions · 8
- Night-time Economy (Glasgow) Questions · 9
- Finance and Local Government Questions · 1
- School Building Questions · 7
- Local Government (Staff Recruitment and Retention) Questions · 7
- Local Development Plans (Planning Guidance) Questions · 6
- NHS Fife (Infrastructure Investment Pipeline) Questions · 10
- Income Tax Questions · 5
- “Local government in Scotland: Financial bulletin 2023/24” Questions · 5
- Medication Assisted Treatment Standards Statement · 30
- Addressing Child Poverty through Education Debate · 47
- Health and Wellbeing Census (Third-party Access) Questions · 20
- Business Motions Business motions · 2
- Parliamentary Bureau Motion Business motions · 2
- Decision Time Decision time · 16
- Local Libraries Members’ business · 40
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.