The consenting task group was formed in 2022, just after the Scottish aquaculture council was formed. For about a year, it interrogated and pulled apart what happens at the start of the fish farm consenting process. We took the time to learn about different ways in which we could fit the system together, but we also took the time to build trust, bring people together and build consensus on the way forward, which was a really important component of the work.
The regulatory report was really helpful in setting out that success comes from good multilateral pre-application activities and that, although individual components might look okay, there needs to be much better co-ordination and management. That is what we set out to consider. We have operated in the pre-application space, because that is what the report directed us to do.
We have designed a process that runs the SEPA and local authority consenting processes together. Two case officers—one from SEPA and one from Highland Council—are identified to run the entire process together. SEPA takes hold of the first element, which involves publishing an environmental risk assessment report, following advice from local authorities and other statutory consultees on issues that might need to be considered through the consenting system. That report is published online, and developers are asked to engage with communities, third parties and other interested groups on it and to collect information on any additional issues that they believe should be considered through the consenting system.
It is important to get local stakeholder knowledge at that stage, because SEPA or the local authority might not have knowledge relating to the location of specific protected species, for example. That sort of information is really important. That process also drives engagement between the sector and others at the earliest stage possible. Once the report is finalised and community engagement has been done, the local authority takes the lead on environmental scoping.
As you can tell, it is a detailed and technical process, but the point is that it gets people together early on, in the pre-application phase, and it co-ordinates what is happening. By the end of the process, all the potential constraints should have been identified. There should be agreement on what has to be monitored and collected as evidence to support the application, and everybody should know where they stand in relation to that. Therefore, the follow-on application process should go smoothly.
Although we have lengthened the process in some ways, we are trying to streamline and co-ordinate it so that things run in parallel or at the same time rather than after one another. We recognise that a lot of people comment on SEPA controlled activities regulations—CAR—applications on issues that are relevant to local authorities and vice versa, so having them work together in this space will be important.