To ask the Scottish Government whether it will provide an update on the implementation of the Housing (Cladding Remediation) (Scotland) Act 2024 and cladding remediation programme, including the Scottish safer buildings accord and single building assessment pilot programme. (S6O-03701)
Paul McLennanSNPThe Minister for Housing · East Lothian
With the Housing (Cladding Remediation) (Scotland) Act 2024 and the single building assessment technical specification now in place, we are able to accelerate the pace of delivery. We will shortly provide a timetable for commencement of the 2024 act, prioritising the powers that are urgently needed, including the completion of the SBA standards to sit alongside the technical specification that has already been published.
Pilot assessments have been undertaken for 30 of the pilot entries, with works to mitigate or remediate risks having started on five of those. We continue to work with developers to agree a contract in order to ensure that they can play their part in speeding up progress.
I welcome the progress that has been made through passing the 2024 act and undertaking what the minister has set out, and I appreciate the complex work that Scottish Government officials are doing on the issue. However, many of my constituents remain frustrated at the lack of progress and clear information coming both from the Government and from developers on their particular buildings.
Can the minister provide further insight into when my constituents will start to receive more regular, clear proactive information on when remediation work may start in their buildings and, when it has started, on progress thereafter?
Paul McLennanSNPThe Minister for Housing · East Lothian
I thank the member for that question, and I am grateful for his continuing commitment to his constituents on these issues. We are taking a number of steps to improve communications with residents, including a regular newsletter; improvement to the content and detail of the Scottish Government website; frequent engagement through the High Rise Action Scotland Group; and the development of a pre-assessment charter.
We are shortly going to be refreshing pilot SBA assessments, as we now have the legislative and robust technical basis on which to do so; we will be writing to relevant owners and occupiers to inform them and to ensure that we undertake engagement pre and post that work. I am happy to meet the member to give a detailed update on developments in his constituency.
I would have expected greater urgency on the matter, because Scotland was quite far behind the curve already, certainly in comparison with the rest of the United Kingdom. I would have expected that the frustration that Ben Macpherson talked about would have been communicated to the sector and to the Government, and that action would have been swifter.
What will the minister do in the next few weeks to ensure that we get some progress? We will have that frustration for much longer if he does not address that.
Paul McLennanSNPThe Minister for Housing · East Lothian
We had a meeting this morning, and I have a meeting with colleagues this afternoon, to talk about that very issue. I previously mentioned the 2024 act, which gives us additional powers to ensure that developers move at a quicker pace. We will continue to meet with developers and officials to pick up the pace. I know that progress needs to be quicker; we have acknowledged that, and we will be ensuring that the work moves at a quicker pace.
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.