I thank all the members who have taken part in today’s debate. I will make one point before I move on. My friend Graham Simpson said that building a station is not that difficult. I assure him that a load of my officials would tell me quite the opposite.
The proposal for a new station at Winchburgh can be traced back two decades to the West Lothian local plan in 2004 and the Edinburgh and Lothian structural plan in 2005. As soon as I got involved after my appointment as a minister, I made it a priority to get a good understanding of the issues and, more important, of how to progress the building of the station, which had been promised by the developers in their vision for a new community around the old village of Winchburgh.
I want to use the opportunity of this debate to set out what progress is being made. Creating a new station as part of a large-scale housing development was an ambitious and far-sighted plan, for which I commend the developers and West Lothian Council. I have visited the area with the developers and the council, so I have seen at first hand the excellent work that they have done, and I can clearly see the vision taking shape.
However, what was never clear to me was how the narrative has developed that, somehow, the failure of a station being built over the past two decades is either Transport Scotland’s or the Scottish ministers’ fault or responsibility. It was absolutely clear—I want to ensure that this fact is understood—that the commitment was, and is, developer led. Any political posturing to say otherwise serves absolutely no one, least of all the people of Winchburgh, whom members in the chamber are here to represent.
Perhaps a wee bit of history behind the saga might help to provide some context to the situation. The ambitious plan and application for Winchburgh was submitted by Winchburgh Developments back in 2005. The application included provision for a new trunk road junction on the M9, a railway station and two park-and-ride facilities on the site. Currently, neither the railway station nor the park-and-ride facilities have reached the point of delivery.
A planning condition that was added to the consent by the planning authority allowed for a further assessment to demonstrate the need for a station at a later date. That allowed the application for the site to be granted and discussions to take place about accommodating the station later in the process, but it was still clearly a developer-led ambition.
Following discussions with Winchburgh Developments Ltd, West Lothian Council, Transport Scotland and Network Rail, and further assessments in line with those discussions, it was agreed in February 2015 that the case for the rail station had been demonstrated. Planning permission in principle was granted for the station in 2015, and it was expected that an application for detailed planning consent would follow from the developer in around December 2017. However, that did not happen.
Throughout the period in which a railway station at Winchburgh has been under consideration, the Scottish Government’s policy has been clear that developers are required to provide any mitigation on infrastructure to support their development. At various points in that period, the developer confirmed its intent to fund the station—I have documentation to confirm that fact. However, it has now become apparent that the developer no longer has the available funds to independently provide the required railway station at Winchburgh. Consequently, my officials are supporting the developer and the council in seeking alternative sources of funding to support the delivery of the proposed station.
The historical consideration and approvals in place for the station place no legal obligation on the developer or West Lothian Council to construct Winchburgh station, which is unfortunate, because the local authority had it within its power to put such an obligation in place when granting the final permissions, but it failed to do so. That, added to the progressively worsening financial restrictions across all sectors, has contributed to stagnation in respect of progress on the station over the past several years.
In the meantime, the developer has continued to develop the community at Winchburgh and has successfully funded and delivered, with financial support from the Scottish Government, the new four-way junction on the M9, which opened in February 2023. However, it should be pointed out that that was a requirement of the developer’s planning consent, which was supported—I emphasise this—by my colleague and local constituency MSP Fiona Hyslop only as an addition to the requirement to build a railway station, not as a get-out or an alternative. That was a legal requirement on the developer and should be seen as such and as a direct result of the hard work that was put in by Fiona Hyslop, as the local constituency MSP, along with regional MSPs, in bringing people together in their campaign to raise awareness of the matter.
It is a matter of fact that the station proposal originated as a developer-led proposal that added to the value of the overall saleability of the master plan. I have to say that I agree with that, but it has never been the duty of, or a requirement on, Transport Scotland or the Scottish Government to be the lead promoter on the project. Transport Scotland’s only role in the process was to act on behalf of the Scottish Government as a statutory consultee in the planning process that was led by the planning authority.
Overall, I can confidently say that we have made significant progress in bringing together a collegiate and productive group whose members have all shared the goal of helping the local authority and Winchburgh Developments Ltd make progress on a station that is clearly demanded by local residents and businesses and, of course, to meet the needs of the environment. All the interested parties whom I have met are clear that they share the objective of continuing that progress.
To aid that process, I believe that it was vital to push support for the reformation of the Winchburgh railway station steering group, which Fiona Hyslop had previously successfully done. The group now comprises the developer, West Coast Capital, West Lothian Council, Transport Scotland, Network Rail, the city region deal and the South East of Scotland Transport Partnership—SEStran. They are currently meeting on a four-weekly basis to progress the immediate next steps that are required for delivery of the station. One of the immediate requirements of the steering group is to investigate potential sources of funding to plug the gap that requires to be filled in lieu of the infrastructure elements that the developer has already delivered to support the station or has agreed by way of existing financial contributions.
Work has also been undertaken to review and, where required, to update the business case to support the station proposal. I understand that the developer and the council plan to meet soon to finalise who will perform the lead promoter role and to identify an appropriate project sponsor to lead with the delivery of the station. In my view, it would seem appropriate for the council and the developer to share that vital lead promoter role but, clearly, that will be something that they will decide for themselves.
My officials have reported to me on the productive nature of the first two meetings. I commend all parties for the positive and constructive nature in which they have engaged, and I urge them to continue in the spirit of co-operation and solution finding. I emphasise the need to allow that group the time and space to do the work that is needed and I encourage others, particularly across the chamber, to remove the political opportunism that has become all too apparent in order to let the constructive nature of the developments—