To ask the Scottish Government, further to the finance secretary’s letter to the Finance and Public Administration Committee on 21 November, whether it will provide an update on the delivery of vessels and piers projects, including the small vessels replacement programme and the port works at Ardrossan and Gourock harbours. (S6T-01658)
Official Report · Chamber
Vessels and Piers Project (Update)
Topical Question Time
Speakers
Choose an MSP to read only their contributions- Fiona Hyslop SNP 5
- Jamie Greene Con 3
- Annabelle Ewing SNP 3
- Stuart McMillan SNP 1
- Katy Clark Lab 1
The record
13 contributionsThe Government remains committed to the funding of new vessels and of port infrastructure to support our lifeline ferry services. The small vessels replacement programme is progressing well and, as Caledonian Maritime Assets Ltd has confirmed, it remains on track, with the outline business case for phase 1 nearing completion, before it moves into the procurement phase. That is a crucial part of the process that will help to ensure that we deliver value for money and that vessels and shoreside works align.
Recent confirmation of in-year budgets does not impact on the overall delivery of key investments in the new ferries for our island communities, as first payments will not be due until contracts are awarded.
The business case for Ardrossan and the scope of the Gourock port projects are under review to help to inform robust investment decisions. The various partners in the Ardrossan project have further work to do in the process, following the pause in procurement in the summer, as the scope of the necessary work has been extended. I recently wrote to the Ardrossan task force members on that work.
We continue to make significant investments across our networks, working with CMAL and the operators to improve reliability and resilience of services as we progress. There has been extensive work from CMAL in the design and business case development of the small vessels replacement programme over the summer and autumn, including consultation of island communities. Through work with Transport Scotland, it is progressing well towards the next planned stage of procurement.
I thank the minister for the update.
Let me probe a little bit about what “on track” means in the real world. The Scottish Government investment plan update from two years ago made categorical commitments that seven vessels of the small vessel replacement scheme would be serving island communities within the next five years—that is, by 2026. The CMAL chief executive responded by saying that
“we are not prepared to wait and wait and wait and see small vessels getting older and older”.
However, as we heard in the chamber today, it was also confirmed this weekend that payments will be made only once the shipbuilding contract is signed. It seems that the process has been pushed back a year, because if the payment follows the contract, surely the work will start only once the contract has been signed.
The obvious question is this: in the light of the “reprofiling”—as it is being called—will our island communities see all those vessels in service by 2026, as was originally planned, and, for the sake of Scotland’s shipbuilding yards, including Ferguson Marine in Inverclyde, who on earth will build the ships?
I remind members of the need to comply with the time that has been allocated for both questions and answers.
CMAL’s published corporate plan for 2020-23 indicated an earlier start date, but we all understand why those plans would not have been delivered. CMAL wants progress, and so do I. We work with CMAL very closely. One of the first things that I did when I came into office was visit CMAL to understand what its plans were for the programme.
On delivery of the vessels, we are clearly at the stage that CMAL thought we would be at, which is completion of the outline business case and design, and the move into procurement. We are delivering the funding for the overall vessel programme that we said we would between 2021 and 2026. The small vessel replacement programme will commence building in 2026, with delivery in the following two years, which is the current plan as set out by CMAL.
The funding is promised, but delivery of the vessels is what people are interested in. When will the vessels be sailing around their communities? It sounds as though we are talking about at least 2028, which I am sure will come as a huge disappointment to our island communities.
The harbour improvements, which are also much needed, include the Ardrossan and Gourock upgrades. We were told that the Ardrossan harbour redevelopment construction would be finished by spring or summer 2026. Will the minister update me on whether that is still on track and on plan? That would contradict comments that were made in the letter to the Finance and Public Administration Committee from Shona Robison. She said that the reprofiling will
“push out timescales of future improvements”.
What future improvements will be pushed out or, in other parlance, delayed? Will the harbour redevelopment plans also be delayed, or are they on track?
Vessels will be delivered from 2026, as planned. There will be important alignment between the overall vessel procurement and shoreside investments, which include harbourside investments. That includes the fact that we want to move to electric ferries, because of our desire to improve the system.
On Ardrossan—bear with me, Presiding Officer, because there was a lot of detail in those questions—the member will know that, as I have outlined in the chamber, the improvement works will need to be extended from the original investment proposal. The replacement or strengthening of the Winton pier and the Irish berth at Ardrossan, which ferries use in certain wind conditions to manoeuvre out of the harbour, has expanded that piece of work. North Ayrshire Council and Peel Ports, as the partners in that process, are delivering on-going work to make sure that we have a robust investment decision.
Minister, I need to go to the supplementary question from Stuart McMillan.
link
The minister will be aware of my support for Ferguson Marine’s workforce and for the yard. The small vessel replacement programme is vital to Ferguson’s, particularly because of its history with the three hybrid ferries. In addition to what has been said so far, can the minister provide an assurance that the announcement of the programme will happen early in the next financial year? The minister will be aware of the correspondence that was sent from local MP Ronnie Cowan, Councillor Elizabeth Robertson and me to the Cabinet Secretary for Wellbeing Economy, Fair Work and Energy. Will the minister agree to meet the three of us to discuss the small vessel replacement programme?
It is clear that Stuart McMillan wants to advocate for his constituents and the Ferguson Marine yard, which he continues to do. The yard has to focus on winning future work and getting itself into a state where it can win future work.
In relation to Ferguson Marine, the lead minister is Neil Gray, who I understand has been in correspondence with Stuart McMillan. Our focus has to be for Ferguson Marine to secure the two new ferries, to ensure that the yard has a future and to serve the island communities.
It is clear that there are opportunities in relation to the procurement of the new small vessel replacements. On the needs of islanders and the local economy that Stuart McMillan represents, I understand that relationship. We are considering future vessel contracts from public agencies on a case-by-case basis.
I understand that the Cabinet Secretary for Wellbeing Economy, Fair Work and Energy had an invitation to meet Stuart McMillan, and I hear that that invitation has been extended to me. However, I would need to reflect on what stage we are at in procurement and whether that might be appropriate.
link
Ardrossan waited six years for the Scottish Government to agree terms with Peel Ports while ministers refused to agree to calls to bring the port back into public ownership to make progress. There is now real concern that Ardrossan will lose out to Troon permanently. What is the Scottish Government doing to ensure urgent consideration of a business case for the essential works at Ardrossan harbour? Why has that work been left so late?
It is clear that the issue of public ownership is different from the progress of the different partners in delivering the works that are required for Ardrossan. On my responsibilities since I have been in post, I have wanted to ensure that we have the most robust business case that we can have. For example, North Ayrshire Council has been liaising with the Isle of Arran ferry committee, and has appointed consultants to provide a report. That will not be available until late November, so we could not deliver on that business case as of now. However, that is what partnership working is about. More than one partner is involved. We have been working with them and Peel Ports and looking at the extension of the need for the Winton pier and the Irish berth, which would not have not been in the original proposals that Katy Clark reflected on.
We will move on to the next item of business after a short pause to allow the front-bench teams to change positions should they wish to do so.
Motions, questions and votes
Linked from this item of the Official ReportIn this meeting
Everything on 28 Nov 2023 →- Time for Reflection Time for reflection · 2
- Topical Question Time Questions · 1
- Public Sector Workforce (Update) Questions · 15
- Vessels and Piers Project (Update) Questions · 13
- Heat in Buildings Statement · 34
- Female Participation in Sport and Physical Activity Debate · 56
- Decision Time Decision time · 2
- World AIDS Day 2023 Members’ business · 11
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.