link
To ask the Scottish Government when the final design for the dualling of the A9 Perth to Inverness road between the Pass of Birnam and the Tay crossing will be published. (S6O-01795)
Official Report · Chamber
Portfolio Question Time Net Zero, Energy and Transport
link
To ask the Scottish Government when the final design for the dualling of the A9 Perth to Inverness road between the Pass of Birnam and the Tay crossing will be published. (S6O-01795)
The design work for that challenging section of the A9 is continuing, following a community co-creative process. That process has helped us to form an extremely positive working relationship with the local community and to broaden the vision for dualling that section of the A9. An announcement on the preferred route option is expected to be made in the coming months, after which the preferred option will be further refined, developed and assessed before commencement of the statutory process.
link
The community in Dunkeld and Birnam, and indeed other users of the A9, have been waiting eight years to see a finalised design for the section. I know that there has been extensive engagement with the local community, but that ceased many months ago and we still have not seen a finalised plan, which we were expecting by the end of last year.
Can the minister be more specific about when exactly a finalised design will be published? Perhaps more important, when can we expect the works to be completed for the dual carriageway on that section?
Murdo Fraser will recognise that, having gone through a co-creative process with the local community and having identified their preferred route option, we have to compare that option against other potential route options. There are three other options to consider alongside the one that is supported by the local community. That assessment work is on-going. Once it has been completed by officials, we should be in a position to set out our preferred route option. As I mentioned in my original response, we will then communicate that. I hope to be able to do that in the coming months.
The final aspect is in relation to the procurement process. Before the work can be undertaken, we have to go through the orders process. Obviously, that is a statutory process. Once it has been completed, we will look at the procurement process for that particular part of the A9.
Even now, the Transport Scotland website says that the dualling of the A9 between Perth and Inverness will completed by 2025. If that happens, I will go out and purchase a hat in order to be able to eat it.
Seriously, do we not owe an apology to the people of the Highlands and of Scotland because we will not achieve that target? Shall we not come clean? Above all, when will we bring forward a fresh timetable and the full details of how we will implement one of the longest-standing pledges we have ever made?
I recognise Mr Ewing’s long-standing interest in the issue. I want to reassure him of the Government’s long-standing and on-going commitment to dualling the A9.
A number of factors are being taken into account at the present moment in relation to the procurement process for the next section that we are looking to dual, and that process has been impacted by Covid. It has also been quite significantly impacted by the very significant levels of construction-cost inflation that are being experienced. Because of some of the economic challenges that we now have, we are also having to look at the procurement approach that we take in relation to this particular project.
We are looking at taking forward further procurement in the months ahead. I can also reassure Mr Ewing that we are looking at the forward timetable for the programme in the years ahead.
link
That concludes portfolio questions. We will briefly pause to allow the members on the front benches to change before we move to the next item of business.
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.