To ask the Scottish Government whether it will give an update on the work to upgrade Ardrossan harbour. (S6O-01378)
Official Report · Chamber
General Question Time
link
To ask the Scottish Government whether it will give an update on the work to upgrade Ardrossan harbour. (S6O-01378)
link
The Ardrossan harbour project is currently at the tender design stage, and further work is required. The legal and commercial arrangements for investment at that third party-owned harbour have been challenging. I am frustrated by the lack of progress, but I remain committed to a solution and to progress being made at Ardrossan.
Following our investment, Troon will be used when MV Glen Sannox comes into service until the Ardrossan works are complete. The investment in Troon also provides options for use as an alternative mainland port of refuge in the longer term.
link
The failure by the landowner, Peel Ports, to agree a deal that is acceptable to the public purse has led to a delay of over four years. In the meantime, islanders on Arran, those who use the ferry services, and the Ardrossan people and economy are suffering. Does the minister agree that enough is enough? Will the Scottish Government now take urgent and compulsory measures so that progress is made?
link
I share Ms Clark’s frustration about progress at Ardrossan, but it is also worth noting that the Scottish Government will invest £40 million in ports and harbours services in this year alone. Some ports, such as the one at Ardrossan, are privately owned, which can substantially slow progress in making improvements. Any work also comes at a cost to the public purse, which is why, in my update to Parliament two weeks ago, I made clear my intention to explore with the relevant partners, local authorities and third party owners—including Peel Ports—how we can improve matters.
It is worth saying that extensive work is needed to complete the improvements at Ardrossan and that Troon—which is another private port—will be the temporary mainland port for the service to Brodick while Ardrossan is closed or if hull 801 comes in before the Ardrossan work starts. The work at Troon is now largely complete, but the need for the closure of Ardrossan and the temporary move to Troon has been widely known for some time. That relates, as Ms Clark has said, to the protracted and on-going negotiations with Peel Ports.
The project entered the design stage in April of this year and is being progressed by the project partners. The development work at Ardrossan is being overseen by the ministerial task force, which I look forward to chairing later this year.
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.