To ask the Scottish Government whether it can confirm whether hull 801 will be delivered by May 2023 and hull 802 by December 2023 and within the latest cost to complete budget of £123 million. (S6T-00844)
Official Report · Chamber
Ferries
Topical Question Time
Speakers
Choose an MSP to read only their contributions- Ivan McKee SNP 6
- Edward Mountain Con 3
- Stuart McMillan SNP 1
- Katy Clark Lab 1
- Graham Simpson Con 1
- Alison Johnstone 1
The record
13 contributions
link
The target date for the completion of hull 801—the Glen Sannox—remains by the end of May 2023, and for hull 802 it is by the end of December 2023. The current budget to complete both vessels remains £123 million, as was set out in the Cabinet Secretary for Finance and the Economy’s update to Parliament on 23 March 2022.
The Deputy First Minister and the Minister for Transport were able to see at first hand the progress made on both vessels during their visit to the shipyard on 2 August this year. We continue to press the shipyard to continue to progress to completion of the vessels in that agreed timeframe and within budget.
The answer is that they will be delivered on the latest timescale and on the latest budget. We know that there is only £30 million left in the budget pot and at least another 15 months of build time, so, to be frank, an overspend is probably inevitable.
Given the latest disastrous information on harbour upgrades, in what year will both ferries be operational on their planned routes?
link
As I indicated, the completion dates for the ferries are by the end of May 2023 and by the end of December 2023. Both ferries will go into operation, obviously, after those dates. Work is continuing to make sure that the turnaround in the yard is delivering those results, and the yard is increasingly becoming more competitive to allow it to bid for other business going forward.
There we have it. We have a Scottish Government that does not even know when the infrastructure will be in place to allow the ferries to operate on the routes. We have a Scottish Government that mucked up the contract, with the nationalisation of the yard. It will overspend its budget and delay building the harbour infrastructure that we so desperately need. What more could possibly have gone wrong?
link
The member is incorrect. The harbour infrastructure is being put in place to ensure that the ferries can operate. The completion dates for the ferries are as I have already indicated, and the work continues to make the yard more competitive so that it can bid for and win more work on the open market. That is what this Government is focused on—saving the jobs, saving the shipyard and making sure that commercial shipbuilding on the Clyde has a future.
If we had listened to others, we would not be in that position today, and we would not have saved more than 300 jobs over that period of time. That is what is important, and that is what this Government cares about—the industrial future of that sector on the Clyde.
link
The Scottish Government has demonstrated its crystal-clear commitment to the communities that are served by the ferry services and its strong commitment to ensuring that the proud tradition of shipbuilding continues in Port Glasgow on the Clyde and that jobs are protected from those who would have closed the yard. What can the Government and Ferguson Marine do to give the yard a secure future and guarantee jobs and skills for generations to come?
link
Stuart McMillan is right to highlight the need for us all to work to give a secure future to the yard and to future generations of employees. Potentially, work will be available from the Government; we have said that we will have a small vessels programme, and there will be longer-term proposals to invest in new ferry vessels. We want Ferguson Marine to be in a position to secure some of that work. However, whether work comes from the Government, other public sources or the private sector, the yard needs to be competitive. We have made clear our expectation in that regard, and we continue to monitor progress closely.
A lot of changes have been put in place since the new chief executive was appointed earlier this year, and we can now see, and say, that significant progress has been made and that the yard is back to being a serious contender for future vessel contracts. I hope that all members will welcome and get behind that.
link
The substitute vessel that is being used on the Ardrossan to Arran route is 38 years old. Caledonian Maritime Assets Ltd says that it has looked at more than 600 vessels in recent years but has managed to procure only one. Will the minister confirm when the work on project Neptune will be published, and will the Scottish Government commit to bringing forward a more sustainable plan to build capacity and construct vessels here in Scotland?
link
I make Katy Clark aware that my colleague the Minister for Transport will be in the chamber on Thursday to give an update on those issues. I look forward to hearing from the minister about the progress that has been made and the plans that are in place to address the issues that the member has raised.
link
The minister was asked about harbour upgrades but did not give a very clear answer. The Ardrossan harbour task force was formed more than six years ago, but we still have no agreement on who is going to pay for what or when the work will be done. When will Ardrossan harbour be ready to take the MV Glen Sannox?
link
Graham Simpson will be aware that Peel Ports is the owner of that facility, but the Government is committed to making sure that the issue is resolved. My colleague the Minister for Transport is working on that and has said that we are working to ensure that matters are in place for when the ferries will be operational.
That concludes topical question time.
Motions, questions and votes
Linked from this item of the Official ReportIn this meeting
Everything on 6 Sep 2022 →- Time for Reflection Time for reflection · 2
- Topical Question Time Questions · 1
- Drug Deaths Questions · 8
- Ferries Questions · 13
- Business Motion Business motions · 1
- Programme for Government 2022-23 Statement · 2
- Programme for Government 2022-23 Debate · 84
- Decision Time Decision time · 1
- Commonwealth Games 2022 (Team Scotland) Members’ business · 7
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.