To ask the Scottish Government what new targets it has set for its affordable homes programme. (S5O-04360)
Official Report · Chamber
Portfolio Question Time Communities and Local Government
link
To ask the Scottish Government what new targets it has set for its affordable homes programme. (S5O-04360)
Prior to the current pause in construction, we were on track to meet the 50,000 affordable homes target and we were working hard with all our delivery partners to ensure that the final approvals and site starts were in place. We remain committed to meeting the target, but the impact of the pandemic means that there has been a necessary pause in all housing delivery.
Once activity can safely resume, and when the impact of the pause and the implementation of the updated safe operating procedures has been assessed, we will be clearer about the full effect that the crisis will have on the timing of the delivery of the affordable housing programme.
From the beginning of this parliamentary session to December 2019, we have delivered 31,136 affordable homes, which form part of the more than 91,000 affordable homes that have been delivered since 2007. I thank the housing sector for all its hard work in that delivery, and, when it is safe to restart the programme, I look forward to the continuation of its efforts.
link
Thank you. Pausing the programme means that we are even further behind. It is my view that we were not going to hit that 50,000 affordable homes target, but the minister has a different view. Has he done any work on the figures that will be needed to catch up? I go back to Willie Coffey’s question about when builders can start back on site; I heard the waffle that the minister gave. He has been speaking to the industry for weeks; he knows that builders can restart, and we know that they can, so when can they do so?
There should be no waffle from anybody.
I will start with the last part of the question. We have been working hard with the industry to put in place a phased approach to a return to construction, along with safe operating procedures. As most people do, Mr Simpson has to understand that our moves forward will be dictated by the virus. It is essential that we get it right and that we do not move to a situation where we put people at risk or there are increases in the spread of the virus. We have taken a precautionary approach, in order to balance out exactly what is required. I believe that that is the right approach. I thank the industry and the trade unions for their efforts in all that we have done.
With regard to the affordable housing programme, we have work on-going on how we can move forward. It is my ambition to ensure that we deliver as many affordable houses as we can during this parliamentary session. Our housing partners share that ambition; however, we have to do all that safely.
We need to speed things up, but I will take brief supplementary questions.
link
Thank you, Presiding Officer. Does the minister acknowledge the severe shortage of affordable housing in Edinburgh, which will be exacerbated by the crisis? Is he prepared to increase the level of support to the council, so that it can maximise the number of affordable homes in the local plan that is under development?
We will work with all local authorities on local development plans, but we will also work with them on the delivery of the affordable housing programme. In recent times, Edinburgh has been in a lucky position, because it has benefited from additional resources that other local authorities were unable to spend. We will continue to co-operate with City of Edinburgh Council and other councils across Scotland, as well as other partners, to maximise the delivery of affordable homes throughout the country.
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.