To ask the Scottish Government what progress is being made in completing the snagging work on the Queensferry crossing, which is due to be completed by the end of the year, and whether that will lead to road works. (S5O-03611)
Official Report · Chamber
Portfolio Question Time Transport, Infrastructure and Connectivity
link
To ask the Scottish Government what progress is being made in completing the snagging work on the Queensferry crossing, which is due to be completed by the end of the year, and whether that will lead to road works. (S5O-03611)
I am pleased to report that good progress has been made on the snagging work on the Queensferry crossing. The tower lifts and tower concrete finishing are nearing completion and underdeck painting is well advanced. As I reported to the Rural Economy and Connectivity Committee on 11 September, the contractor has advised that snagging work will be completed by the end of this year, weather permitting. Traffic management will continue to be required at times to enable safe access by operatives when they are undertaking those works. All works that require traffic management are undertaken overnight to minimise disruption to road users.
link
Last night, when I drove across the Queensferry crossing at around 9.30 pm, the northbound carriageway was down to one lane. That is a frequent occurrence, as the cabinet secretary will know, causing a great deal of frustration for my constituents in Fife, particularly when there are traffic delays as a result. I am sure that he will understand the frustration and concern that a bridge that has been open to the public for two years is still facing a large programme of work, which is causing those delays. What guarantees can he give my constituents that the works will not extend past the end of the year? How are the costs of the snagging works being met?
Well—
link
Are they part of the contract, or are they additional costs to the taxpayer—
Get a move on with it, Mr Fraser.
The costs of the snagging works are met by the contractor. I am sure that Murdo Fraser will recognise the significant benefit that has been gained from the opening of the Queensferry crossing. Over the two years, there have been at least 34 occasions when the Queensferry crossing was able to continue to operate but the Forth road bridge would have been closed to high-sided vehicles. I am sure that he welcomes the additional resilience factor that has been provided to his constituents and those beyond his region in being able to cross the Forth during adverse weather.
Murdo Fraser will also be aware that the traffic management that is deployed for the work that is undertaken by operatives cannot commence before 8 o’clock in the evening; even then, it can be delayed if the evening peak continues for an extended period. There have been instances when the traffic management system has not been engaged until 10 o’clock at night in order to allow traffic flows to reduce. I am sure that he will recognise that, in big infrastructure projects, there will always be snagging work that should be undertaken after the infrastructure is in use. He will also recognise that we have to appreciate the health and safety needs of those who operate on the bridge and put in place appropriate measures to consider their welfare while that work is being completed. That is why the traffic management system is required.
The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.