Queensferry Crossing (Snagging Works)

Portfolio Question Time Transport, Infrastructure and Connectivity

Wednesday 2 October 2019 Meeting of the Parliament Questions 7 contributions · 3 speakers Watch on Scottish Parliament TV

Speakers

Choose an MSP to read only their contributions

The record

7 contributions
Murdo Fraser Con Mid Scotland and Fife
link

To ask the Scottish Government what progress is being made in completing the snagging work on the Queensferry crossing, which is due to be completed by the end of the year, and whether that will lead to road works. (S5O-03611)

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

I am pleased to report that good progress has been made on the snagging work on the Queensferry crossing. The tower lifts and tower concrete finishing are nearing completion and underdeck painting is well advanced. As I reported to the Rural Economy and Connectivity Committee on 11 September, the contractor has advised that snagging work will be completed by the end of this year, weather permitting. Traffic management will continue to be required at times to enable safe access by operatives when they are undertaking those works. All works that require traffic management are undertaken overnight to minimise disruption to road users.

Murdo Fraser Con Mid Scotland and Fife
link

Last night, when I drove across the Queensferry crossing at around 9.30 pm, the northbound carriageway was down to one lane. That is a frequent occurrence, as the cabinet secretary will know, causing a great deal of frustration for my constituents in Fife, particularly when there are traffic delays as a result. I am sure that he will understand the frustration and concern that a bridge that has been open to the public for two years is still facing a large programme of work, which is causing those delays. What guarantees can he give my constituents that the works will not extend past the end of the year? How are the costs of the snagging works being met?

Christine Grahame SNP The Deputy Presiding Officer · Midlothian South, Tweeddale and Lauderdale
link

Well—

Murdo Fraser Con Mid Scotland and Fife
link

Are they part of the contract, or are they additional costs to the taxpayer—

Christine Grahame SNP The Deputy Presiding Officer · Midlothian South, Tweeddale and Lauderdale
link

Get a move on with it, Mr Fraser.

Michael Matheson SNP The Cabinet Secretary for Transport, Infrastructure and Connectivity · Falkirk West
link

The costs of the snagging works are met by the contractor. I am sure that Murdo Fraser will recognise the significant benefit that has been gained from the opening of the Queensferry crossing. Over the two years, there have been at least 34 occasions when the Queensferry crossing was able to continue to operate but the Forth road bridge would have been closed to high-sided vehicles. I am sure that he welcomes the additional resilience factor that has been provided to his constituents and those beyond his region in being able to cross the Forth during adverse weather.

Murdo Fraser will also be aware that the traffic management that is deployed for the work that is undertaken by operatives cannot commence before 8 o’clock in the evening; even then, it can be delayed if the evening peak continues for an extended period. There have been instances when the traffic management system has not been engaged until 10 o’clock at night in order to allow traffic flows to reduce. I am sure that he will recognise that, in big infrastructure projects, there will always be snagging work that should be undertaken after the infrastructure is in use. He will also recognise that we have to appreciate the health and safety needs of those who operate on the bridge and put in place appropriate measures to consider their welfare while that work is being completed. That is why the traffic management system is required.

Motions, questions and votes

Linked from this item of the Official Report
  1. Rural Economy Questions · 1
  2. Convergence Funding Allocation Questions · 4
  3. Convergence Funding Questions · 9
  4. Farm Payments (Land Parcel Identification System) Questions · 4
  5. Local Authority Services (Rural Economy) Questions · 7
  6. Food and Drink Sector (Glasgow) Questions · 8
  7. Tree Diseases and Pests Questions · 4
  8. Farm Tenancies Questions · 6
  9. Broadband Connectivity (Stirling) Questions · 6
  10. Road Improvements (A92 at Glenrothes) Questions · 4
  11. Queensferry Crossing (Snagging Works) Questions · 7
  12. Bus Usage Questions · 6
  13. Congestion (Edinburgh) Questions · 6
  14. Dundee Northern Relief Road (Cost Benefit Analysis) Questions · 4
  15. ScotRail (Customer Satisfaction Targets) Questions · 7
  16. Rail Electrification (Kilmarnock to Glasgow) Questions · 5
  17. Nursery Funding (Deferred Entry to Primary School) Debate · 37
  18. ScotRail Franchise Debate · 45
  19. Business Motion Business motions · 1
  20. Parliamentary Bureau Motions Business motions · 2
  21. Decision Time Decision time · 14
  22. Scottish Women and Girls in Sport Week Members’ business · 21

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.