Cockenzie Site (Planning Application)

Topical Question Time

Tuesday 17 April 2018 Meeting of the Parliament Questions 8 contributions · 2 speakers Watch on Scottish Parliament TV

Speakers

Choose an MSP to read only their contributions

The record

8 contributions
Iain Gray Lab East Lothian
link

To ask the Scottish Government for what reason it has called in the planning application for a substation on the site of the former Cockenzie power station. (S5T-01023)

Kevin Stewart SNP The Minister for Local Government and Housing · Aberdeen Central
link

As planning minister, I called in the application as it clearly raises issues of national importance. The Cockenzie power station site is a strategic site in national planning framework 3, which was published in 2014. The framework recognises Cockenzie as an important hub with significant opportunities for renewable energy-related investment and it identifies two national developments relating to the site. The framework states that Cockenzie is part of the high-voltage energy transmission network, which is listed as a national development.

Consent and associated marine licences were granted in 2014 for the Inchcape offshore wind farm and a grid connection agreement is in place to connect it to the Cockenzie site. The planning application is in relation to the electricity substation that is required to make that connection. There is a deadline in quarter 1 of 2019 for a bid for United Kingdom funding for the Inchcape development through the contracts for difference process. To be eligible, all permissions and consents must be in place. Calling in the planning application gives a greater chance of a timely decision ahead of the funding deadline. The reporter will consider local views including the local development plan, and the calling in of the application does not predetermine the outcome of the planning process.

Iain Gray Lab East Lothian
link

The site is of strategic importance all right; it is the biggest opportunity for economic development and job creation in local living memory. The proposed substation is right on the waterfront and could jeopardise the potential development of the site as a port. Its future should be decided locally by local councillors who understand that potential and who are accountable to local people. That is what happened in 2014, when planning permission for the same substation, on a different part of the site, was granted by East Lothian Council. A local decision was okay in 2014; why does the minister think that he knows better this time?

Kevin Stewart SNP The Minister for Local Government and Housing · Aberdeen Central
link

As I said in my first answer to Mr Gray, there is an issue here of potential national significance. The Government recognises the importance of local decision making and we use call-in powers sparingly. On this occasion, we decided to call in.

The reporter from the planning and environmental appeals division will ensure that the community is given the appropriate time to consider and comment on the application, so that community views are taken into account prior to the reporter making a recommendation to me, as minister.

Iain Gray Lab East Lothian
link

The other issue here, of course, is that in 2016 this project was bought by Red Rock Power, a company that is owned by the Chinese State Development and Investment Corporation, which the First Minister was meeting last week at the very moment when the planning decision was called in. Can the minister understand that it looks to my constituents as if he is prepared to ride roughshod over their interests and aspirations, to protect the interests and aspirations of a Chinese-backed project that will create not one job in East Lothian? If he wants to convince my constituents otherwise, will he do that now, by returning this decision to East Lothian Council, where it belongs?

Kevin Stewart SNP The Minister for Local Government and Housing · Aberdeen Central
link

As Mr Gray is well aware, I made the decision to call in on 4 April, and that was related to East Lothian Council on 9 April, before the First Minister was in China—

Kevin Stewart SNP The Minister for Local Government and Housing · Aberdeen Central
link

We have been absolutely clear that there was no connection whatever to the First Minister’s visit to China.

Consideration of planning cases is focused on the merits of the case. The identity of the applicant is not a planning consideration that is relevant to the assessment of any application.

Motions, questions and votes

Linked from this item of the Official Report
  1. Time for Reflection Time for reflection · 2
  2. Business Motion Business motions · 1
  3. Pinneys of Scotland Questions · 10
  4. Cockenzie Site (Planning Application) Questions · 8
  5. 2 Sisters Factory (Closure) Questions · 8
  6. NHS Tayside Statement · 26
  7. Air Quality Debate · 38
  8. Burntisland Fabrications Statement · 29
  9. Decision Time Decision time · 1
  10. Aberdeen Trades Union Council Members’ business · 7

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.