Aberdeen Western Peripheral Route

Topical Question Time

Tuesday 23 October 2012 Meeting of the Parliament Questions 22 contributions · 10 speakers Watch on Scottish Parliament TV

Speakers

Choose an MSP to read only their contributions

The record

22 contributions
Maureen Watt SNP Aberdeen South and North Kincardine
link


2. To ask the Scottish Government what steps it is taking to expedite the building of the Aberdeen western peripheral route following the Supreme Court’s final rejection of the legal protests that have delayed the project. (S4T-00078)

Keith Brown SNP The Minister for Transport and Veteran Affairs · Clackmannanshire and Dunblane
link
We are already expediting the delivery of this vital project for the north-east. During the legal challenges, we ensured that as much preparatory work as possible was progressed so that we were in a position to move immediately following the United Kingdom Supreme Court judgment last week. The prior information notice signalling the start of procurement was published only two days after the judgment, on 19 October. Further works will begin next month—drilling rigs are on site to carry out vital ground investigations. Over the next year, there will be more advance works to clear the site ahead of the main works, which are expected to get under way in 2014 and to be completed by the spring of 2018.

Maureen Watt SNP Aberdeen South and North Kincardine
link
The minister has already agreed that there should be community benefit clauses in the contracts that guarantee opportunities for apprentices and the long-term unemployed. I hope that there will be work with the universities to give trainee civil engineers and surveyors practical experience. Will the minister also work with the Cabinet Secretary for Rural Affairs and the Environment to urge farmers to use recycled stones lying at the sides of their fields in the construction process so that we can regain some agricultural land, which is being lost at a phenomenal rate to house building?

Keith Brown SNP The Minister for Transport and Veteran Affairs · Clackmannanshire and Dunblane
link
I have assured the member that we will raise that issue with the procurement team for the project. Any development that ensures that materials do not have to be transported, helps the environment and means that we do not need to buy further materials but can use local materials instead will be good for the project. I have therefore given an undertaking to the member that I will take up the issue with officials to see what we can take forward. I give the member the commitment that I will work closely with the Cabinet Secretary for Rural Affairs and the Environment to see what we can do in that area.

Maureen Watt SNP Aberdeen South and North Kincardine
link
Can the minister give us any idea of what savings will be made by combining the AWPR project with the Balmedie to Tipperty project?

Keith Brown SNP The Minister for Transport and Veteran Affairs · Clackmannanshire and Dunblane
link
We were sure of the savings that we would have made had we been able to proceed with the project when we wanted to some years ago. However, officials are currently working on the cost of the project and therefore the savings that would be arrived at by bundling those two projects together. I intend to produce that information for the Parliament as soon as possible.

Tricia Marwick The Presiding Officer · Mid Fife and Glenrothes
link
Many members want to ask supplementaries, so I urge them to be as brief as possible.

Richard Baker Lab North East Scotland
link
The minister has indicated that the AWPR will be complete in 2018. What impact will that have on improvements at the Haudagain roundabout, which ministers have linked to completion of the work on the AWPR? Can the minister give a completion date for that linked project?

Keith Brown SNP The Minister for Transport and Veteran Affairs · Clackmannanshire and Dunblane
link
It is not just ministers who have linked the programme; Aberdeen City Council has also said that the AWPR and the third Don crossing require to be in place in order to meet the transport planning objectives for the Haudagain roundabout. It is also worth saying that we have already committed £3 million towards the design work for the Haudagain roundabout. We now have to get on with the AWPR.

It would be interesting to know from Richard Baker—if possible—whether he intends to continue to support the project or to start to cast it into doubt, as his colleague Elaine Murray has done with the Forth road crossing, which she now says she has had second thoughts about. We really should have continuity on that from the Labour Party.

Brian Adam SNP . · Aberdeen Donside
link
I very much welcome the decision of the courts in recent weeks. Can the minister confirm that the Haudagain redevelopment and the third Don crossing works will be included in the AWPR contract? Can he give us some idea of when the individual elements of what is a package are likely to happen?

Keith Brown SNP The Minister for Transport and Veteran Affairs · Clackmannanshire and Dunblane
link
It is worth saying that, over 30 years, the project will support 14,000 jobs in the north-east of Scotland and create £6.3 billion of additional income, so it will have a massive impact.

As I said in relation to the Haudagain roundabout, it has always been our position that the Balmedie to Tipperty and AWPR projects should proceed first before we can accrue the benefits from the Haudagain roundabout and, obviously, we await legal proceedings in relation to the third Don crossing. I assure the member that we will crack on with the project as soon as we can and that we intend to see the benefits accrue to the north-east as soon as possible.

Alex Johnstone Con North East Scotland
link
Given that the minister has made it clear that other road development projects in the north-east will be included as part of the AWPR development, has he given any further consideration to the option of including the A90-A937 junction at Laurencekirk as part of the AWPR contract?

Keith Brown SNP The Minister for Transport and Veteran Affairs · Clackmannanshire and Dunblane
link
There is no update to provide in relation to Alex Johnstone’s question since the last time that he asked it. We do not intend to include that junction in the bundle for the AWPR.

Kevin Stewart SNP Aberdeen Central
link
Can the minister outline any discussions that he has had with Aberdeen City Council with regard to its responsibilities for the construction of the third Don crossing, which would complete the holy trinity of vital roads projects to keep Aberdeen moving?

Keith Brown SNP The Minister for Transport and Veteran Affairs · Clackmannanshire and Dunblane
link
The member will be aware of the legal constraints on discussion of the matter. There have been discussions between officials at this stage. We very much hope that Aberdeen City Council will share our desire to progress with the project as soon as possible, because we can then see the implementation of the whole suite of transport solutions for Aberdeen and the north-east. We will continue to work with Aberdeen City Council, with which we have developed a very constructive relationship on how the AWPR is paid for and progressed. We hope to continue such co-operation with the council on other projects.

Lewis Macdonald Lab North East Scotland
link
Can the minister confirm that potential private finance partners remain interested in the AWPR under the non-profit-distributing model that the Government has taken forward? In the event that no competitive bids are received, what is the Government’s plan B for financing such a project?

Keith Brown SNP The Minister for Transport and Veteran Affairs · Clackmannanshire and Dunblane
link
As the member would expect, there is a very healthy interest in the market for the project. We have been asked to make as many projects proceed as possible within the resource constraints that we face. I do not expect there to be a lack of competition for the contract. In fact, the opposite seems to be the case. We will have the same huge level of interest that there was in relation to, for example, the M8, which was another NPD project. We are very confident about the level of interest that there will be in the project.

Alison McInnes LD North East Scotland
link
The commitment made many years ago was that the two councils would each fund 9.5 per cent of the cost of the AWPR, minus the fastlink costs. The minister has rolled in the Balmedie to Tipperty project and there is talk of rolling in the third Don crossing. How will it be possible to identify the discrete costs of the AWPR if the contract is let in that way? How can local taxpayers be sure that they are not being asked to pick up part of the tab for the other projects? There needs to be absolute transparency and clarity. What mechanism does the minister propose to use? Has he discussed the matter with the local councils?

Keith Brown SNP The Minister for Transport and Veteran Affairs · Clackmannanshire and Dunblane
link
The mechanism will be one of dialogue. We are talking to the two councils. It is not beyond the wit of the officials and the politicians involved to ensure that we produce the right solution. Discussions have so far been very productive and I am very confident that we will get an agreeable solution.

Patrick Harvie Green Glasgow
link
If the minister is concerned about inconsistency from the other side of the chamber, perhaps he will welcome consistency from the Green Party on the issue. How are we supposed to take remotely seriously any assessment of the costs and benefits of the project when we are still working on an estimate of the cost from almost a decade ago? If he is going to come forward with a revised cost, can he give a clear commitment that he will specify the portion of the revised cost that is about the AWPR specifically and does not relate to the other projects?

Keith Brown SNP The Minister for Transport and Veteran Affairs · Clackmannanshire and Dunblane
link
Yes, I am perfectly willing to give a commitment that the figures that I will produce for Parliament very shortly—as the member will understand, given that the court decision has just been made, they are currently being worked on—will itemise the cost of the two projects. It will also be clear at that time that it makes sense to do the two projects together.

There is no doubt about the benefits. I have mentioned 14,000 jobs. That is a serious issue. The project will support 14,000 jobs in the north-east of our country, there will be £6.3 billion of benefit and there will be huge environmental and safety benefits. This is a very good project and I am delighted that we are getting to grips with it.

Tricia Marwick The Presiding Officer · Mid Fife and Glenrothes
link
I regret that I do not have time to call Nigel Don.

Motions, questions and votes

Linked from this item of the Official Report
  1. Time for Reflection Time for reflection · 2
  2. Business Motion Business motions · 1
  3. Hall’s Meat Processing Plant Questions · 8
  4. Aberdeen Western Peripheral Route Questions · 22
  5. Edinburgh Agreement Statement · 45
  6. Greenhouse Gas Emissions (Annual Target Report) Statement · 36
  7. Role of the Media in Criminal Trials Debate · 41
  8. Parliamentary Bureau Motion Business motions · 3
  9. Presiding Officer’s Ruling Procedure · 9
  10. Decision Time Decision time · 2
  11. 5th Fife Scout Group (Scottish Championship Award) Members’ business · 17

The type of each item (debate, statement, questions, members’ business and so on) and the times shown are worked out by this site from headings, the chair’s opening words and the Official Report’s running timestamps. They are not the Parliament’s own classification. Text: the Scottish Parliament Official Report.