What steps it is taking to ensure that the specifications in the Clyde and Hebrides Ferry Services contract to be directly awarded to CalMac are discussed with the recognised trade unions before 1 October 2025.
Started with S6W-39984 on 19 Aug 2025; latest 23 Sep 2025. Each later question says it follows up an earlier answer.
The thread, in order
Each answer’s opening lines; open a question for the full text-
To ask the Scottish Government what steps it is taking to ensure that the specifications in the Clyde and Hebrides Ferry Services contract to be directly awarded to CalMac are discussed with the recognised trade unions before 1 October 2025.
Fiona Hyslop, 16 Sep 2025: Since the launch of the RMT People’s CalMac Campaign in 2022 we have been engaging with Trade unions on their aspiration for a CHFS3 of Direct Award to CalMac Ferries. The Scottish Government agrees that a Direct Award is the best and most appropriate way forward. The detailed Contract specification will be published … -
In relation to the Clyde and Hebrides Ferry Services 3 (CHFS3) contract, whether (a) detailed specification of the contract will be published on the Transport Scotland website before 1 October 2025, and (b) it will instruct CalMac to share a copy of the contract with the recognised trades unions as soon as possible.
Fiona Hyslop, 1 Oct 2025: The grant agreement containing the full CHFS3 specification has been published on the Transport Scotland website and we have intimated this by letter to unions amongst other bodies and welcome the positive statements made at publication by union representatives. -
In relation to the Clyde and Hebrides Ferry Services 3 (CHFS3) contract, what discussions of the detailed specifications of the contract Transport Scotland officials have had with the (a) the Chair of the Ferries Community Board, (b) local authorities and (c) CMAL since 8 March 2025, and what the outcome was.
Fiona Hyslop, 1 Oct 2025: Since 8 March 2025, Transport Scotland have continued to engage with the Ferries Community Board, both in relation to performance management of the new contract, and also the nature of their ongoing role post-award. This was invaluable to inform the suite of performance indicators, and the role of the Ferries Communit…
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.