Whether it will provide a breakdown of the number of buses ordered to date under the second phase of the Scottish Zero Emission Bus Challenge Fund (ScotZEB 2) by (a) manufacturer and (b) place of manufacture.
Started with S6W-38726 on 13 Jun 2025; latest 5 Jul 2025. Each later question says it follows up an earlier answer.
The thread, in order
Each answer’s opening lines; open a question for the full text-
To ask the Scottish Government whether it will provide a breakdown of the number of buses ordered to date under the second phase of the Scottish Zero Emission Bus Challenge Fund (ScotZEB 2) by (a) manufacturer and (b) place of manufacture.
Jim Fairlie, 3 Jul 2025: Through the second phase of the Scottish Zero Emission Bus Challenge Fund (ScotZEB) a consortium of companies was awarded £41.7 million capital from the Scottish Government to support the purchase of more than 250 vehicles and the installation of their supporting infrastructure.ScotZEB 2 differs from previous rounds o… -
And regarding the value of subsidies, what the (a) average value per vehicle and (b) total value for each bus manufacturer has been, for each phase of the Scottish Zero Emission Bus Challenge Fund.
Jim Fairlie, 29 Jul 2025: Through ScotZEB 1, the average subsidy per vehicle, excluding infrastructure was £176,000. Through ScotZEB 2, the average subsidy per vehicle, excluding infrastructure is £108,000. ScotZEB 2 is still a live project in its delivery phase, and consortium membership and vehicle numbers may be subject to change. Both phas… -
In which he stated that “the Scottish Government does not collect data on the locations in which vehicles are manufactured”, how it monitors and assesses the level and impact of social value of the Scottish Zero Emission Bus Challenge Fund in the absence of such data.
Jim Fairlie, 29 Jul 2025: The social value of the Scottish Zero Emission Bus Challenge Fund arises in several ways, including through the reduction in greenhouse gas emissions from the bus sector by accelerating the uptake of zero emission buses and coaches as part of wider activity to address the climate emergency.In addition, Wider community…
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.