Parliament Workbench

Question thread · 3 questions

When the contract with EDF as part of Scotland's national electricity supply framework arrangements expires, and what provision exists for the terms of the contract to be varied before expiry.

Started with S6W-29944 on 16 Sep 2024; latest 7 Nov 2024. Each later question says it follows up an earlier answer.

Follow-ups
2
longest chain 1 step
Span
52 days
16 Sep 2024 to 7 Nov 2024
Answered
3 of 3
by Ivan McKee
Asked by
1
Sarah Boyack

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S6W-29944 16 Sep 2024 Sarah Boyack Lab Answered

    To ask the Scottish Government when the contract with EDF as part of Scotland's national electricity supply framework arrangements expires, and what provision exists for the terms of the contract to be varied before expiry.

    Ivan McKee, 24 Sep 2024: The National Electricity Supply expires on 31 March 2026, the framework has 3 optional 12 month extensions.Variations to the framework can be made, however these must be in accordance with procurement law and be non-material changes and in agreement with the Supplier.
  2. S6W-31128 7 Nov 2024 Sarah Boyack Lab Answered

    Whether it will be exercising its first 12-month extension to the existing National Electricity Supply Contract.

    Ivan McKee, 18 Nov 2024: A decision on exercising the first extension is still to be made, once this decision has been reached then the supplier will be informed.
  3. S6W-31129 7 Nov 2024 Sarah Boyack Lab Answered follows S6W-29944

    Whether it is possible to amend the current National Electricity Supply Contract to include provision for clients to reduce their demand for electricity from the single supplier within the framework, if they choose to buy locally produced renewable electricity, in order to further community wealth building.

    Ivan McKee, 18 Nov 2024: As part of the framework process, in the run up to the start of every financial year, the supplier works with each individual customer to determine their estimated consumption for the next financial year. If the volume is going to decrease or increase the supplier will work with the Scottish Procurement team to reshap…

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.

All question threads