Question thread · 3 questions
Regarding the Level 4 tables in its 2024-25 Budget, whether it will outline what the potential impact will be of the 33.9% reduction to grants, loans and capital for vessels and piers on (a) its contract with Ferguson M…
Started with S6W-24320 on 22 Dec 2023; latest 1 Feb 2024. Each later question says it follows up an earlier answer.
The thread, in order
Each answer’s opening lines; open a question for the full text-
To ask the Scottish Government, regarding the Level 4 tables in its 2024-25 Budget, whether it will outline what the potential impact will be of the 33.9% reduction to grants, loans and capital for vessels and piers on (a) its contract with Ferguson Marine for the Glen Sannox and Glen Rosa ferries and (b) the business case for upgrading Ardrossan Harbour.
Neil Gray, 19 Jan 2024: The level of funding set out in the Scottish Budget reflects that the delivery of Glen Sannox (801) is now at an advanced stage. The costs and delivery schedules of both 801 and 802 continue to be scrutinised closely, with updates provided regularly to the Scottish Parliament. The business case and cost review exercis… -
What the most recent (a) total cost is of the contract for Hull (i) 801 and (ii) 802 and (b) projected operational date is for Hull 801.
Mairi McAllan, 19 Feb 2024: The Chief Executive of Ferguson Marine provided the most recent costs for completion of the vessels to the Net Zero, Energy and Transport Committee in September 2023. The Chief Executive also informed the NZET Committee in January that the estimated total cost to complete both vessels was being reviewed and the outcom… -
On what date it anticipates that it will report the outcomes from the business case and cost review exercise for upgrading Ardrossan Harbour.
Fiona Hyslop, 21 Feb 2024: I wrote to the Ardrossan Task Force on the 27 November 2023 to advise that the business case and cost review exercise for the Ardrossan Harbour project is currently being progressed. Transport Scotland and our project partners continue to make progress in the development of the business case and the updated cost estim…
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.