How many public buildings it has inspected since the start of 2021 to determine whether they were constructed with reinforced autoclaved aerated concrete (RAAC), broken down by building type, and how many of these were …

Started with S6W-18315 on 23 May 2023; latest 7 Jun 2023. Each later question says it follows up an earlier answer.

Follow-ups
2
longest chain 1 step
Span
15 days
23 May 2023 to 7 Jun 2023
Answered
3 of 3
by Shona Robison
Asked by
1
Craig Hoy

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S6W-18315 23 May 2023 Craig Hoy Con Answered

    To ask the Scottish Government how many public buildings it has inspected since the start of 2021 to determine whether they were constructed with reinforced autoclaved aerated concrete (RAAC), broken down by building type, and how many of these were confirmed to have been constructed with RAAC.

    Shona Robison, 7 Jun 2023: The Scottish Government has not undertaken an inspection for reinforced autoclaved aerated concrete (RAAC) in the Core SG Estate since 2021. A specialist has been appointed to develop a scope for inspection surveys. The Core Estate is defined as those sites/buildings where SG Directorates operate from.
  2. S6W-19022 7 Jun 2023 Craig Hoy Con Answered

    By what date its appointed specialist will have developed the scope for inspection surveys.

    Shona Robison, 26 Jun 2023: Scottish Government have recently appointed professional experts to prepare a scope for future surveys. Final security checks are currently being completed and thereafter it is anticipated that the 6 week programme to develop a scope will be completed by September 2023.
  3. S6W-19021 7 Jun 2023 Craig Hoy Con Answered follows S6W-18315

    When it anticipates that inspection surveys will (a) begin and (b) finish.

    Shona Robison, 26 Jun 2023: Scottish Government has recently appointed an external professional advisor to provide guidance on the scope of building condition surveys required for Scottish Government buildings. It anticipates receiving details of the scope within approximately 8-10 weeks, surveys will be instructed immediately thereafter and in …

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.

All question threads