What reviews have taken place to ensure that the NHSScotland Design Assessment Process (NDAP) action plan for The Baird Family Hospital and The ANCHOR Centre Project, which was undertaken in 2019, has been completed.

Started with S6W-15479 on 28 Feb 2023; latest 23 Mar 2023. Each later question says it follows up an earlier answer.

Follow-ups
2
longest chain 1 step
Span
23 days
28 Feb 2023 to 23 Mar 2023
Answered
3 of 3
by Michael Matheson, Humza Yousaf
Asked by
1
Alexander Burnett

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S6W-15479 28 Feb 2023 Alexander Burnett Con Answered

    To ask the Scottish Government what reviews have taken place to ensure that the NHSScotland Design Assessment Process (NDAP) action plan for The Baird Family Hospital and The ANCHOR Centre Project, which was undertaken in 2019, has been completed.

    Humza Yousaf, 16 Mar 2023: The NDAP process does not use the term, or produce an ‘action plan’. The process results in essential and advisory recommendations at the end of each of each Business Case stage which must be developed by the Board. The Board will submit evidence or a commitment to address the recommendations prior to their NDAP repor…
  2. S6W-16179 23 Mar 2023 Alexander Burnett Con Answered

    For what reason client changes are being introduced for The Baird Family Hospital and The ANCHOR Centre at this stage in the build process and were not introduced at an earlier stage.

    Michael Matheson, 17 Apr 2023: All projects are subject to ongoing review and consideration. It is for NHS Grampian’s project team, in discussion with the contractor, to determine whether any client changes are actioned.
  3. S6W-16178 23 Mar 2023 Alexander Burnett Con Answered follows S6W-15479

    What updated assurance processes are now required for The Baird Family Hospital and The ANCHOR Centre, and for what reason this is being introduced at this stage in the build process and was not introduced at an earlier stage.

    Michael Matheson, 17 Apr 2023: As set out in the response to S6W-15482 on 16 March 2023, all projects are subject to review by NHS Scotland Assure prior to opening. The Key Stage Assurance Review (KSAR) process examines projects at key points in their lifecycle. It does not remove any legal or contractual obligations from the NHS Health Board, thei…

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.