In light of the reference to its announcement of an additional £200 million of funding on page 11 of the Scotland's Railway July 2022 publication, Enhancements Delivery Plan, when it anticipates it will have distributed…

Started with S6W-12917 on 2 Dec 2022; latest 13 Jan 2025. Each later question says it follows up an earlier answer.

Follow-ups
2
longest chain 1 step
Span
773 days
2 Dec 2022 to 13 Jan 2025
Answered
3 of 3
by Fiona Hyslop, Jenny Gilruth
Asked by
1
Liam Kerr

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S6W-12917 2 Dec 2022 Liam Kerr Con Answered

    To ask the Scottish Government, in light of the reference to its announcement of an additional £200 million of funding on page 11 of the Scotland's Railway July 2022 publication, Enhancements Delivery Plan, when it anticipates it will have distributed all of this funding, and whether it will provide details of exactly what the funding will be spent on.

    Jenny Gilruth, 21 Dec 2022: The Scottish Government is planning to deliver the identified Aberdeen to Central Belt funding by the end of 2026. The funding will be spent on a series of infrastructure upgrades including signal enhancements and specific capacity alternations to facilitate the operation of more and faster trains on the same route.
  2. S6W-24344 3 Jan 2024 Liam Kerr Con Answered

    Whether it has now finalised what the £200 million of funding on page 11 of the Scotland's Railway July 2022 publication, Enhancements Delivery Plan, will be spent on, and by when, and, if not, when it anticipates it will.

    Fiona Hyslop, 30 Jan 2024: The Scottish Government is continuing to develop the business case for the Aberdeen to Central Belt Enhancements project. This will be considered in in the coming months and within the context of the funding available for rail enhancements. We remain firmly committed to infrastructure investment as a key factor in sec…
  3. S6W-33246 13 Jan 2025 Liam Kerr Con Answered follows S6W-12917 also cites S6W-12918

    What progress it is making with delivering each of the "Transport Scotland Required Outputs" listed on page 11 of the Scotland's Railway July 2022 publication, Enhancements Delivery Plan.

    Fiona Hyslop, 28 Jan 2025: I refer the member to the answer to the question S6W-32369 on 8 January 2025. All answers to written Parliamentary Questions are available on the Parliament’s website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.