Whether it will confirm when actions to remove cladding from properties identified as dangerous under the Single Building Assessment programme will be completed.

Started with S6O-01324 on 30 Aug 2022; latest 23 Jan 2023. Each later question says it follows up an earlier answer.

Follow-ups
1
longest chain 1 step
Span
146 days
30 Aug 2022 to 23 Jan 2023
Answered
1 of 2
by Shona Robison
Asked by
2
MSPs

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S6O-01324 30 Aug 2022 Kaukab Stewart SNP Oral

    To ask the Scottish Government whether it will confirm when actions to remove cladding from properties identified as dangerous under the Single Building Assessment programme will be completed.

    Oral · 7 Sep 2022
  2. S6W-14277 23 Jan 2023 Mark Griffin Lab Answered

    What evidence it used to substantiate the statement that “we expect the vast majority of buildings that will be assessed to be found to be safe” prior to any form of building assessment for combustible cladding materials.

    Shona Robison, 7 Feb 2023: Buildings within the scope of the Cladding Remediation Programme will be subject to a process of increasing assessment scrutiny. A baseline assessment will identify those buildings which require a full assessment based on an evaluation of fire risk. The proportion of buildings identified as requiring a full assessment…

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.

All question threads