What assurances it can provide that ordnance clearances taking place as part of the Seagreen Offshore Wind Farm project are not high order detonations.

Started with S6W-03602 on 7 Oct 2021; latest 19 Jan 2022. Each later question says it follows up an earlier answer.

Follow-ups
2
longest chain 2 steps
Span
104 days
7 Oct 2021 to 19 Jan 2022
Answered
3 of 3
by Michael Matheson
Asked by
1
Beatrice Wishart

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S6W-03602 7 Oct 2021 Beatrice Wishart LD Answered

    To ask the Scottish Government what assurances it can provide that ordnance clearances taking place as part of the Seagreen Offshore Wind Farm project are not high order detonations.

    Michael Matheson, 25 Oct 2021: The marine and European Protected Species licences issued to Seagreen Wind Energy Limited (SWEL) in respect of unexploded ordnance (UXO) clearance activities were conditioned such that high order detonation techniques for UXO clearance are used only when it is not possible to undertake UXO clearance using low yield or…
  2. S6W-05332 19 Dec 2021 Beatrice Wishart LD Answered

    Whether it will publish the written report by Seagreen Wind Energy Limited in respect of unexploded ordnance clearance activities.

    Michael Matheson, 10 Jan 2022: Marine Scotland – Licensing Operations Team (“MS-LOT”) intends to publish the written report by Seagreen Wind Energy Limited in respect of unexploded ordnance clearance activities on its website (marine.gov.scot) once the internal review of the report is complete.
  3. S6W-05817 19 Jan 2022 Beatrice Wishart LD Answered

    What the timeframe is for publishing the report by Seagreen Wind Energy Limited in respect of unexploded ordnance clearance activities.

    Michael Matheson, 31 Jan 2022: Marine Scotland – Licensing Operations Team (“MS-LOT”) has recently received the written report from Seagreen Wind Energy Limited in respect of unexploded ordnance clearance activities. MS-LOT is currently conducting a review of the report and will publish on its website (marine.gov.scot) once this review is complete.

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.

All question threads